Article
Superseded and Discontinued Construction Memorandums
Issued |
Subject |
Number |
05/12/22 |
Alternate Overlay Mix Design Using E5 Internal Cure and E5 Liquid Fly Ash (rev. 10/04/22) *Superseded by Memo 23-01* | 22-04 (Revised) |
04/04/22 |
Alternate Curing Method for Structural Concrete using E5 Internal Cure and E5 Liquid Fly Ash (rev. 06/14/22), (rev. 08/30/22), (rev. 09/22/22) *Superseded by Memo 23-01* | 22-02 (Revised) |
03/10/22 |
IRI Implementation for CY 2022 *Superseded by Memo 23-04* | 22-01 |
03/18/21 |
Submittals and Weigh Tickets during COVID-19 *Superseded by Memo 22-03*
Load Tracking Log (.xls) |
21-08 |
02/26/21 |
Alternate Curing Method for Structural Concrete Using E5 Internal Cure *Superseded by Memo 22-02* | 21-05 |
01/28/21 |
IRI Implementation for CY 2021 *Superseded by Memo 22-01* | 21-02 |
04/09/20 |
Submittals and Weigh Tickets During COVID-19 *Superseded by Memo 21-08* | 20-05 |
01/22/20 |
IRI Pilot Contracts for CY 2020 *Superseded by Memo 21-02* | 20-02 |
06/11/18 |
Maintenance of Impact Attenuator & Guardrail End Treatments *Superseded by Memo 20-01* | 18-04 |
11/28/17 |
Use of the Law Enforcement Officer for Work Zone Safety *Superseded by Memo 21-06* | 17-17 |
09/20/17 |
LPA and State Shop Drawing and Falsework Review Procedures *Superseded by Memo 20-10* | 17-14 |
08/07/17 |
Alternate to Concrete Sealers Unique Special Provision *Discontinued on 02/01/2018* | 17-12 |
06/09/17 |
Electronic Payroll Submission by Contractors (rev. 08/24/2017) *Superseded by Memo 19-07* | 17-11 |
01/19/17 |
Notice of Termination (NOT) *Superseded by Memo 19-10* | 17-01 |
06/10/16 |
Unique Special Provision for FALSEWORK REMOVAL/Revisions to Section 702 *Discontinued* | 16-06 |
06/03/16 |
Implementation of the Contractor Performance Evaluation (CPE) system *Superseded by 21-10* | 16-05 |
01/28/16 |
Notice of Termination, NOT *Discontinued. See Memo 17-01* | 16-02 |
08/14/15 |
FHWA PY 2016 PODI List for Change Order Approval- *Superseded by Memo 20-11* | 15-14 |
05/30/14 |
The Removal of FHWA Change Order Approvals from Select Construction Contracts *Superseded by Memo 15-14* | 14-07 |
04/22/14 |
Change Orders on Construction Contracts Policy *Superseded by Memo 22-08* | 14-05 |
01/30/14 |
Notice of Termination (NOT) *Superseded by Memo 17-01* | 14-02 |
11/07/13 |
LPA and State Shop Drawing and Falsework Review Procedures *Superseded by Memo 17-14* | 13-13 |
07/17/13 |
Transverse Corrugations in Sidewalk Curb Ramps *Discontinued* | 13-07 |
05/01/13 |
Notice of Termination (NOT) *Superseded by Memo 14-02* |
13-04 |
04/30/12 |
SiteManager Field Enhancement Policies and Procedures *Superseded by Memo 17-03* |
12-06 |
12/05/11 |
11-11 |
|
03/03/11 |
State and LPA Shop Drawing and Falsework Review Procedures *Superseded by Memo 13-13* |
11-02 |
02/03/10 |
10-02 |
|
01/04/10 |
New Change Order Policy *Superseded by Memo 14-05* |
10-01 |
11/30/09 |
Project Commitments Database *Superseded by Memo 10-05* |
09-22 |
11/16/09 |
M-39 & Contract Closeout *Superseded by Memo 14-03* |
09-21 |
06/11/09 |
Shop Drawing & Falsework Submittal & Review Procedures for LPA Projects *Superseded by Memo 11-02* |
09-13 |
05/06/09 |
09-12 |
|
04/30/09 |
Active Commitments Report *Superseded by Memo 09-22* |
09-11 |
04/29/09 |
Overruns on ARRA Contracts *Superseded by Memo 09-14* |
09-10 |
03/30/09 |
Construction Zone Impact Attenuators *Discontinued on 06/05/2015* |
09-09 |
03/25/09 |
Shop Drawing Submittals for Three-Sided Drainage Structures *Discontinued on 09/01/2011* |
09-07 |
02/23/09 |
PCCP Cost Savings Measures *Discontinued* |
09-06 |
02/23/09 |
HMA Cost Savings Measures *Discontinued* |
09-05 |
01/08/09 |
Shop Drawing & Falsework Review Procedures *Superseded by Memo 11-02* |
09-01 |
12/02/08 |
Construction Zone Impact Attenuators *Discontinued on 06/05/2015* |
08-15 |
08/14/08 |
08-11 |
|
05/29/08 |
Procedure for How to Handle Existing Construction Claims *Superseded by Memo 09-16* |
08-08 |
04/24/08 |
Revised Borrow and Disposal Site Specifications *Discontinued* |
08-05 |
01/28/08 |
Revised IC-730 Request for Approval of Subcontractor *Discontinued* |
08-02 |
12/18/07 |
Unit Price Justification for Extra Work *Superseded by Memos 17-15 and 17-16* |
07-28 |
12/17/07 |
HMA Revisions for 2008 *Discontinued* |
07-27 |
05/14/07 |
Clarification on Mandrel Testing of Pipes *Superseded by Memo 09-20* |
07-10 |
03/26/07 |
IC-730 Request for Approval of Subcontractor *Superseded by Memo 08-02* |
07-06 |
01/24/07 |
Monitoring of Suspended or Debarred Firms *Discontinued* |
07-03 |
01/24/07 |
Procedures for Determining When the Davis Bacon Act (DBA) Applies *Superseded by Memo 15-05* |
07-02 |
08/23/06 |
Policy for Use of Temporary Worksite Speed Limit Assembly Signs *Discontinued*, see Memo 14-06 |
06-22 |
07/17/06 |
Shop Drawing & Falsework Review Procedures *Superseded by Memo 09-01* |
06-20 |
06/13/06 |
Change Order & Time Extension Policies *Superseded by Memo 10-01* |
06-18 |
04/12/06 |
Documentation That Traffic Control Devices Meet 350 Crash Test Requirements *Discontinued on 06/05/2015* |
06-08 |
03/24/06 |
Concrete Mix Designs for 2006 *Discontinued* |
06-03 |
08/24/05 |
Specification Section 306 Milling *Discontinued* |
05-13 |
06/13/05 |
Acceptance of Plastic Pipe & Pipe Liner Materials *Superseded by Memo 12-04* |
05-11 |
05/25/05 |
Change Order Procedures *Superseded by Memo 06-18* |
05-09 |
03/29/05 |
05-04 |
|
03/05/05 |
Change Orders *Superseded by Memo 06-18* |
05-02 |
09/23/04 |
Specification Section 306 Milling *Superseded by Memo 05-13* |
04-12 |
03/22/04 |
Standard Specifications Section 213, Flowable Backfill *Discontinued* |
04-04 |
03/30/04 |
QC/QA Failed Materials Policy Revision *Superseded by Memo 05-07* |
04-03 |
03/03/04 |
04-02 |
|
12/19/03 |
Materials & Tests Approved Lists *Superseded by Memo 04-01* |
03-16 |
01/29/03 |
Buy American Specification *Discontinued* |
03-02 |
06/21/02 |
Revised Change Order Approval Policy *Superseded by Memo 06-18* |
02-08 |
05/29/02 |
2002 SMA Specifications *Discontinued* |
02-05 |
10/17/01 |
Clarification of Field Office Specification 105.17 *Discontinued* |
01-13 |
07/11/01 |
Maintenance of Attenuator & Guardrail End Treatments*Superseded by Memo 18-04* |
01-08 |
06/25/01 |
Bridge Paint Specification Changes *Discontinued* |
01-07 |
04/05/01 |
Clarification of Specification 105.17 (Field Office) *Discontinued* |
01-03 |
01/02/01 |
01-01 |
|
12/14/00 |
Time Extensions *Superseded by Memo 06-18* |
00-19 |
06/20/00 |
Change Order & Time Extension Approval Authority *Superseded by Memo 06-18* |
00-13 |
05/24/00 |
Bridge Painting Subcontractors *Discontinued* |
00-11 |
03/31/00 |
00-10 |
|
03/31/00 |
00-09 |
|
03/31/00 |
00-08 |
|
03/06/00 |
00-05 |
|
03/01/00 |
00-03 |
|
02/04/00 |
Guidelines for Transportation Enhancement Projects *Discontinued* |
00-02 |
08/31/99 |
Field Office Computers - Y2K - *Discontinued* |
99-10 |
08/12/99 |
Ignition Oven for HMA Mixture with Dolomite *Discontinued* |
99-09 |
04/23/99 |
99-05 |
|
04/09/99 |
Longitudinal Joints in HMA *Discontinued* |
99-04 |
03/30/99 |
Detail Changes to Standard Drawings for Guardrail Transition, Type TGB *Superseded by Memo 99-05* |
99-03 |
03/22/99 |
400 Spec Section of the Standard Specification *Discontinued* |
99-02 |
03/01/99 |
99-01 |