Location: 
U.S 40 from Belle St. (intersection with Casey’s, First Financial, and Freeze) going East to County Road 200 East (intersection before Harbor Graphics and Brazil Treatment Plant).
Project Summary:
This project consists of a Full Depth Pavement Replacement along U.S 40 for approximately 1.6 miles between Belle St. and County Road 200 E. Along with the pavement replacement, the project will include the following within the project limits:
- New curb and gutter
- New sidewalks on the north and south sides of U.S 40
- A new fully enclosed storm sewer system
- Replacement of the small structures over Billy Creek and Harmony Drain
This project is currently at the very beginning stages of its design process. As the design progresses and plans are made available, this website will be updated.
Proposed Schedule:
1. Stage One / Culvert Hydraulics May 2026
2. Stage Two / Right-of-Way Plans December 2026
3. Stage Three / Utility Certification/ Permit Approvals February 2028
4. Final Tracings June 2028
5. Bid Letting October 2028
6. Construction, TBD / Anticipated 2029-2030