INDOT Alternative Delivery

The mission of the Major Projects Delivery Division is to develop, manage and execute complex projects. Using a variety of procurement methods, including alternative delivery methods, the Major Projects Delivery team strives to get the best value for Indiana taxpayers while staying within budget and on schedule.

In collaboration with the State’s general contractor and consultant engineer partners, INDOT will continue to facilitate partnerships with private industry and local communities to meet the needs of an expanding transportation program.

The three alternative delivery methods used by the Major Projects Delivery team are Design-Build (DB), Progressive Design-Build (PDB), and Construction Manager General Contractor (CMGC).

Early general contractor involvement (i.e., during the preconstruction activities) is the main difference between alternative delivery methods and the traditional Design-Bid-Build method of project delivery.

This early involvement is most useful on complex projects as it has been shown to enhance risk mitigation, accelerate delivery, increase industry collaboration, incentivize innovation in design, and provide greater cost certainty through all phases of project development.

Downloadable Manual

Download

Fact Sheet

Download

Industry FAQs

Download

Downloadable Manual (Redline Version)

Download

Presentation Deck

Download

Presentation (Recording)

Watch Video

Panel Discussion (Recording)

Watch Video

Please note: The Alternative Delivery Manual uses bookmarks to improve navigation within the document. Bookmarks work best when the file is opened in a PDF reader, such as Bluebeam or Adobe. To use bookmarks, look for the bookmarks panel typically found on the left or right side of the window. If it's not visible, you can open it by clicking on the bookmark icon.

To jump to a specific section, simply click on the bookmark in the bookmarks panel and the document will automatically scroll to the corresponding page.

You can also scroll below to easily access appendices to the manual.

Easily access appendices to the Alternative Delivery Manual:
Appendix A: Alternative Delivery Summary MatrixAppendix B: Template DBLB DocumentsAppendix C: Template DBBV Documents
Appendix D: Template Progressive RFPAppendix E: Template CGMC AgreementAppendix F: Template PDB Agreement
Appendix G: Preconstruction Phase Hourly Rate PolicyAppendix H: Sample Risk RegisterAppendix I: Sample Quantity Reconciliation Sheet
Appendix J: Sample Innovation Log  

Request for Proposals for FlexRoad

Learn More: Request for Proposals for LevelUp31 (Interchange Modification for I-465 and US 31 in Hamilton County)

INDOT is excited to announce that an Apparent Selected Proposer has been identified for the Level Up 31 CMGC Project.  Rieth-Riley Construction Co., Inc. is the Apparent Selected Proposer for the Project, the first undertaken as a CMGC procurement in the State.  INDOT anticipates completing negotiations and executing a CMGC agreement by August 15, 2024 (per Section 1.5 of the RFP).

Share Your Feedback

We welcome your comments as we share the Alternative Delivery Manual for your feedback. Please send your questions and comments to AlternativeDelivery@indot.in.gov.

Benefits of Alternative Delivery

  • Provides for substantial constructability integration in design development through early contractor engagement, which can help to achieve project goals.
  • Allows for schedule acceleration through all phases of the project since design and construction activities can occur simultaneously.
  • Enhances risk mitigation by using a risk register. This approach improves a project’s cost certainty, protects the contractor in the event of unanticipated changes in the scope of work, and assures INDOT that the construction cost is not inflated to include unidentified risks.
  • Increases industry collaboration and streamlines processes by forming an early contractual relationship with INDOT, the designer, and the contractor, ultimately enhancing project efficiency.

History

INDOT began using Design-Build in the 1990s. The authority to add Progressive Design-Build (PDB) and Construction Manager-General Contractor (CMGC) was passed in July 2023 for a five-year pilot and will further improve INDOT’s commitment to deliver the Statewide Transportation Improvement Program (STIP).