Campus Parkway Interchange (Exit 210)

The project included widening the Campus Parkway bridge over I-69 and reconfiguring the Campus Parkway interchange (Exit 210) into a double-crossover diamond design to improve traffic flow. Similar interchanges have been constructed at I-69 and SR 1 (Dupont Road) in Allen County and at I-65 and Worthsville Road in Johnson County.

The Campus Parkway double-crossover diamond interchange traffic pattern was opened on May 17, 2017.

How to Navigate a Double-Crossover Diamond Interchange

Campus Parkway Construction Phasing

  • Phase 1 - Completed in Spring 2017
  • Phase 2 - Shift to Double Crossover Diamond Completed Spring 2017
  • Phase 3- Completed in Summer 2017
  • Phase 4 - Completed in Summer 2017
  • Phase 5 - Completed in Summer 2017
  • Phase 6 - Completed in Summer 2017
    • Click on image to enlarge     

                  

Stay Informed

Follow @INDOTEast on Twitter and like us on Facebook at INDOTEastCentral. Join the conversation using the hashtag #I69MM2020

Email Updates from GovDelivery
To sign up for INDOT updates or to access your subscriber preferences, please enter your contact information below.

News and FAQs

INDOT Events

Click here to view more events

Top FAQs