Header

  Close Menu
INDOT: Superseded and Discontinued Construction Memorandums

Article

Construction Memorandums
Superseded and Discontinued

Superseded and Discontinued Construction Memorandums

Issued
Subject
Number
02/01/24
E5 Internal Cure and E5 Liquid Fly Ash in Concrete (rev. 05/15/24) *Supersedes 23-01* **Superseded by 25-02**
24-03
07/07/23
E-Ticketing Incentive *Discontinued*
23-08
03/13/23
E5 Internal Cure and E5 Liquid Fly Ash in Concrete *Superseded by 24-03*
23-01
10/26/22
Infrastructure Investment and Jobs Act - Build America, Buy America *Superseded by 24-02*
22-09
05/12/22
Alternate Overlay Mix Design Using E5 Internal Cure and E5 Liquid Fly Ash
*Superseded by 23-01*
22-04
04/04/22
Alternate Curing Method for Structural Concrete using E5 Internal Cure and E5 Liquid Fly Ash
*Superseded by 23-01*
22-02
03/10/22
IRI Implementation for CY 2022 *Superseded by 23-04*
22-01
03/18/21
Submittals and Weigh Tickets during COVID-19 *Superseded by 22-03*
Load Tracking Log (.xls)
21-08
02/26/21
Alternate Curing Method for Structural Concrete Using E5 Internal Cure *Superseded by 22-02*
21-05
01/28/21
Buy America Certification Supplemental Information *Superseded by 24-10*
21-03
01/28/21
IRI Implementation for CY 2021 *Superseded by 22-01*
21-02
04/17/20
Buy America Requirement Clarification Supplemental Instructions *Superseded by 24-10*
20-06
04/09/20
Submittals and Weigh Tickets During COVID-19 *Superseded by 21-08*
20-05
03/16/20
QC/QA Hot Mix Asphalt 2020 Specification changes
20-04
03/03/20
Buy America Certification *Superseded by 24-10*
20-03
01/22/20
IRI Pilot Contracts for CY 2020 *Superseded by 21-02*
20-02
12/17/19
Notice of Termination, NOT *Superseded by 23-07*
19-10
02/21/19
QC/QA Hot Mix Asphalt 2019 Specification Changes (rev. 03/01/19)
19-03
02/07/19
Implementation of the Electronic Constructability Review Forms (ECRF) *Superseded by 23-06*
19-01
11/26/18
Determining Construction Equipment Costs *Superseded by 24-07*
18-06
06/11/18
Maintenance of Impact Attenuator & Guardrail End Treatments *Superseded by 20-01*
18-04
01/31/18
QC/QA Hot Mix Asphalt Test Strips and Aggregate Gsb Determination
18-01
11/28/17
Use of the Law Enforcement Officer for Work Zone Safety *Superseded by 21-06*
17-17
11/28/17
Change Order Extra Work Cost Verification Procedure *Superseded by 24-11*
17-16
11/28/17
Revised Item Bid History Spreadsheet for Use with New Items of Extra Work *Superseded by 24-11*
17-15
09/20/17
LPA and State Shop Drawing and Falsework Review Procedures *Superseded by 20-10*
17-14
08/07/17
Alternate to Concrete Sealers Unique Special Provision *Discontinued on 2/1/2018*
17-12
06/09/17
Electronic Payroll Submission by Contractors *Superseded by 19-07*
17-11
03/31/17
QC/QA Hot Mix Asphalt Test Result Appeals
17-06
03/13/17
Buy America Requirement for Utilities *Discontinued* See Memo 24-10
17-04
02/22/17
Acceptance method for Hot Pour Joint Sealant
17-02
01/19/17
Notice of Termination (NOT) *Superseded by 19-10*
17-01
10/13/16
The New EquipmentWatch Website *Superseded by 24-07*
16-11
06/10/16
Unique Special Provision for FALSEWORK REMOVAL/Revisions to Section 702 *Discontinued*
16-06
06/03/16
Implementation of the Contractor Performance Evaluation (CPE) system *Superseded by 21-10*
16-05
01/28/16
Notice of Termination, NOT *Discontinued* See Memo 17-01
16-02
08/19/15
Binder Deficiency Adjustment
15-15
08/14/15
FHWA PY 2016 PODI List for Change Order Approval *Superseded by 20-11*
15-14
05/30/14
The Removal of FHWA Change Order Approvals from Select Construction Contracts *Superseded by 15-14*
14-07
04/22/14
Change Orders on Construction Contracts Policy *Superseded by 22-08*
14-05
01/30/14
Notice of Termination (NOT) *Superseded by 17-01*
14-02
11/07/13
LPA and State Shop Drawing and Falsework Review Procedures *Superseded by 17-14*
13-13
08/30/13
N.O.T. Erosion and Sediment Control Inspections and Reports *Discontinued*
13-09
07/17/13
Transverse Corrugations in Sidewalk Curb Ramps *Discontinued*
13-07
05/01/13
Notice of Termination (NOT) *Superseded by 14-02*
13-04
04/30/12
12-06
12/05/11
11-11
07/01/11
11-05
03/03/11
11-02
06/09/10
10-07
02/03/10
10-02
01/04/10
New Change Order Policy *Superseded by 14-05*
10-01
11/30/09
Project Commitments Database *Superseded by 10-05*
09-22
11/16/09
M-39 & Contract Closeout *Superseded by 14-03*
09-21
06/11/09
09-13
05/06/09
09-12
04/30/09
Active Commitments Report *Superseded by 09-22*
09-11
04/29/09
Overruns on ARRA Contracts *Superseded by 09-14*
09-10
03/30/09
Construction Zone Impact Attenuators *Discontinued on 6/5/2015*
09-09
03/25/09
09-07
02/23/09
PCCP Cost Savings Measures *Discontinued*
09-06
02/23/09
HMA Cost Savings Measures *Discontinued*
09-05
02/06/09
09-03
01/08/09
09-01
12/02/08
Construction Zone Impact Attenuators *Discontinued on 6/5/2015*
08-15
08/14/08
08-11
05/29/08
08-08
04/24/08
08-05
02/11/08
08-04
01/28/08
08-02
12/18/07
Unit Price Justification for Extra Work *Superseded by 17-15 and 17-16*
07-28
12/17/07
HMA Revisions for 2008 *Discontinued*
07-27
07/23/07
07-18
05/14/07
07-10
03/26/07
07-06
01/24/07
07-03
01/24/07
07-02
12/14/06
06-25
08/23/06
Policy for Use of Temporary Worksite Speed Limit Assembly Signs *Discontinued* See Memo 14-06
06-22
07/17/06
06-20
06/13/06
06-18
04/12/06
06-08
04/03/06
06-05
03/24/06
Concrete Mix Designs for 2006 *Discontinued*
06-03
08/24/05
Specification Section 306 Milling *Discontinued*
05-13
06/13/05
05-11
06/24/05
05-10
05/25/05
Change Order Procedures *Superseded by 06-18*
05-09
04/21/05
05-07
03/29/05
05-06
03/29/05
05-04
03/05/05
Change Orders *Superseded by 06-18*
05-02
09/23/04
04-12
06/08/04
04-09
05/21/04
04-08
03/22/04
Standard Specifications Section 213, Flowable Backfill *Discontinued*
04-04
03/30/04
04-03
03/03/04
04-02
02/23/04
04-01
12/19/03
03-16
05/06/03
03-06
05/05/03
03-05
01/29/03
03-02
07/10/02
02-11
07/02/02
02-10
06/21/02
02-08
05/29/02
2002 SMA Specifications *Discontinued*
02-05
04/19/02
02-03
10/17/01
Clarification of Field Office Specification 105.17 *Discontinued*
01-13
07/11/01
01-08
06/25/01
Bridge Paint Specification Changes *Discontinued*
01-07
05/30/01
01-05
04/05/01
Clarification of Specification 105.17 (Field Office) *Discontinued*
01-03
01/02/01
01-01
12/14/00
Time Extensions *Superseded by 06-18*
00-19
06/20/00
00-13
05/24/00
Bridge Painting Subcontractors *Discontinued*
00-11
03/31/00
00-10
03/31/00
00-09
03/31/00
HMA Roller *Discontinued*
00-08
03/06/00
00-05
03/01/00
00-03
02/04/00
Guidelines for Transportation Enhancement Projects *Discontinued*
00-02
08/31/99
Field Office Computers - Y2K - *Discontinued*
99-10
08/12/99
Ignition Oven for HMA Mixture with Dolomite *Discontinued*
99-09
04/23/99
99-06
04/23/99
99-05
04/09/99
99-04
03/30/99
99-03
03/22/99
400 Spec Section of the Standard Specification *Discontinued*
99-02
03/01/99
99-01

News and FAQs

INDOT Events

Click here to view more events

Top FAQs