INDOT Hydraulic Engineering designs or reviews all waterway projects including, but not limited to, bridges, culverts, storm sewers, and detention ponds along state roads, U.S. routes or interstates or local projects built with state or federal funds.
Index
Developing Design Guidance
- Bridge
- For scour projects, all bedrock types, including limestone, are considered to have an unknown scour resistivity. Therefore, the Hec-RAS Scour Memo Template Instructions have been updated to reflect which scenarios should be sent to Part B for scour determination.
- The current version of HEC-RAS approved by INDOT is version 5.0.7. For 2D models, we will allow the use of 6.1.0.
- Small Structure
- CLARIFICATION OF IDM 203-2.02(02) 2.a.1.: The replacement structure does not have to have the same span as the existing structure when the existing structure is going from pipe to a proposed box type structure. However, the cross-sectional structure area cannot be reduced.
- Example: An existing twin 8 foot diameter pipes may be replaced with a proposed 15x7 box structure, even though the twin pipes have a total span of 16 feet while the box has 15 feet, as long as the proposed total area is equal to or greater than the existing. In this case, the existing area is about 101 square feet, while the proposed box (with haunches) has an area of 103 square feet.
- Example 2: An existing 6 foot diameter pipe cannot be replaced with a 5x5 box because the existing pipe has an area of 28 square feet, while the proposed box (with haunches) has an area of 23 square feet.
- HY-8 v.7.2 is currently the only version permitted for use by the INDOT Hydraulic Engineering. Please click the following link to download the software. (Active Design Memoranda16-34).
- Due to Window's updates, HY-8 v.7.2 will not install without first installing the application that can be downloaded by clicking here. After this application is installed, HY-8 v.7.2 may be installed.
- A flow chart has been developed to help designers select which structure and liner options should be analyzed. Modeling guidance has also been included. This chart can also be found as Proposed Structures Flow Chart under Other Links and Forms below.
- When analyzing an existing structure that is showing overtopping, the designer should NOT artificially raise the road to analyze headwater elevation as it may exaggerate the backwater total, but rather make certain that the discharge through the liner/new pipe at overtopping is greater than the existing.
- CLARIFICATION OF IDM 203-2.02(02) 2.a.1.: The replacement structure does not have to have the same span as the existing structure when the existing structure is going from pipe to a proposed box type structure. However, the cross-sectional structure area cannot be reduced.
- Storm Sewer MOT
For temporary storm sewer systems, the following criteria are recommended to be met for MOT:
- If a project has a construction duration in place less than 1 year, then a 2-year serviceability.
- If a project has a construction duration in place more than 1 year, then a 5-year serviceability.
- If a project has a specific known flooding history, then a 5-year serviceability should be used regardless of the construction duration in place.
- The allowable spread should allow for 8 ft of unimpacted surface per lane.
- Slotted drain may be used for temporary calculations. Any slotted drain used should follow Indiana Standard Drawings E715-SLDR-01, E715-SLDR-02, and E715-SLDR-03.
- Slab Top
- Thickness Estimation:
- The structure depths described below are for the crown of a road and should be used to determine the overflow elevation. The shoulder will be based on the minimum slab thickness and used for serviceability determination of the roadway.
- For spans up to and including 15’, that slab-top structure should have a minimum slab thickness of 12”. When computing structure depth, it would be 12” + 2% * (1/2 width of the roadway + shoulder).
- As an example, a 15’ span structure with a normal crown on a road with two 12’ lanes and 4’ shoulders, the minimum structure depth would be : 12” + 0.02*(12’+4’)*(12”/Ft) = 15.84” in thickness.
- For spans over 15’ and up to and including 20', that slab-top structure should have a minimum slab thickness of 15”. When computing structure depth, it would be 15” + 2% * (1/2 width of the roadway + shoulder).
- Please contact INDOT bridge design to estimate the slab thickness for structure over 20'.
- Wider roads (>32’ including lanes and shoulders) and longer spans (>15’) would likely need to have a larger structure depth.
- All spans have a minimum desirable structural free board of 1 ft.
- Slab tops should not be designed to be under pressure flow.
Slab-top structures are concrete slabs installed on two vertical abutments with the top of the slab normally being the driving surface. Therefore, no pavement would typically be installed on top of it. Comparatively, a 3-sided structure is precast structure with the walls and top seamlessly constructed together and a driving surface installed over the top of the structure.
Please note that the structural depths described below are only estimates and feasible for hydraulic design only. To determine the actual structural depth, please contact the engineer of record.
- Thickness Estimation:
Requests and Submitting Documents
To submit a request to INDOT Hydraulics, please use the Hydraulic Request Application (HRA). With this application, you can submit requests, obtain the status of your request, and upload any hydraulic related files for your project.
In order to submit projects for review to the HRA, the engineer must complete the appropriate training courses listed below. These courses provide basic knowledge of INDOT hydraulic requirements.
For more information on accessing the HRA, please refer to the Hydraulic Request Application and How to Use It presentation.
To determine if a project should be considered a design or a review in the HRA, please follow the HRA Project Type Determination flow chart.
If an asset number is not available for a structure, a new undocumented asset number may be warranted. Please follow How to Create New Undocumented Asset Numbers in HRA for further instructions.
When submitting documents for review, sample reports, memo templates, and instructions are provided in the Submitting Documents section below.
