[CITE: Fossil Fuels Min., Inc. v. DNR, 3 CADDNAR
35 (1986)]
[VOLUME 3, PAGE 35]
Cause #: 85-102R
Caption: Fossil Fuels Min.,
Inc. v. DNR
Administrative Law Judge: Lucas
Attorneys: Conlon; Szostek, DAG
Date: March 21, 1986
ORDER
With
respect to administrative cause number 85-120R, it is ordered that Notice of Violation
#N50412-S-00053 is affirmed.
With
respect to administrative cause number 85-103R, it is ordered that Notice of
Violation #N50412-81-122 is affirmed.
With
respect to administrative cause number 85-145R, it is ordered that Cessation
Order #C50603-S-00053 is affirmed.
With
respect to Adm. Cause no. 85-150R, it is ordered that Cessation Order #C50603-81-122
in the Marion Circuit Court, Cause No. C86-0849, it is ordered that the Findings
and Conclusions of Defendant in 85-102R, 85-103R, 85-145R, and 85-150R are sustained.
(July 31, 1986)
FINDINGS OF FACT
A. With respect to
administrative cause number 85-102R:
1. The
Department
of Natural Resources (hereinafter the "Department") is an agency as
defined in IC 4-22-1. The Director of the Department (hereinafter the
"Director") is the ultimate authority of the Department with respect
to this proceeding.
2.
On April 25, 1985, Fossil Fuels Mining, Inc. (hereinafter Fossil) requested
that the Department provide a hearing to review Notice of Violation
#N50412-S-00053.
3.
The Director appointed an Administrative Law Judge in accordance with IC 4-22-1
and 310 IAC 0.5-1 to conduct this administrative action in response to the
hearing request by Fossil.
4.
On August 7, 1985, the parties filed written factual stipulations and jointly
moved for summary decision under 310 IAC 0.5-1-11 in lieu of hearing.
5.
The Director has jurisdiction over the subject matter and over the parties to
this administrative action.
6.
Fossil holds permit S-00053 to conduct Surface Coal Mining Operations at the
Castle Hill Mine in Greene County.
7.
On April 12, 1985, Shirley Adkins, an authorized representative of the
Director, wrote Notice of Violation #N50412-S-00053 (hereinafter the Permanent
Program NOV)
8.
The Permanent Program NOV was issued because of the failure by Fossil to
control sediment so that all sediment would be retained within the area
disturbed under the permit. The location of the violation was the northern edge
of Bond Segment B of the permit, and the provision cited in the Permanent
Program NOV was 310 IAC 12-5-20 (b) (3).
9.
310 IAC 12-5-20 (b)(3) provides as follows:
"(b)
Sediment control measures include practices carried out within and adjacent to
the disturbed area. Sediment control measures consist of the utilization of
proper mining and reclamation methods and sediment control practices, singly or
in combination. Sediment control methods include, but are not limited to:. . .(3) retaining sediment within the disturbed areas..
."
10.
The Permanent Program NOV stated the action required to abate the violation was
to "construct (a) terrace to the south of this area to direct runoff into
basin #10. This terrace should tie in with the one on the interim permit
(81-122) area to the east. (Fossil should) seed & mulch upon
completion." The time set for compliance with the required abatement was
8:00 a.m. on May 15, 1985.
11. Fossil
failed to abate the violation within the time set for compliance and on June 3,
1985,Cessation Order #C5063-S-00053 was issued because of the failure by Fossil
to abate the Permanent Program NOV.
12.
The Permanent Program NOV was issued as a result of a reoccurrence of
activities cited in #N50312-S-00053.
13. In general terms, a purpose of IC 13-4.1, as set forth in IC
13-4.1-1-2(2, is to "[e]stablish a statewide
program to protect society and the environment from the adverse effects of
Surface Coal Mining Operations."
14.
To implement this purpose, among the requirements imposed upon a permittee under IC 13-4.1 are those set forth under IC
13-4.1-8-1 to: (1) Conduct his surface coal mining
[VOLUME 3, PAGE 36]
operation
in a manner which maximizes the utilization and conservation of the solid fuel
resource which is recovered so that re-affecting the land in the Future through
Surface Coal Mining is minimized. . .(10) minimize disturbance to the
prevailing hydrologic balance at the mine site and ground water systems during
and after Surface Coal Mining and Reclamation Operations. . ."
15.
These statutory purposes and requirements are implemented, in part, by 310 IAC
12-5-20.
16.
In accordance with IC 13-4.1-12-1(c), each day in violation of IC 13-4.1 may be
considered a separate violation for purposes of assessing a civil penalty.
17.
Generally, where there is a continuing duty under an environmental law to do an
act.[FOOTNOTE i]
18.
That a new Notice of Violation is issued for a violation of IC 13-4.1, which
was also cited on a previous date, does not in itself make the new Notice of
Violation invalid.[FOOTNOTE ii] Each day a requirement under IC 13-4.1 is
not performed by a permittee constitutes a separate
violation.
19.
The Division of Reclamation of the Department is not deprived of jurisdiction
to vacate a Notice of Violation or Cessation Order because of the pendency of
an action under the administrative adjudication act (IC 4-22-1) regarding that
Notice of Violation or Cessation Order.[FOOTNOTE iii]
20. Issuance
of NOV #N50412-b-00053 (the Permanent Program NOV) should be sustained.
B. With respect to
administrative cause number 85-103R:
1.
The findings (and footnotes) included in Part II A are incorporated by
reference.
2.
On April 25, 1985, Fossil requested that the Department provide a hearing to
review Notice of Violation #N50412-81-122 (herein the Interim Program NOV).
3.
Fossil holds permit 81-122 to conduct Surface Coal Mining Operations at the
Castle Hill Mine in Greene County.
4.
On April 12, 1985, Shirley Adkins, an authorized representative of the
Director, wrote the Interim Program NOV.
5.
The Interim Program NOV issued because of the failure by Fossil "to
restore, in a timely manner, all disturbed areas to conditions capable of
supporting the uses to which they were capable of supporting prior to
mining."
6.
The provisions cited in the Interim Program NOV as having been violated by
fossil were
(a)
IC 13-4-6-1.6;
(b)
30 CFR 715.13 (a); and,
(c)the Plan of Reclamation--item 14.
7.
IC 13-4-6-1.6 was enacted by the Indiana General Assembly as Public Law
148-1985 and was made effective April 9, 1985.
8.
Pursuant to 30 CFR 914.15(f), IC 13-4-6-1.6 was approved by the Director of the
Office of Surface Mining as a portion of the Indiana State program under the
Federal Surface Mining Control and Reclamation Act of 1977 (30 USC 1201-1328;
see particularly 30 USC 1253) on May 13, 1985.
9. 30
CFR 732.17(g) provides that "[w]henever changes
to laws or regulations that make up the approved state program are proposed by
the state, the state shall immediately submit the proposed changes to the
Director [of the Office of Surface Mining] as a amendment. No such change to
laws or regulations shall take effect for purposes of a state program until
approved as an amendment."
10.
When the Interim Program NOV was issued, IC 13-4-6-1.6 was not a portion of the
approved Indiana program under the Federal Surface Mining Control and
Reclamation Act of 1977 (herein SMCRA).
11.
30 USC 1254 (g) provides: "Whenever a Federal program is promulgated for a
State pursuant to the Act [SMCRA], and statutes or regulations of such State which
are in effect to regulate Surface Mining and Reclamation Operations subject to
the Act shall, insofar as they interfere with the achievement of the purposes and
the requirements of this Act and the Federal program, be preempted and
superseded by the Federal program. The Secretary shall set forth any State Law
or Regulation which is preempted and superseded by the Federal program."
12.
30 CFR 730.11(a) provides as follows: "No State Law or regulation shall be
superseded by any provision of the [Surface Mining Control and Reclamation] Act
or the regulations of this chapter, except to the extent that the State Law or
regulation is inconsistent with, or precludes implementation of, requirements
of the Act or this chapter. The Director [of the Office of Surface Mining]
shall publish a Notice of the proposed action in the Federal Register setting
forth the text or a summary of any State law or regulation initially determined
by him to be inconsistent with the Act or this chapter. The notice shall
provide 30 days for public comment. Following the close of the public comment
period, the Director [of the Office of Surface Mining] shall make a final
determination which shall be published in the Federal Register."
13.
Where the federal and
[VOLUME 3, PAGE 37]
state
governments exercise concurrent power, the Supremacy Clause, United States
Constitution, Article VI, Section 2, acts to preempt State Laws only where it
is clear that Congress so intended. Statutes are construed to avoid preemption,
absent an unmistakable intention to the contrary. Where it is not clearly
stated that the state law is preempted, the state law is preserved unless it
conflicts with federal law or would frustrate the federal scheme, or unless it
is discerned from the totality of the circumstances that Congress sought to
occupy the field to the exclusion of the States.[FOOTNOTE iv]
14.
IC 13-4-6-1.6 was not superseded, nor was its implementation preempted, by
SMCRA prior to approval by the Director of the Office of Coal Mining. That the
provisions of IC 13-4-6-1.6 were not inconsistent with SMCRA is implicit in the
approval of that statutory section by the Director of OSM on May 13, 1985. The
federal scheme would be thwarted, not by the implementation of IC 13-4-6-1.6,
but by declining to implement its provisions.
15.
IC 13-4-6-1.6 was effective for purposes of Indiana Law on April 12, 1985, the
date on which the Interim Program NOV was issued.
16.
IC 13-4-6-1.6 states: "All Surface Coal Mining Operations that operate or
have operated under a permit issued under this chapter subject to Acts 1978,
P.L. 159, Acts 1979, P.L. 314, Acts 1980, P.L. 101, Section 5, or Acts 1981,
P.L. 331 are subject to IC 13-4.1-11, IC 13-4.1-12, IC 13-4.1-13, 30 U.S.C.
1252, 30 U.S.C. 1260 (d), 30 U.S.C. 1272(e), and 30 C.F.R. 710 through 716.
17.
Permit 81-122 was issued under Acts 1981, Public Law 331 and is subject to 30
C.F.R. 710 through 716. Included within 30 C.F.R. 710 through 716 is 30 C.F.R. 715.13(a),
the provision cited in the Interim Program NOV.
18.
30 C.F.R. 715.13(a) was in effect when the Interim Program NOV was issued.
19.
30 CFR 717.13(a) states: "General. All disturbed areas shall be restored
in a timely manner 1) to conditions that are capable of supporting the uses
which they were capable of supporting before mining, or 2) to higher or better
uses achievable under criteria and procedures of paragraph (d) of this
section."
20.
The Interim Program NOV sets forth a factual basis for a violation of 30 CFR
715.13(a) and is supportable under the substantive law then in effect.[FOOTNOTE v]
21.
Issuance of NOV #N50412-81-122 (the Interim Program NOV) should be sustained.
C. With respect to Administrative
Cause Number 85-145R:
1.
The findings (and footnotes) included in Part II A and Pat II B are incorporated by reference.
2.
Fossil in a timely fashion requested that the Department provide a hearing to
review Cessation Order #C50603-S-00053 (hereinafter the Permanent Program CO) issued
for failure to abate by June 3, 1985 the Permanent Program NOV.
3.
The Permanent Program CO was written by Shirley Adkins on June 3, 1985.
4.
Fossil failed to control sediment in the area covered by the Permanent Program
CO as required by 310 IAC 12-5-20(b)(3).
5.
Issuance of Cessation Order #C50603-S-00053 (the Permanent CO) should be
sustained upon the facts presented by the parties.[FOOTNOTE vi]
D. With respect to
Administrative Cause #85-150R:
1.
The findings (and footnotes) included in Part II A, Part II B and Part II C are incorporated by reference.
2.
Fossil in a timely fashion requested that the Department provide a hearing to review
Cessation Order #C50603-81-122 (hereinafter the Interim Program CO) issued for
failure to abate by June 3, 1985 the Interim Program NOV.
3.
The Interim Program CO was written by Shirley Adkins on June 3, 1985 pursuant
to IC 13-4-6-1.6.
4.
Fossil failed to reclaim areas described in the Interim Program CO according to
an abatement schedule set forth in the Interim Program NOV.[FOOTNOTE vii]
5.
Issuance of Cessation Order C50603-81-122 (the Interim Program CO) should be
sustained upon the facts presented by the parties.
FOOTNOTES:
i. Illustrative of this legal principle are two
decisions, an older appellate case from Illinois and a very recent Indiana
case, where criminal convictions for the violation of environmental laws upheld,
even though the active roles of the defendants ceased before the effective date
of the applicable statutes. In People v. Jones (1946), 329 Ill.Ap.
503, 69 N.E. 2d 522, an operator was charged with failing to plug an oil well,
although the statute governing plugging was enacted 18 months after the well
was abandoned. A conviction was sustained against an attack that the statute
was an ex post facto law; and, more importantly to the instant administrative
action, against an attack that a statute of limitation barred prosecution.
"[T]he nuisance is a continuing one and each day that the said well
remained unplugged would constitute another offense." Jones at 69 N.E. 2d 524. The
Jones decision was cited favorably in a
[VOLUME 3, PAGE 38]
recent Indiana Court of Appeals
decision sustaining a conviction under the provisions regulating the storage of
hazardous waste materials. In DeHart v. State,
(1984) Ind. App., 471 N.E. 2d 312, the court sustained a criminal conviction
for violating the Environmental Management Act (IC 13-7-1), although the act
took effect in 1980 and no waste materials had been stored by the defendant
since 1971. If the legal principle set forth in Finding 16 has application to a
criminal proceeding, an even more compelling case is made for its application
in a noncriminal context, where the standard of proof is lesser and where the
result more directly affects the quality of the environment.
ii. A factual circumstance could exist which would preclude enforcement of a
second Notice of Violation. Two penalties could not, for example, be assessed
on the same date for the same violation. A second Notice of Violation might be
barred by action o law, as upon res judicata or collateral
estoppel. The facts presented by the parties in the
instant administrative actions do not support preclusions of a second Notice of
Violation. Since the earlier Notice of Violation (Administrative Cause Number
85-068R) was being processed for dismissal when the Permanent Program NOV was
issued, no duplication or penalty assessment could result. The earlier NOV was
vacated because Fossil implemented measures to correct (albeit ineffectively)
the source of the violation. The dismissal of Administrative Cause Number
85-068R did not address the merits of the violation. Fossil argues that its
efforts to abate the violation set forth in Administrative Cause Number 85-068R
were constructed by the Division of Reclamation to have been temporary
measures: "If the measures taken to abate the NOV in 85-068R were
temporary then such abatement measures should have been reviewed as interim'
under 310 IAC 12-6-69(g). Respondents [Department] should have moved to amend
its termination of the NOV in cause no. 84-068R since the matter was still
pending review rather than to have issued another NOV [Fossil's Brief at page
4.] 310 IAC 12-6-69(g) provides: "Whenever an abatement time in excess of
90 days is permitted, interim abatement measures may be imposed to the extent necessary
to minimize harm to the public or environment." Use of the word
"may" in the rule subsection demonstrates that its application by the
Department is discretionary rather that mandatory. More importantly, the
subsection does not speak to what mechanism is to be employed where an
"interim abatement measure" proves unsatisfactory. While a sense of continuity
might better served by reinstating the original NOV (and the previous
administrative action), rather than issuing a new NOV, no regulatory or
statutory authority cited by Fossil mandates that result, Fossil suffers no
peculiar harm since the consequences of the various scenarios are the same.
When on April 12, 1985, Shirley Adkins observed a violation (whether that
violation is viewed as a new violation, a continuing violation on a new date or
a reoccurrence of a previously cited violation),
Fossil was no more or less responsible for its consequences. Perhaps without
fully articulating its position, Fossil seeks relief from statutory and
regulatory infringements through application of an affirmative defense or
defenses. While the concept of an affirmative defense is recognized in 310 IAC
0.5-1-8, Fossil has failed to demonstrate that relief should be accorded.
iii. Fossil cites Gateway Coal Co. v. OSM
(No CH 2-50-R) 84 IBLA 371, January 25, 1985 in support of the proposition that
once an administrative action is instituted, only the Director (or his
administrative law judge) has jurisdiction over a disputed NOV or CO.
Accordingly, the Division of Reclamation would be precluded from vacating an
NOV or CO. The court in Gateway determined that where an action was pending
before a federal administrative law judge, OSM lost jurisdiction to vacate the
Notice of Violation at issue in the administrative action. Implicit to Fossil's
argument is that the federal administrative law judge should here be analogized
to an Indiana administrative law judge; and the Office of Surface Mining should
be analogized to the Division of Reclamation. The analogy is reasonable, if not
compelling. In any event, there are important factual distinctions between Gateway and the NOV's and CO's at issue in
the four instant administrative actions. The Gateway decision was tied to
judicial concern for the protection of a third-party (intervenor),
an occupant of a dwelling adjacent to the mine site, who objected to the
vacation. The
[VOLUME 3, PAGE 39]
instant administrative actions involve
exclusively Fossil (the permittee) and the
Department. Probably a more critical distinction is found in the emphasis
placed by the Gateway court on a well-established declared federal agency
policy stating that once an appeal is taken, jurisdiction over a particular
matter rests exclusively in the appellate body: ". . .For a considerable
period of time it has been the declared policy of the Department [of the
Interior] that when an appeal is taken from the decision of one of its offices,
that office loses jurisdiction of the matter until that jurisdiction is
restored by disposition of the appeal of the appellate body. . .This policy was
extended to cases involving appeals from decisions issued by OSM in one of the
earliest cases decided by the Interior Board of Surface Mining Appeals. . .
." [Citations omitted. Gateway at 84 IBLA 374 and 375.] There is so similar policy
of the Indiana Department of Natural Resources. The concept recognized in Gateway
is not without merit. The orderly disposition of disputes would be promoted,
parties would be better apprised of the status of an individual case, and the
Division of Reclamation would not be unduly burdened. The concept should be
applied only following a clear policy declaration by the Director, or
preferably through rule promulgation, and should exclusively be given
prospective application. The Gateway decision cannot appropriately negate the
actions by the Division of Reclamation in the instant actions.
iv. See by way of illustration Tennessee
v. Champion International Corp. (1985), 22 ERC 1338, Tenn., App., which
constructed the Clean Water Act (33 U.S.C. section 1251, et seq.). There the
court rejected the proposition that Congress intended to preempt state law with
the scheme providing for a National Pollutant Discharge Elimination Systems
(NPDES) permit. With reasoning analogous to SMCRA, the court concluded:
"We find nothing in the CWA to remotely suggest that Congress intended to
preempt the states' prerogatives in the field of water pollution. In fact, the
opposite is true. The states are invited, and we think encourage, to adopt water
quality standards more stringent than those set by the Federal Government under
the act."
v. In its Reply Brief the Department urges that reference in the Interim
Program NOV to Item 14 of the Plan of Reclamation forms, in itself, a
sufficient basis to support a violation. A difficult question is presented as
to whether a term within a plan of reclamation, which is not authorized by the
statutory structure creating a regulatory program, may be enforced under that
statutory structure. The question need not be addressed here, since 30 CFR
715.13 established a proper foundation for issuance of the Interim Program NOV.
vi. Fossil argues in its Brief that the Two Cessation Orders here at issue were
entered by the Department in violation of IC 4-22-1-5. Although a journey
through the administrative adjudication act is a wondrous expedition,
guaranteed to dismay even the most seasoned traveler, it is thought this
argument is misdirected. Fossil presents no evidence that the issuance of
either Cessation Order has caused the company to do anything to its detriment,
nor does Fossil show prejudice of any manner caused by issuance of these COs. The hearing requests made by Fossil have resulted in
actions against the company to be held in abeyance pending completion of the hearing
process and a final order by the Director. Presumably, the hearing requests
have, in essence, served as stays against further agency action. Once the
hearing process is completed, he issue becomes moot. In any event, if IC 13-4.1
contains a process not recognized under the administrative adjudication act, IC
13-4.1 must control. IC 13-4.1 is the more recent and more specific enactment,
and under general principles of statutory construction would prevail, even assuming
some conflict with IC 4-22-1.
vii. Fossil urges in its Brief that the Interim Program CO "should be
vacated" because the company was "not given a reasonable time to
abate" the Interim Program NOV. What is reasonable is ordinarily a factual
question and not subject to resolution upon summary decision. To be noted is
that both parties have agreed to a determination of the instant actions upon summary
decisions. While circumstances might exist under which an abatement period is unreasonable
[VOLUME 3, PAGE 40]
as a matter of law, those
circumstances have not been established with respect to the Interim Program NOV
and the Interim Program CO. Neither can it be said, however, that the abatement
period has been shown to be reasonable as matter of law. If Fossil wishes to
request a hearing to determine the reasonableness of the abatement period
stated in the Interim Program NOV, that request should be made within the
period provided for objections, and a hearing will be granted. Fossil contends
that failure by the Department to provide a hearing opportunity on the
abatement period prior to issuance of the CO is a fatal flaw to its issuance.
According to Fossil, the Department's "Issuance of its Orders which were
final orders as to the time for abatement were issued without notice and an
opportunity to be heard" are granted with respect to the NOV. A person
aggrieved by the period set for abatement in the NOV may request a hearing on
the NOV and secure a modification of the abatement period. See by way of
illustration Jaeco, Inc. v. Department of Natural Resources,
Division of Reclamation, Administrative Cause Number 85-206R (January 10,
1986) where an extension of the abatement period set forth in an NOV was
provided by final order of the Director.
_____________________________________________________________________
[NOTE: CADDNAR citation does not apply below this line.]
[NOTE: THIS CASE WAS AFFIRMED
ON JUDICIAL REVIEW BY THE MARION CIRCUIT COURT ON MARCH 21, 1986. THE FINDINGS AND
ORDER OF THAT COURT FOLLOW:]
FINDINGS OF FACT
1.
On March 21, 1986, Defendant issued his final order in Cause Nos. 85-102R,
85-145R and 85-150R, sustaining the Notices of Violation (NOV) and Cessation Orders
(CO) issued by the Department under the Surface Mining Law. This order was
issued as a result of the parties' stipulation that the consolidated cases be
submitted for decisions by Motions for Summary Decision without a hearing being
held. The Motions were submitted to Stephen L. Lucas, Hearing Officer, and
after Plaintiff's objections to his proposed order were submitted, the Director
issued his final order, all pursuant to the Administrative Ajudication
Act.
2.
Plaintiff's petition for judicial Attachment: review of said alleges that said
order is not in accordance with the law and is an abuse of administrative
discretion; and that as to one of the Cessation Orders, the facts do not show a
reasonable time for abatement. In support thereof, he alleges the following
reasons:
1.
Defendant's decisions on the NOVs and COs are not in accordance with the law
and or otherwise an abuse of administrative discretion in that the Defendant
erroneously held that:
a) a
field inspector for the Department may at any time and without notice to
Plaintiff remove from Defendant subject matter jurisdiction over a matter undergoing
administrative review pursuant to IC 13-5.1-11-8 and IC 4-22-1, et seq.; and
that
b) it is lawful for an NOV to be written to include subject
matter which is already undergoing administrative review in another matter; and
that
c) an NOV may be written based upon a law not otherwise
authorized by CFR 732.17(g); and that
d) the provisions of IC 4-22-1-5 are discretionary and that
Plaintiff to claim relief must show actual prejudice.
2.
Defendant's decision in CO #C50412-81-122 was given is not supported by the
facts as presented in that the field inspector for the Department presented
inconsistent written statements concerning the length of time for abatement.
3.
With regard to Plaintiff's contention 1.a, the record reflects that the
Department inspector vacated an NOV which was undergoing administrative review.
The Court finds that the Department is not deprived of jurisdiction to vacate a
Notice of Violation or Cessation Order because of the pendency of an action
under the Administrative Attachment: Adjudication Act (IC 4-22-1) regarding
that Notice of Violation or Cessation Order. The inspector's vacation of an NOV
does not remove jurisdiction from the reviewing official (the Director), since
the inspector is the Director's authorized representative under IC 13-4.1-11
and IC 13-4.1-2-2, nor does it remove jurisdiction from the Administrative Law
Judge, since under IC 4-22-1 the Administrative Law Judge makes recommendations
to the Director. The Court further finds that this allocation of functions
under state law does not render the Indiana Surface Mining Law inconsistent
with the Federal Surface Mining Law.
4.
With regard to Plaintiff's contention 1.b, the Court finds that each day in violation
of IC 13-4.1 constitutes a separate violation of the Act. That a new NOV issued
for a violation of IC 13-4.1, which was also cited on a previous date, does not
in itself make the new notice of violation invalid.
5.
With regard to Plaintiff's contention 1.c, the Court finds that IC 13-3-6-1.6
does not interfere with the achievement of the purposes and requirements of the
Federal Program. This being the case, the Federal Program does not supersede the
State Program (under 30 USCA sec. 1254 (g); IC 13-4-6-1.6 was enforced by the
Department on April 12, 1986, the date on the record on which the NOV in
question was written.
6.
With regard to Plaintiff's contention 1.d, the Court finds that, as to the COs
issued, the application for review process of IC 13-4.1-11 results in issuance
of a final order by the Director. The record reflects that Plaintiff had notice
and opportunity to be heard prior to Attachment: issuance of the final order by
the Director.
7.
With regard to Plaintiff's contention 2, the Court finds that the record discloses
Plaintiff failed to request a hearing on the issue of the reasonableness of the
time granted by the Department to abate the violation in cause No. 85-103R.
Plaintiff thus failed to exhaust administrative remedies as required, and
cannot now seek judicial review of this issue. Conclusion of Law:
The
Court finds that:
1.
Defendant did not act in a arbitrary, or capricious manner.
2.
The decision was not contrary to any constitutional rights of Plaintiff.
3.
The decision was not in excess of any statutory jurisdiction.
4.
That proceedings were duly observed.
5.
That the decision is supported by the evidence.
6.
That the law is with Defendant. IT IS THEREFORE ORDERED, ADJUDGED AND DECREED
that the Findings and Conclusions of the Defendant in 85-102R, 85-103R, 85-145R
and 85-150R are sustained.