CenterPoint Energy/Vectren Distributed Generation Tariff

CenterPoint Energy received IURC approval of a new tariff for procuring excess distributed generation on Apr. 7, 2021.

  • In the case before the IURC, the OUCC filed testimony recommending denial, along with closing and response briefs.
  • Publicly filed documents are available from the IURC's online case file for cause No. 45378.

The Indiana Court of Appeals reversed and remanded the order in a Jan. 28, 2022 decision.

The case is now on appeal before the Indiana Supreme Court.

  • The OUCC has until  Apr. 4, 2022 to file its response.

This page will be updated based on case developments.

6-1-2022