Header

Main Content

Article

NIPSCO Gas Infrastructure Plans

Indiana Code 8-1-39 allows electric and natural gas utilities to seek IURC approval of long-term infrastructure plans. If a utility’s plan is approved, it is then allowed to request rate increases every 6 months to cover the costs of projects in the plan. The law requires the IURC to consider the plans and increases within very short timeframes.

Proposed 2020-2025 Plan (Pending)

UPDATE (7-22-2020): The IURC approved NIPSCO's plan in a July 22, 2020 order.

Northern Indiana Public Service Company (NIPSCO) filed a new 6-year natural gas system improvement plan in December 2019, in IURC Cause No. 45330. According to NIPSCO's testimony and exhibits:

  • The plan's estimated capital cost is nearly $949 million.
  • Projects throughout NIPSCO's natural gas transmission and distribution systems would include replacement of aging transmission and distribution infrastructure, storage projects, targeted economic development projects, and expansion into rural areas that currently do not have natural gas service.
  • Construction would start in 2020 and continue through 2025. The plan's first rate increase of approximately 0.66 percent would take effect in 2021.
  • Annual rate increase amounts through 2025 would vary, ranging from 0.6 percent to 1.7 percent each year. The average annual percentage increase over the 6-year term would be approximately 1.27 percent.

The OUCC filed testimony (Grosskopf and Krieger) recommending denial of the plan on April 9, 2020. On May 22, 2020, the OUCC filed a proposed order and closing brief. State law requires the IURC to issue an order by July 28, 2020.

2014-2019 Plan

NIPSCO’s natural gas utility received approval of a 7-year plan in April 2014 (IURC Cause No. 44403), referring to the program as its Natural Gas Infrastructure Modernization Plan.

  • The plan originally included about $713.1 million in capital improvement projects.
  • Projects throughout NIPSCO's natural gas service territory include replacement of aging infrastructure, new transmission mains, the installation of automated valves, and expansion into rural areas that currently do not have natural gas service.

In recent tracker filings:

  • NIPSCO’s June 2016 TDSIC adjustment raised the monthly residential gas bill for a customer using 72 therms (an average monthly amount over the course of a year) by $2.67 over the utility's base rates.
     
  • In December 2016, the IURC approved NIPSCO's request to decrease that amount to $1.87. OUCC testimony recommended approval of the request.
     
  • NIPSCO's adjustment receiving Commission approval in June 2017 raised the 72-therm amount by 36 cents, to $2.23. For the case file, click here, enter cause number 44403, and click the link for "44403 TDSIC 6."
     
  • In December 2017, NIPSCO received approval of an adjustment reducing the 72-therm amount by 60 cents, to $1.63. The OUCC filed testimony (Grosskopf and Golden) in October 2017. Under the federal Tax Cuts and Jobs Act, the amount was further reduced to $1.41.
     
  • NIPSCO's most recent tracker filing received Commission approval in August 2018 and raised the 72-therm amount to $5.81. For the case file (Cause No. 44403-TDSIC 8), click here. The OUCC filed testimony (Grosskopf and Golden) on April 30, 2018.
     
  • In Cause No. 44403-TDSIC 9, the OUCC, industrial customers, and NIPSCO reached a settlement agreement that would reduce the amount for an average residential customer to a 78-cent credit. Reductions are primarily due to federal tax reform and the withdrawal of certain projects in light of a 2018 Indiana Supreme Court ruling. The OUCC filed settlement testimony on November 7, 2018. The settlement received Commission approval on December 27, 2018.
     
  • An order in Cause No. 44403-TDSIC 10 sets the average residential charge at seven cents. In Cause No. 44403-TDSIC 11, the charge was reduced to a 53-cent credit.

NIPSCO terminated its plan effective December 31, 2019.

 

A brief summary of the TDSIC law

Indiana Code 8-1-39 allows electric and natural gas utilities to submit infrastructure improvement plans for IURC approval. A plan may cover a 5- to 7-year range. The IURC must rule within 210 days once such a request is filed.

  • Once a plan receives IURC approval, the utility may request incremental rate increases every 6 months to pay for the projects. The rate adjustment is referred to as the Transmission, Distribution and Storage System Improvement Charge (TDSIC). The IURC has 120 days to rule on such a request.
     
  • TDSIC rate increases are limited to no more than 2 percent of a utility's total retail revenues.
     
  • The TDSIC rate mechanism (or tracker) allows the utility to recover 80 percent of the costs as they are incurred. The remaining costs are deferred until the utility's next base rate case, which must be filed before the end of the 5-to-7-year period.

 

NIPSCO's electric infrastructure plan was approved in a separate docket.

6-24-2020