CADDNAR


[CITE: Dilger v. Department, 5 CADDNAR 196 (1990)]

 

[VOLUME 5, PAGE 196]

 

Cause #: 90-072R

Caption: Dilger v. Department
Administrative Law Judge: Rider  
Attorneys: Dilger, pro se; Law
Date: July 25, 1990

ORDER

 

The inspection result notification pertaining to the February 6, 1990 bond release inspection of Permit S-00084 is affirmed and bond is ordered released.

FINDINGS OF FACT

 

1. On April 4, 1990, Beno and Marie Dilger (the "Claimants") filed an objection to a pending bond release at the Energy Supply, Inc., Mariah Hill Pit, permit #S-00084.

 

2. The pending bond release was announced as an inspection result notification pertaining to a February 6, 1990 bond release inspection.

 

3. The bond release inspection was conducted by Dee Geier an authorized representative of the director, department of natural resources.

 

4. IC 4-21.5, IC 13-4.1, 310 IAC 0.6 and 310 IAC 12 apply to this proceeding.

 

5. The natural resources commission (the "Commission") is an agency as defined in IC 4-21.5-1-3 and is the ultimate authority for this proceeding.

 

6. The Claimants object to the bond release for three reasons:

 

a. They claim that a significant drainage problem exists in the area (Issue-1).

b. They present a paper included in the original permit which bears only the signature of Beno Dilger and not Marie Dilger (Issue-2).

c. They allege that the contemplated bond release would deplete the bond moneys held to a level insufficient to cover the remaining needed reclamation (Issue-3).

 

7. To substantiate Issue-1, the Claimants presented pictures taken in April 20, 1990 which showed water pooled in locations on the permit area.

 

8. Inspector Geier testified that the area was not in that condition on the day of the bond inspection (February 16, 1990).

 

9. Since the bond release is predicated on the bond inspection, it cannot be subject to constant, post-inspection scrutiny by the bond inspector.

 

10. Perhaps a notice of violation by a compliance inspector would be in order but the present condition of the area cannot be an issue in this case.

 

11. The Claimants objection here goes to the inspection result notification which resulted from the February 6, 1990 inspection and no evidence was presented as to a drainage problem on that day.

 

12. The document the Claimant alludes to in Issue-2 is a page from the original permit S-00084.

 

13. The page was executed in August 1983 and is signed by Beno Dilger.

 

14. The page is not a contract but rather is a statement of understanding that upon conclusion of reclamation the land in question will not be exactly as it was prior to mining.

 

15. While it would be preferable to have both property owners' signatures on this document (the Claimants own the land jointly), the time to object would have been within 30 days after the permit was issued and filed in the county library.

 

16. Obviously, Mr. Dilger did not disagree with the proposed postmining configuration and it is improbable Mrs. Dilger would have objected as her testimony was that, other than the lease papers, she was not involved in the dealings with the coal company.

 

17. Finally, even if the page were declared invalid, it is difficult to see how it would affect this bond release seven years after the page was signed.

 

18. The premise presented in Issue-3 cannot be applied to this bond release. The Claimant wishes the administrative law judge to invalidate the bond release on the premise that there must be enough bond money left after release to complete the remaining reclamation.

 

19. While it is true that the Department is responsible for assuring that at all times enough bond is present to cover needed reclamation, this is not a factor by rule or statute which would deny bond release on an area that meets all bond release

 

[VOLUME 5, PAGE 197]

 

criteria.

 

20. If the Claimants feel that after bond release the remaining bond money is insufficient and that the Department has failed to act in regard to demanding additional bond, they could deal with the problem under the provisions of IC 4-21.5, the Administrative Adjudication Act.

 

21. However, even if the administrative law judge were to use the remaining bond sufficiency as a criterion here, the evidence does not show the remaining bond is insufficient.

 

22. Inspector Geier testified that after release, bond of $85,101.25 would be remaining. She opined that this amount would be sufficient to complete reclamation.

 

23. The Dilgers produced no evidence to the contrary except a letter from a United States government official which gave his opinion as to reclamation costs in the area.

 

24. This letter was excluded from evidence because its hearsay nature precluded the Department from examining the credentials of the declarant and eliciting testimony as to how his opinions were reached.

 

25. None of the testimony advanced by the Dilgers at hearing would preclude the proposed bond release.