CADDNAR


[CITE: Peabody Coal v. DNR, 4 CADDNAR 58 (1988)]

 

[VOLUME 4, PAGE 58]

 

Cause #: 86-166R

Caption: Peabody Coal v. DNR
Administrative Law Judge: Drew
Attorneys: Joest; Sheffler, DAG
Date: March 18, 1988

ORDER

 

[NOTE: THE HOLDING IN THIS CASE WAS DISAPPROVED IN PEABODY COAL COMPANY v. INDIANA DEPARTMENT OF NATURAL RESOURCES, (1994) IND. APP., 629 N.E.2d 925.]

Notice of Violation #N61024-S-00017 is vacated.

FINDINGS OF FACT

 

1. On December 2, 1986, Peabody Coal Company (the "Claimant") requested administrative review of the Notice of Violation #N61024-S-00017 issued by the Division of Reclamation of the Department of Natural Resources (the "Respondent").

 

2. IC 4-22-1 and IC 13-4.1, the Surface Coal Mining Act, apply to this proceeding.

 

3. The Department of Natural Resources is an agency as the term is defined in IC 4-22-1. The Director is the ultimate authority of the Department with respect to the subject matter of this administrative action.

 

4. The Director has jurisdiction over the subject matter and parties to this proceeding.

 

5. On December 12, 1987 Claimant filed a Motion of Summary Decision pursuant to 310 IAC 0.5-1-11 and on June 22, 1987 oral argument was held in the above cause.

 

6. Claimant holds permit #S-00017 to conduct surface coal mining operations in Sullivan County, Indiana at its Dugger 8900 area mine.

 

7. On October 24, 1986 an authorized representative of the Director cited Claimant with Notice of Violation #61024-S-00017.[FOOTNOTE 1]

 

8. Notice of Violation #N61024-S-00017 cited Claimant for failure to control all surface drainage from the disturbed area through use of a siltation structure, a series of siltation structures, or such alternative techniques as provided in 310 IAC 12-5-20 before leaving the permit area and cites 310 IAC 12-5-17(a)(1), 310 IAC 12-3-4 and Part IV, G(2)(a) of the permit as the provisions violated.

 

9. The inspector report accompanying the Notice of Violation indicated there were two locations where sediment control measures failed (sites "A" and "B")[FOOTNOTE 2] and three other locations where sediment control measures were needed but not the implemented (cited "C", "D", and "E".)

 

10. During the inspection of site B the inspector noted a single row straw bale check dam had been erected and that drainage from the area was undercutting one of the bales and bypassing the dam.

 

11. The inspector also observed at site B sediment deposition in a drainage way of the permit. The deposition generally exceeded one inch in depth and extended laterally at least fifty to seventy-five feet.

 

12. Sites C, D and E are small drainage areas where, according to the inspector's report, effluent was discharged without appropriate sediment controls.

 

13. Drainage from sites B through E enters into an unnamed tributary of Buttermilk Creek. It is uncontested that water samples were not taken during the inspection.

 

14. IC 13-4.1-8-1 is the controlling statute and requires that disturbances to the hydrologic balance be minimized and then lists various methods by which this can be accomplished.

 

15. IC 13-4.1-8-1 (10)(B) states that violations of effluent limitations are established under state or federal laws shall be prevented, to the extent possible, using the best technology currently available.

 

16. IC 13-4.1-8-1(10)(C) concerns the construction of siltation structures as a means of implementing clause (10)(B).

 

17. IC 13-4.1-8-1(10)(G) allows the Natural Resources Commission (the "commission") to take additional action as it may prescribe.

 

18. 310 IAC 12-5-17 also regulates water quality standards and effluent limitations affecting the hydrologic balance. It requires all surface drainage from the disturbed are to be controlled through siltation structures or through alternative techniques provided in 310 IAC 12-5-20.

 

19. It is a basic principle of administrative law that an administrative agency cannot adopt or enforce regulations that add or detract from a statute enacted to cover the same circumstances of purposes. Hill v. Review Board, 124 Ind. App. 83, 112 N.E. 2d 218 (1953), Indiana Department of State Revenue v. Colpaert Realty Corp., 231 Ind. 563, 109 N.E. 2d 415 (1953).

 

20. 310 IAC 12-5-17 is a regulation designed to protect the hydrologic balance as required by IC 13-4.1-8-1 by regulating water quality standards and effluent violations. Consequently, 310 IAC 12-5-17 may not exceed the requirements found in IC 13-4.1 -8-1 and may only require sediment control measures where necessary to prevent violations of effluent limitations to the extent possible using the best technology currently available.

 

21. No water samples were taken to measure whether an effluent violation did or did not occur.[FOOTNOTE 3]

 

22. Where, however, 310 IAC 12-5-17 is cited because sediment control measures are necessary to prevent a violation of applicable effluent limitations, then this regulation could be properly invoked and a violation issued.

 

23. Respondent has failed to demonstrate that an effluent limitation violation was likely to occur or that Claimant allowed such a condition to exist.

 

24. Clause (10)(G) empowers the Commission to take any additional action it deems necessary to carry out the intent of IC 13-4.1-8-1(10). The Commission, however, may only take additional action; it may not take any action inconsistent with what the statute already prescribed.

 

[VOLUME 4, PAGE 59]

 

25. Clause (10)(C) of IC 13-4.1-8-1 and 310 IAC 12-5-17 refer to the use of siltation structure as a means of controlling effluent limitations and protecting water quality standards. Therefore, 310 IAC 12-5-17 cannot be said to be an additional action as required to fall under the scope of clause (10)(G) of the governing statute.[FOOTNOTE 4]

 

26. Respondent has not established a prima facie case showing that an effluent violation did occur.

 

FOOTNOTES

 

1. The Notice of Violation also required Claimant to undertake certain abatement actions. Claimant also objected to these actions in its petition for review. However, the violation has since been terminated and this question is therefore moot.

 

2. On November 25, 1986 the Inspector modified the Notice of Violation by deleting site A from the location of the violation because bond on this area was previously released.

 

3. The inspector's report was based solely on visual observations. In an uncontroverted affidavit, Ron G. McAhron established that it was not possible to reliably infer that a violation of effluent limits occurred based solely on whether sediment was deposited in the receiving stream. According to McAhron, effluent violations are based upon sediment concentrations, not total amounts of sediment, and thus are not dependent on volume of flow.

 

4. Respondent argues that clause (10)(B) of IC 13-4.1-8-1 is intended as one means for protecting the hydrologic balance by ensuring that effluent limitations are not exceeded. Respondent further argues that the sediment controls found in 310 IAC 12-5-17 are important to the hydrologic balance above and beyond effluent considerations and this can be said to be additional measures as provided for in clause (10)(G). That is not the case, however. 310 IAC 12-5-17 specifically regulates water quality standards and effluent limitations affecting the hydrologic balance. Sediment control measures, on the other hand, are regulated by 310 IAC 12-5-20 and consequently 310 IAC 12-5-17 cannot be said to be an additional measure relating to the protection of the hydrologic balance.