CADDNAR


[CITE: Foertsch Construction Co., Inc. v. DNR, 3 CADDNAR 20 (1986)]

 

[VOLUME 3, PAGE 20]

 

Cause #: 85-036L

Caption: Foertsch Construction Co., Inc. v. DNR
Administrative Law Judge: Shadley 

Attorneys: Hargis; Szostek, DAG
Date: April 4, 1986

ORDER

 

Notice of Violation #N50129-S-00055 is modified to delete under provision violated 310 IAC 12-5-24(g). Notice of Violation #N50129-S-00055, as modified herein, is affirmed.[FOOTNOTE 4]

 

FINDINGS OF FACT

 

1. On February 4, 1985, Foertsch Construction Co., Inc. ("Foertsch") requested review of Notice of Violation #N50129-S-00055.

 

2. IC 4-22-1 and IC 13-4.1-11-8 apply to this proceeding.

 

3. The Department of Natural Resources (the "Department") is an agency as defined in IC 4-22-1. The Director is the ultimate authority of the Department with respect to proceedings to review Notices of Violation and Cessation Orders.

 

4. The Director has jurisdiction over the subject matter and the parties to this proceeding.

 

5. Notice of Hearing was given to: Mr. John A. Hargis, Attorney for Foertsch, Wagoner, Ayer & Hargis, 104 South Third Street, Rockport, Indiana 47635; Mr. Charles Bates, P.E., Foertsch Construction Co., Inc., PO Box 16, Lamar, Indiana 46580; Mr. Steven J. Szostek, Deputy Attorney General and Attorney for the Department, 309 West Washington Street, Suite 201, Indianapolis, Indiana 46204; Mr. Wilbur Pershing, Daviess County Recorder, Courthouse, Washington, Indiana 47501.

 

6. On March 13, 1986 a hearing was conducted pursuant to IC 13-4.1, IC 4-22-1 and 310 IAC 0.5.

 

7. Foertsch holds permit S-00055 to conduct surface coal mining operations in Daviess County at its Little Sandy #3 Mine.

 

8. On January 29, 1985, an authorized representative of the Director cited Foertsch with Notice of Violation #N50129-S-00055 which was issued on site on that day.

 

9. Notice of Violation #N50129-S-00055 cited Foertsch for failure to maintain and protect sediment basin and diversions from erosion, in violation of 310 IAC 12-5-24(d), (e) and (g) at all diversions, inlets and side slopes of Basin #1 and Basin #3, the emergency spillway channel and the primary spillpipe outfall of Basin #3.

 

10. The Notice of Violation required Foertsch

 

(1) temporarily install and maintain straw bale energy dissipaters at regular intervals of 50 to 100 feet, in all diversions entering Basins #1 and #3, and pack gullies in side slopes of Basin #1 with straw bales;

(2) mulch side slopes of emergency spillway of Basin #3 and side slopes of diversions entering Basins #1 and #3 where soil materials has been either placed or unremoved;

(3) riprap primary spillpipe outfall of Basin #2;

(4) regrade inlets to Basins #1 and #3, side slopes of Basin #1 and riprap the last 75 feet of each inlet entering each basin, regrade emergency spill channel of Basin #3, seed and mulch all unprotected areas, seed all areas which have previously been mulched and install riprap check dams in diversions entering Basin #3 at regular intervals to prevent erosion.

 

11. The time frame set for abatement was February 26, 1985 for items (1), (2), and (3), and April 29, for item (4).

 

12. 310 IAC 12-5-24 contains the performance standards and design requirements for permanent and temporary impoundments.

 

13. 310 IAC 12-5-24(d) requires slope protection be provided to minimize erosion.

 

14.  310 IAC 12-5-24(e) requires all embankments to temporary and permanent impoundments and surrounding areas and diversion ditches disturbed or created by construction, shall be graded, fertilized seeded and mulched to comply with the requirements of 310 IAC 12-5-59 through 310 IAC 12-5-65 after the embankment is completed, provided that the active upstream face of the embankment where water will be impounded may be rip rapped or otherwise stabilized. Areas in which the vegetation is not successful or where

 

[VOLUME 12, PAGE 21]

 

rills and gullies develop shall be repaired and revegetated to comply with requirements of 310 IAC 12-5-57 and 310 IAC 112-5-59 through 310 IAC 12-5-65.

 

15. 310 IAC 12-5-57, as it existed on January 15, 1985, required rills and gullies deeper than nine (9) inches which develop in regraded and topsoiled areas and which are not vegetated or otherwise stabilized to be filled, graded or otherwise stabilized.

 

16. 310 IAC 12-5-59 through 310 IAC 12-5-65 contain the performance standards for revegetation.

 

17.   310 IAC 12-5-24(g) requires all dams and embankments shall be routinely maintained during the mining operations. Vegetation growth shall be cut where necessary to facilitate inspection and repairs. Ditches and spillways shall be cleaned. Any combustible materials present on the surface, other than material such as mulch or dry vegetation used for surface stability, shall be removed and all other appropriate maintenance procedures followed.

 

18. Basins #1 and #3 are used to retain water.

 

19. 310 IAC 12-1-3 defines in impoundment as a closed basin, naturally formed or artificially built, which is dammed or excavated for the retention of water, sediment or waste.

 

20. Basins #1 and #3 are either temporary or permanent impoundments subject to the requirements of 310 IAC 12-5-24.

 

21. A diversion, identified by the parties as the eastern diversion, was not constructed as a diversion by Foertsch, but was an area used to direct water into the basin by having water flow at a low point between stockpiled shale and into a basin.

 

22. The eastern diversion is a man made structure to divert water from one area to another.

 

24. [Misnumbered in Original Findings of Fact] This eastern diversion is a diversion ditch disturbed or created by the construction of a temporary or permanent impoundment, as defined by 310 IAC 12-1-3.

 

25. The eastern diversion had ungraded, unvegetated slopes, which were composed of shale and in which rills and gullies had developed.

 

26. A diversion identified by the parties as the southeast diversion was constructed by Foertsch with a backhoe, resulting in it having nearly vertical slopes, which had not been graded or vegetated and which were composed of shale. This diversion fed into Basin #3, and the sides of the diversion were eroded evidenced by rills and gullies.

 

27. Lack of vegetation on and failure to grade the side slopes of a diversion disturbed or created by the construction of a permanent or temporary impoundment is a violation of 310 IAC 12-5-24(e).[FOOTNOTE 1]

 

28. The southern inlet to Basin #1 was two to three feet deep, with unvegetated side slopes, parts of which had sloughed onto the bottom of the drainage was. The inlet was composed of spoil.

 

29. The northern inlet into Basin #1 had unvegetated side slopes, composed of spoil material, which had eroded.

 

30. The inlet to Basin #3 was eroded.

 

31. The emergency spillway channel to Basin #3 was eroding, did not have sufficient vegetative cover and insufficient slopes.

 

32. The primary spillpipe outfall of Basin #3 did have some rip rap, but was eroding.

 

33. The inlet into a permanent or temporary impoundment, the emergency spillway channel and the primary spillpipe outfall are areas surrounding a permanent or temporary impoundment.

 

34. Lack of vegetation on and failure to grade the slopes of an inlet into a permanent or temporary impoundment and emergency spillway channel is a violation of 310 IAC 12-5-24 (e).[FOOTNOTE 2]

 

35. Evidence of erosion occurring at the location of the outfall from a primary spillpipe is proof of a violation of 310 IAC 12-5-24(e).

 

36. The side slopes or embankment of Basin #1 was composed of shale, was not vegetated and had evidence of erosion in the form of gullies which had developed.

 

37. The side slopes or embankment of Basin #3 was composed of spoil material, was not vegetated and had evidence of erosion in the form of gullies.

 

38.  Evidence of gullies and loss of material on an unvegetated slope is unprotected from erosion.

 

39. Failure to protect the slopes on the embankments of a temporary or permanent impoundment to minimize erosion is a violation of 310 IAC 12-5-24(d) and 310 IAC 12-5-24(e).

 

40. Foertsch violated 310 IAC 12-5-24(d) and 310 IAC 12-5-24(e) at the diversions into Basin #1 and #3, at the inlets to Basin #1 and #3, at the emergency spillway channel of Basin #3 and at the primary spillpipe outfall of Basin #3.

 

 

FOOTNOTES:

 

1. Foertsch argues that because the material from which the diversions were constructed was spoil or non-prime farmland subsoil, the requirement to revegetate should not apply. They argue the requirements in 310 IAC 12-55-59 through 310 IAC 12-5-65 should only apply when reclaiming the area to its approved post mining land use. I disagree. 310 IAC 12-5-24 clearly requires that after the embankment of a permanent or temporary impoundment is completed, the surrounding area and diversion ditches disturbed or created by the construction of the impoundment are to be fertilized, seeded and mulched. This is a different requirement than the requirement for final reclamation to the approved post mining land use. The purpose of this requirement is to limit water pollution resulting from the active mining operation, primarily by preventing the impoundment from receiving contaminated water further

 

[VOLUME 3, PAGE 22]

 

contaminated by erosion of the diversion bringing water to the impoundment. The post mining land use requirements are designed to return the mined land back to a state of being capable of supporting the uses is was capable of supporting prior to mining of the land. If the rule had only intended the area be vegetated as part of the post mining land use, the rule would not have included temporary impoundments within its purview. The rules of statutory construction, which also apply to the construction of agency rules, require that no provision be interpreted to be meaningless, and when there appears to be a conflict between two rules the rules are to be constructed together to give effect to both rules. To do so in this case results in a conclusion that the surrounding areas and diversions into a temporary or permanent impoundment are to be vegetated during the mining phase, not just during final reclamation and when part of the post mining land use. Additionally the Department introduced a copy of the portion of permit S-00055 related to diversions. The mining and reclamation plan provided that the top and side slopes of diversions would be seeded to establish sufficient ground cover to prevent erosion (see Respondent's Exhibit 19). Foertsch's witness, who had written the plan for Foertsch, indicated he included this provision because it was required in order to have the permit application approved by the Natural Resources Commission. If such a provision was necessary in order to be granted approval for a permit to mine, obviously it is a provision which the Commission intended be complied with. Although this Notice of Violation was not issued for a violation of the permit, it could have been. Since the mining and reclamation plan is mandated by law, this evidence is persuasive that the top and sides of diversions are to be vegetated. It is obvious that both parties to this proceeding understood this to be a condition precedent to being able to obtain a permit to mine in Indiana, and as such, this condition should be complied with.

 

2. See Footnote 1.

 

3. The Director has previously established the elements of proof necessary to establish a violation of 310 IAC 12-5-24(g). In Amax Coal Company vs. Department of Natural Resources-Division of Reclamation, Administrative Cause No. 84-269R (NOV #N41016-S-00040), the Director held that a failure to maintain violation is appropriate where the failure is such that it either has caused or if it continues could cause the structure to short circuit, where is would have been possible to prevent the short circuiting, and the condition is being neglected or is the result of a failure on the part of the operator to take appropriate measures to keep the structure in good operation or repair. In this cause, the evidence was given to conclude that if the violation continued, it was likely that a violation of the effluent limitation would result.

 

4. Foertsch did not challenge the required abatement action or the time frame set for abatement, so no consideration is given to that part of the Notice of Violation.