CADDNAR


[CITE: Walthers v. DNR, 14 CADDNAR 57 (2016)]

 

 

[VOLUME 14, PAGE 57]

 

 

Cause #: 13-147W

Caption: Walthers v. DNR

Administrative Law Judge: Wilson

Attorneys: pro se (Walthers); Wooding (DNR)

Date: April 15, 2016                                                                         

 

 

[NOTE: ON MAY 16, 2016, WALTHERS TOOK JUDICIAL REVIEW IN THE MARION SUPERIOR COURT (49D06-1605-PL-017105).   ON JUNE 13, 2017, THE SUPERIOR COURT AFFIRMED THE COMMISSION. ON FEBRUARY 5, 2018, MATTER WAS TRANSFERRED TO MARION SUPERIOR COURT, ENVIRONMENTAL DIVISION. ON APRIL 13, 2018, THE ENVIRONMENTAL DIVISION ENTERED “ORDER ON PETITION FOR JUDICIAL REVIEW AND ORDER ON MOTION FOR ORDER ENFORCING ADMINISTRATIVE FINAL ORDER”.  ON JULY 3, 2018, THE MARION SUPERIOR COURT, CIVIL DIVISION 12 ENTERED COURT’S ORDER ENFORCING THE ADMINISTRATIVE FINAL ORDER.]

 

 

FINAL ORDER

 

1)     The NOV is affirmed.

 

2)     Walthers shall comply with the requirements identified under the section of the NOV identified as “Action Appropriate to Mitigate the Violation” by completion of either all of Action 1 or all of Action 2, within 90 days.

 

 

FINDINGS OF FACT AND CONCLUSIONS OF LAW

 

Statement of the Proceeding

 

1       On August 31, 2013, Paul Walthers (“Walthers”) and Ronald Richards and Carolyn Richards (“Richards”[1]) filed correspondence with the Natural Resources Commission (“the Commission”) requesting an administrative review of  Notice of Violation number VTS-DM-3951 (“NOV”), issued to Walthers and Richards by the Department of Natural Resources (“DNR”). 

 

2       Correspondence filed by Walthers and Richards avers that DNR issued an NOV to Walthers and Richards for “an alleged violation of Indiana Code (I.C.) 14-27-7.5….” and that Walthers and Richards “allege and contend that the basis and the engineering determination upon which the NOV was issued for Forest Lake Dam #32-17 is incorrect.”

 

3       Indiana Code (“IC”) 14-25.5 provides the authority to DNR to issue a NOV for the enforcement of IC 14-27, as relevant to this proceedingIC 14-25.5-1-1.  

 

4       The NOV, issued by the DNR Division of Water, was attached to the Petitioners’ correspondence and is dated August 22, 2013. DNR alleges, within the NOV, that Walthers and Richards violated IC 14-27-7.5 et seq., commonly known as the “Dam Safety Act”, pertaining to the regulation and classification of dams. The NOV states the following as the Nature of the Violation:

 

Forest Lake Dam is a high hazard dam (State Identification #32-17), and is located in Section 10, Township 15N, Range 1E, showing on the Brownsburg Quadrangle map, and within Hendricks County. 

 

A dam owner is required by Indiana Code (I.C.) 14-27-7.5 to keep the structure (dam) maintained in a safe condition by the exercise of prudence, due regard for life and property, and the application of sound and accepted technical principles.

 

Findings:

 

The owners of the Forest Lake Dam are Paul R. Walthers, and Ronald D & Carolyn Richards.

 

The Forest Lake Dam is an unsafe, unauthorized dam. There is no record of a permit issued for this dam or as-built engineering plans proving the structure was properly designed and constructed. A high hazard inspection report has not been received for the structure as required by I.C. 14-27-7.5.

 

The owners of the Forest Lake Dam have failed to maintain and keep the structure in the state of repair and operating condition required by the exercise of prudence, due regard for life and property, and the application of sound and accepted engineering principles which is a violation of Indiana Code 14-27-7.5.

 

The owners have not complied with the recommendations of the February 23, 2013 letter which asked that the owners to complete a series of scheduled actions including retaining registered professional engineer experienced in dam design, performing high hazard inspection reports and submitting such reports to DNR. Also requested was a lowering of the lake to safer level until safety deficiencies could be resolved. These actions and the failures to act are violations of Indiana Code 14-27-7.5.

 

5       NOV’s issued pursuant to IC 14-25.5, are addressed procedurally by IC 4-21.5-3-6, and become effective unless a person timely requests administrative review under the Administrative Orders and Procedures Act, commonly referred to as “AOPA”.  IC 14-25.5-2-4 and IC 14-25.5-2-5.

 

6       The correspondence filed by Walthers and Richards timely initiated administrative review under AOPA and the administrative rules adopted by the Commission at 312 IAC 3-1 to assist with the implementation of AOPA. IC 14-10-2-3.

 

7        The Commission is the “ultimate authority” with respect to the subject matter of the instant proceeding and it has adopted rules at 312 IAC 10.5 to assist with the administration of the Dam Safety Act. IC 4-21.5-1-15 and 312 IAC 3-1-2.

 

8       The Commission has jurisdiction over the subject matter of this proceeding and over the persons of the parties.

 

9       The Commission’s Administrative Law Judge (“ALJ”), Stephen Lucas, was appointed and assigned the proceeding. Following the retirement of ALJ Lucas, ALJ Dawn Wilson accepted the appointment and assignment of this case as a substitute qualified ALJ. IC 14-10-2-2.

 

[VOLUME 14, PAGE 58]

 

10    DNR was represented throughout the proceeding and was represented by Attorney Sean Wooding at the administrative hearing.

 

11    The Richards were represented by John Mervilde and Nicholas Gahl. The Richards were no longer parties to this matter when the administrative hearing was heard.

 

12    Walthers was self-represented throughout the proceeding.

 

13    Following the issuance of notice to Walthers, Richards, and DNR, ALJ Lucas conducted a prehearing conference on October 2, 2013, in Indianapolis, Indiana. The Report of Initial Prehearing Conference and Notice of Second Prehearing Conference, dated October 3, 2013, records a summary of the events that occurred during the prehearing conference. ALJ Lucas ordered DNR to file a statement of contentions by November 18, 2013. The Petitioners[2], were each ordered to file and serve their statements of contention by December 18, 2013, including any applicable affirmative defense. [3]

 

14    DNR filed a statement of contentions on November 18, 2013. The statement alleged specific violations on which DNR based its NOV.

 

15    Walthers filed a response to DNR’s statement of contentions on December 16, 2013, but no statement of contentions. Walthers asserted in his response to DNR’s statement of contentions:

 

a        “IC 14-27-7.5-1 specifically states that the chapter does not apply to properties such as Lake Forest.”

b       Walthers states he “became a lake dweller in 1966 and purchased the lake and dam properties in 1972. …When the lake was first developed no water entered the property from the north of the railroad and Highway 36. The watershed was less than a half square mile. Over the years, the state and county agencies’ programs diverted watershed into Lake Forest.” He asserted that it is “against the law to change the natural watershed to a neighbor’s property and thereby cause said neighbor to have problems.” He asserted that the consensus of three Indiana Legislators and numerous Hendricks County government officials is that if DNR declares the dam is a high hazard problem, “the DNR should fix it.”

c       Walthers acknowledged that he was informed, in writing, that the dam was classified as a high hazard dam in 2003. However, Walthers asserts that the “risk of damage to the dam and adjoining lake properties is very minimal.”

 

16    The issues were assigned to mediation on January 14, 2014. A Mediator’s Report was filed stating that the parties met and mediated on February 24, 2014. The mediator’s report stated that mediation did not result in agreement but that the parties requested additional time to further explore settlement options.

 

17    On July 23, 2015, a status conference was heard, following the filing of status updates by the parties, as requested by the ALJ. Thereafter, the following prehearing orders were issued by order dated July 24, 2015:

 

a       The parties were ordered to exchange Preliminary Witness and Exhibit Lists on or before August 27, 2015.

b       Discovery was to be completed on or before October 1, 2015.

c       The parties were ordered to exchange and file Final Witness and Exhibit lists on or before October 13, 2015.

d       A Final Status Conference was set for October 26, 2015.

e       An administrative hearing was scheduled to be heard on November 9, 2015.

 

18    Upon motion by Richards, prehearing deadlines were extended and the hearing date was vacated to allow the parties the opportunity to discuss settlement. The date originally set for a Final Status Conference was converted to a Second Status Conference and the Final Status Conference was reset to be heard on December 15, 2015.

 

19    During the Second Status Conference on October 26, 2015:

 

a       The discovery deadline was extended to November 16, 2015.

b       The deadline to exchange Final Witness and Exhibit lists and to file the Final Witness and Exhibit List with the ALJ was expanded to include an exchange of all potential exhibits between the parties by December 1, 2015.  The prehearing order states, “Any exhibit not exchanged may be excluded from consideration at a hearing, upon objection by any party, at the discretion of the ALJ.”

c       The hearing was reset to be heard on February 8, 2016.

 

20     On November 17, 2015, having resolved maters through settlement, DNR and Richards filed an Agreed Settlement and Stipulation of Dismissal.[4] The ALJ issued a Final Order of Dismissal as to Ronald and Carolyn Richards on November 18, 2015.

 

21    On December 1, 2015, DNR and Walthers each filed witness and exhibit lists.

 

22    On December 15, 2015, during the Final Status Conference:

 

a       DNR asserted that no potential exhibits had been received from Walthers. Walthers did not dispute DNR’s assertion. Yet again, the ALJ ordered Walthers to provide his potential exhibits to DNR and set an additional deadline, December 28, 2015.

b       The ALJ granted DNR’s request for a more specific delineation of witnesses in Walthers’ witness and exhibit list for potential witnesses identified as “lake dwellers” and “forthcoming experts.” 

c       DNR also advised that numerous Interrogatories were received from Walthers on November 16, 2015, and requested additional time to respond to the request. DNR’s request was granted.

d       To allow Walther’s an opportunity to review DNR’s Interrogatory responses, Walthers was allowed to file an appropriate amended witness and exhibit list before January 21, 2016.

e       A Supplemental Final Status Conference was set for January 29, 2016.

f        The hearing date, February 8, 2016, remained unchanged.

 

23    On January 12, 2016, an email from Lisa Walthers was received by the ALJ requesting a meeting to discuss the settlement terms between DNR and Richards. On January 14, 2016, an Order Denying Petitioner’s Request to Meet with the ALJ was issued.

 

24    On January 29, 2016, a Supplemental Final Status Conference was heard:

 

a       DNR asserted that Walthers had not provided any potential exhibits to DNR. Walthers confirmed DNR’s assertion to be true. The ALJ informed Walthers orally and in the written summary of the conference that his disregard of the ALJ’s prior orders regarding the exchange of potential exhibits could prevent the admission of documents that he might offer at hearing.

b       DNR reported that it had received an amended witness and exhibit list from Walthers. The amended list was not filed with the Commission, contrary to the ALJ’s order.

 

25    On February 8 and 9, 2016, Walthers and DNR attended the administrative hearing, in Indianapolis, Indiana. Walthers appeared, self-represented, who was accompanied by his daughter, Lisa Walthers. DNR appeared by counsel, Sean Wooding, who was accompanied by DNR Attorney Ed Harcourt and Jon Eggen, DNR’s Division of Water, Compliance and Enforcement Manager.

 

[VOLUME 14, PAGE 59]

 

 

Findings of Fact[5]-DNR Jurisdiction to Regulate Forest Lake Dam

 

26    Walthers challenges DNR’s jurisdiction to regulate Forest Lake Dam.

 

27    Jon Eggen (“Eggen”) has been the Manager of the Compliance and Enforcement Section of the DNR Division of Water since 2007. Eggen conducts inspections, supervises inspections, reviews documents and drafts warning letters and violations, including required time frames and optional mitigation, if applicable. See testimony of Eggen.

 

28    A stream runs to and through Forest Lake. See testimony of Eggen.

 

29    DNR claims jurisdiction over dams that have at least one of three criteria. One criterion is that the dam has a drainage area that exceeds one square mile. The second is when a dam is at least 20 feet in height. The third is when the structure impounds at least 100 acre feet of water.

 

30    Susie Delay (“Delay”) is a Hydraulic Engineer in the Compliance and Enforcement Section of the DNR Division of Water. Delay has worked for DNR for 20 years, with over two years in her current capacity. In her position, Delay performs inspections for potential and ongoing violations and she prepares engineering documentation for all active violations including computer modeling and calculations for dam safety. Delay calculates breach assessments to determine the impact of a catastrophic dam failure on structures downstream, including residential, commercial and bridges. Her calculations concerning that impact are used by DNR in hazard determinations. See testimony of Delay and Eggen.

 

31    Delay determined the height of the structure to be 19 feet, calculated at the top of the dam, Delay determined the volume of water impounded to be 55 acre feet. See testimony of Delay and Exhibit H[6].

 

32    DNR is not claiming jurisdiction over the dam based on the height of the dam or the volume of the impoundment. See testimony of Knipe.

 

33    DNR rests its authority to regulate the Forest Lake Dam on its determination that the drainage area of Forest Lake Dam is more than one square mile. See testimony of Knipe.

 

34    David Knipe is the Engineering Section Manager, for the Central Basin Team for DNR’s Division of Water. Knipe has been with DNR for over 24 years. Knipe manages engineering functions within the Division of Water, including flood plain mapping and hydraulics. See testimony of Knipe.

 

35    On behalf of DNR, Knipe calculated the drainage area above the Forest Lake Dam. Knipe conducted his analysis by using “ArcHydro” software, an ArcGIS mapping program and StreamStats, an online product available to the general public through the United States Geological Survey (USGS) website. With these products, he reviewed “one foot contour mapping” that he obtained from Hendricks County records and subdivision plans for the upper end of the watershed. See testimony of Knipe.

 

36    Knipe preformed an analysis and determined which way water flows in the area above the dam. He then concluded that the watershed, or drainage area, is approximately 1.23 square miles. See Testimony of Knipe, Eggen and Exhibits F and G.

 

37    Walthers refuted the conclusions reached by Knipe by producing maps indicating watershed areas of less than one square mile for an area above Forest Lake.  However, the drainage areas addressed by those maps begin at a point upstream of the lake and do not include the area of Forest Lake itself. See testimony of Walthers, Eggen and Exhibits 1 and 2.

 

38    ALJ finds that the drainage area of Forest Lake is approximately 1.23 square miles.

 

39    Walthers argues that growth in Hendricks County, and specifically Avon, has increased the “watershed” of Forest Lake. Walthers’s offers no evidence to support a change in the area of the watershed[7]. See testimony of Walthers.

 

 

Findings of Fact- NOV basis: High Hazard Classification & Inspection Reports

 

40    Within Walther’s response to DNR’s statement of contentions Walthers states that he received a letter from DNR identifying the Forest Lake Dam as “high hazard” in 2003. No evidence of this notification was provided by either party. Walthers now requests reconsideration of the Forest Lake Dam classification as a high hazard dam.

 

41    In 2004, DNR staff informed Walthers that Soliman Sherkawi, Engineering Geologist informed Walthers that the Forest Lake Dam was classified as a “significant hazard dam.”  When Walthers was asked if there was any “new development downstream, he said that there is a road and a bridge under it.” It is unclear from the evidence whether the hazard classification reported by DNR indicated a change from the initial high hazard classification or if the determination was based on the information provided by Walthers, which omitted disclosure of the subdivision. See Exhibit 7.

 

42    Dam hazard classifications change over time, depending on what is found to be downstream of the dam. See testimony of Eggen and Exhibit 7.

 

43    Delay determined a breach assessment for the Forest Lake Dam. She analyzed best available data and established hazard calculations, based on a catastrophic breach of Forest Lake Dam on a sunny day. Her determinations were based on sunny day breach calculations so as to consider only the water potentially impounded by the dam, without additional water from rain. Based on the height of the dam and the volume of the impoundment at the top of the dam, Delay established a total dam break breach discharge to be “5037 cfs”. See testimony of Delay and Exhibit H.

 

44    Delay then calculated the impact of such a failure downstream, based on the surface elevations within the “maximum breach inundation area”. She captured water surface elevations to establish a flow path at various cross sections on the map identified as Exhibit H. As she expected, her calculations revealed lower water surface elevations further from the breach point. Based on her calculations, she determined the breach inundation area included a county road and structures, specifically homes, and found that some homes were above breach elevation. She determined that 29 homes were within the breach inundation area, with 12 having the home’s lowest adjacent grade at least one foot below the elevation, or a flood depth of over one foot, inside those structures. Her determinations are based on her mathematical calculations of the best available information, not utilization of software. See testimony of Delay and Exhibit H.

 

45    Delay determined, based on her calculations and analysis, that Forest Lake Dam should be classified as a high hazard structure. See testimony of Delay and Exhibit H, page 2.

 

46    Walthers does not believe that the dam is a high hazard dam because the volume of water in the lake would not create an actual threat to life and property downstream. To support his assertion, Walthers reports that there is quite a bit of sediment in the lake. In addition, he measured the depth of the lake at various points on the lake from a boat. He acknowledges that his measurements are “not all that accurate”, but he believes that the depth would not create a danger downstream. See testimony of Walthers.

 

[VOLUME 14, PAGE 60]

 

47    It is noted that Delay’s calculations are based, in part, on the height of the dam and the potential impoundment of the lake. Walthers’s calculation is based on the water level at various points on the lake on a specific but undisclosed date. A maximum breach inundation area, as defined by 312 IAC 10.5-2-7 includes an uncontrolled release of a dam’s contents when “the impoundment is at maximum design pool elevation.”  Delay’s calculations would be the appropriate figures to use when calculating the impacted area below the dam. 312 IAC 10.5-2-7.

 

48    Walthers argues that the Forest Lake Dam should not be designated as a high hazard dam because he believes DNR approved downstream residences in the neighborhood of Thornridge. Walthers argument is not supported by the facts. See testimony of Walthers and Exhibit 3.

 

49    To support his contention, Walthers submitted a DNR permit from 1995, for  construction activities within the floodway consisting of “two 14” diameter storm sewer outfall pipes with with metal end sections, and approximately 30 linear feet of a grass swale with 4:1 side slopes.” The permit also included a reference to riprap to be placed at the base of the outlets for energy dissipation. The permit states that the residential subdivision would be developed landward of the floodway except portions of Lots 13, 14 and 15. The permit applicant was “Thornridge, Inc.” See Exhibit 3.

 

50    DNR’s authority under the Flood Protection Act includes the authority to issue permits for construction in a floodway, here the unnamed tributary to White Lick Creek. A DNR memorandum, dated April 7, 1995, states that plans for the project proposed would not “decrease the cross-section flow area of the stream.” The locations of the houses within the Thornridge subdivision are not in the floodway and were not included in the permit issued by DNR. See testimony of Eggen and Exhibit 3.

 

51    The ALJ finds that Walthers’ evidence does not support his contention that DNR approved the Thornridge subdivision. The ALJ also finds that a DNR permit approval does not equate to approval of the underlying project for which a permit is requested.

 

52    George Crosby (“Crosby”) is the Manager of Dam and Levee Safety Section for DNR and has been in his current position for over 25 years. He possesses a Master’s Degree in Engineering Geology from Purdue. See testimony of Crosby.

 

53    While DNR’s dam safety program began in the early 1960s, Crosby recalls that there were changes to the law in 2002 which thereafter, required high hazard dam owners to file reports. See testimony of Crosby.

 

54    Ken Smith (“Smith”) is a Civil Engineer and the Assistant Director of the DNR Division of Water, with over 39 years of experience with DNR. Smith currently oversees four sections: (1) enforcement, (2) surveying, (3) project development and (4) dam safety. See testimony of Smith.

 

55    Smith participated in a site visit of Forest Lake Dam prior to issuance of the NOV.  He determined that one basis for the NOV issued was that the owners had not submitted the reports required for a high hazard dam reflecting the owner’s engineer’s inspection findings. See testimony of Smith.

 

56    On the date of the administrative hearing, none of the required inspection reports had been submitted by Walthers. No contrary evidence was presented that alleged inspection reports had been filed by Walthers. See testimony of Smith.

 

 

Findings of Fact - NOV basis: State of Repair/Operating Condition

 

57    Walthers estimates that Forest Lake Dam was built 75 years ago. See testimony of Walthers.

 

58    Walthers was a “caretaker” of the dam for 50 years and was engaged in “taking care of the litter”, including the removal of leaves, tree limbs and other debris. He acknowledges he placed sandbags at the primary spillway but asserts the placement was designed to be temporary. See testimony of Walthers and Exhibit D.

 

59    Walthers acknowledges that he has not actively cared for the dam since 2013. See testimony of Walthers.

 

60    Crosby estimates that Forest Lake Dam was built over 50 years ago and that its design and construction were not originally permitted by DNR or its predecessor. See testimony of Crosby.

 

61    Since the construction of Forest Lake Dam, there have been no DNR permits issued to authorize alterations to the dam, such as observed changes to the principle spillway and the placement of fill in the abutment zone of the dam. See testimony of Crosby and Exhibit J-17.

 

62    Walthers acknowledges that he has made alterations to the structure and has “worked hard” to eliminate erosion. He constructed a retaining wall to keep the water from traveling down the road and washing out the bridge. Walthers made alterations to the dam because he observed an increase in water flow into his lake from the Town of Avon. Over time, he has had as many as 10 engineers on the dam. However, when making various alterations to the dam, Walthers did not use plans developed by one or more engineers. See testimony of Walthers.

 

63    Walthers states that he has built several subdivisions and has a general science degree from Purdue, as well as other master’s degrees in undisclosed disciplines. Walthers is not a licensed engineer but he claims to possess information and experience concerning “how things work” and he believes that engineering specifically related to dams is “not all that complicated”.  While a couple of engineers live on the dam, Walthers reports that “we are not licensed super hydraulics experts, no we’re.., none of us.” See testimony of Walthers.

 

[VOLUME 14, PAGE 61]

 

64    Crosby’s perspective of dam safety generally is that it is a multi-disciplinary science. Crosby oversees technical elements of the creation of new dams by working with the professional engineering teams hired by property owners, in the areas of site selection, planning and construction. Crosby ensures adequate supervision by a design engineer for construction permits. Once built, Crosby and his staff regulate dam maintenance and repairs, including the permitting of dam alterations. Crosby involves himself with the long term management of structures throughout the life of Indiana dams. For dams classified as high hazard, he reviews high hazard dam reports that are submitted, as required, every two years by the owners of high hazard dams. Crosby also acts as a general advisor to others, including other agencies, for issues involving dam safety. See testimony of Crosby.

 

65    Crosby asserts that, while all dams have some risk of failure, with proper upkeep and maintenance, dams can maintain an acceptable level of safety. The purpose of good engineering design, construction and maintenance is to reduce risk. Crosby analogizes an improperly designed, constructed and maintained dam to a bus with bad brakes and tires. “Not all busses with bad brakes and tires will crash but there is an elevated risk of a safety problem.” The standards required by DNR are minimally acceptable safety standards. While DNR regulates dams, dam owners are responsible to control and safely impound the water, and owners may choose higher standards than those required by DNR. See testimony of Crosby.

 

66    Delay conducted site visits and inspections of the Forest Lake Dam on several occasions. Every time she was there, she observed something that caused her concern and she expressed these concerns to her supervisors. See Testimony of Delay and Exhibit I.

 

67    Eggen observed the site of the Forest Lake Dam prior to the issuance of the NOV. He took photographs at the site to capture his observations of the general condition of the site. Eggen observed sandbags placed at the primary spillway raising the elevation of the lake. He also observed a structure within the lake that provided for drainage. Downstream from the lake, he saw a road and residences in a subdivision across the road.  After the site visit, he reached a conclusion based on his observations that the dam was in violation, because it was in disrepair, alterations had not been properly completed and that the dam presented potential safety concerns downstream. His conclusions resulted in the issuance of a warning letter on February 28, 2013, to Walthers concerning noncompliance in the care of the dam. In the correspondence, he included corrective measures that were recommended by DNR. See testimony of Eggen and Exhibit B and D.

 

68    Crosby and Delay conducted a site visit of the Forest Lake Dam on May 15, 2013. Crosby took photographs of items that concerned him about the “extremely poor maintenance and apparent multiple unauthorized modifications to the structure….” Specifically, on May 15, 2013, Crosby observed what he determined to be “serious issues” and deficiencies with the embankment, the primary spillway and the auxiliary spillway. See testimony of Crosby and Exhibit J-1.

 

a       Crosby observed the following deficiencies in the embankment:

i)      Large trees are on the crest of the dam’s embankment. The roots of living trees will break down soils that should be compacted and seek out the water tables. When trees die, their decaying roots will create flow paths for water and create voids in the dam, substantially weakening the strength of the dam. Also trees may be downed in a windstorm and may remove huge portions of the embankment of the dam. Trees also inhibit the proper inspection of a dam, in that trees prevent the ability to “sight across” and inspect for bulges that indicate potential problems.

ii)    An unauthorized utility shed is seen on the embankment. The placement of the shed is unacceptable because it prohibits inspection under the shed, it attracts animals to reside and burrow into the soils of the dam and it increases shedding of water in a rainstorm in a concentrated area.

iii)  Crosby observed uncompacted and potentially unstable fill on the downhill slopes as well as erosion, voids and depressions on the slopes.

iv)   Crosby observed buried and partially buried pipes in the embankment and noted water flowing outside a discharge pipe adjacent to the principle spillway, indicating internal erosion in the structure.

See the testimony of Crosby and Exhibit J-1, J-5, J-12, J-17, Exhibit K.

 

b       Crosby observed serious deficiencies with the design and maintenance of the principle spillway of the Forest Lake Dam.

i)      Crosby found that the location was not well suited for the open chute principle spillway found at Forest Lake Dam. He also observed that the open spillway system was not properly designed, in that it was built over manmade fill, and the spillway system was undersized. An appropriate design would include a closed large concrete box riser with an appropriate “trash rack” connected to a concrete box with seepage control features. An adequate design for an open cute principle spillway would include concrete slabs for the floor, a vertical retaining wall, a cut off wall and subsurface drains downstream for seepage control. None of those features appear in this dam, which resulted in erosion of the embankment, a sinkhole and weakening of the integrity of the dam. The inappropriate and inadequate design creates a risk of breach.

ii)    He also observed poor maintenance through cracks, missing rocks, and extensive erosion. He observed small and large voids providing dangerous flow paths for internal erosion. In addition, he found that the sides above the stilling basin of the primary spillway were nearly vertical and he observed that it had been patched together on numerous occasions. He observed erosion in this area and attempted repairs that did not appear stable. 

iii)  At the primary spillway, Crosby observed seepage at the end of a pipe indicating seepage from the collars and around the outside of the pipe, which causes internal erosion along the outside of the pipe. Walthers was not present when the photographs were taken but he denies that the photographs show water running outside the pipe. Walthers believes water in the photographs is running through the pipe, not around the pipe and is coming from the pipe in the lake. Crosby observed no water was entering the pipe in the lake on the day he took the photos. The photographs show water flowing out of the pipe as well as around the outside of the pipe. It is unclear from the photograph within the lake whether there is water flowing into the pipe from the lake. Uncontrolled seepage creates a safety issue because, as the water over the years saturates the soils, added pressure results which undermines the integrity of the dam. A properly designed dam would include appropriate subsurface controls to pick up the seepage and discharge it at points that can be monitored over the life of the structure. The Forest Lake Dam seepage, over time, will impact the integrity of the dam.

See testimony of Walthers, Crosby and Exhibit J-1, J-3, J-4, J-6, J-7, J-8, J-9, J-10, J-11, J-12, J-18, J-20.

 

[VOLUME 14, PAGE 62]

 

c       Also on May 15, 2013, Crosby observed serious unauthorized, improper alterations and deficiencies regarding the auxiliary spillway, also commonly referred to as an emergency spillway.

i)      He observed the addition of a concrete wall, reducing the capacity of the spillway system by blocking water flow.

ii)    Crosby observed damage to the spillway outlet with “cobbled” repair attempts from too frequent operation of the spillway. Crosby observed that fill had been added to the right abutment. It is unusual that the addition of soil would be needed and Crosby determined that the addition would require a permit to ensure it had been done as the owner and the owner’s engineer recommended and as the alteration had been approved. 

iii)  Crosby observed and photographed a view of the inlet for the emergency spillway showing concrete blocks, debris and a pontoon close enough to the inlet to block the spillway reducing capacity. In addition, he saw that there is no cut off wall in the area creating a risk for water to flow under the slab.

See testimony of Crosby and Exhibit J-17, J-18, J-19, J-20. 

 

69    Crosby prepared a report of the deficiencies that he observed. He summarized the deficiencies in a report and determined that “the dam and spillway have serious safety deficiencies and with time these problems will continue to worsen and threaten the integrity of the structure.”  See testimony of Crosby and Exhibit J-1.

 

70    Exhibit K includes an additional summary of deficiencies in Forest Lake Dam. See Exhibit K.

 

71    Smith determined that a basis for the NOV was that owners of the dam are responsible to maintain their dam in a safe state of repair. Based on his own observations and the reports from his staff with expertise in modeling and dam safety, he determined that the structure known as Forest Lake Dam had multiple serious deficiencies. See testimony of Smith.

 

72    Based on their education, experience and observations of the Forest Lake Dam over time, Crosby and Smith concluded that the Forest Lake Dam was not sufficiently strong; not maintained in a good and sufficient state of repair or operating condition; not designed to remain safe during infrequent loading events and unsafe; and dangerous to life and property, in accordance with the requirements found in IC 14-27-7.5-11. Based on information he personally gathered and information gathered by his staff, Eggen drafted NOV number VTS-DM-3951 and it was issued by DNR on August 22, 2013. See testimony of Eggen, Smith and Exhibit A.

 

73    Following the initiation of this proceeding, as a mitigation effort, Walthers put in a siphon system and some pipes. He also removed collars on the draw down structures in the lake. Those efforts are no longer functioning in that, at some later time, the collars and rigs were put back on the drain. See testimony of Smith.

 

74    Following the issuance of the NOV, Crosby conducted a site visit in July of 2015 and prepared an Emergency Log to document an event. The site visit followed the report of a major incident or emergency and revealed that the dam was in a state of progressive failure. Crosby predicted during his site visit memorandum in 2013, “The grouted principle spillway chute is seriously deficient and a probable location of where a breach of the dam could initiate….” In 2015, the principle spillway had failed and a “good portion” of the principle spillway chute was gone. See testimony of Crosby and Exhibit E.

 

75    The Richards worked with their “owner engineer”, Ross Holoway, a private professional engineer, who sent an email on July 10, 2015, stating, “The dam was in active failure with severe damage to the principle spillway.” See testimony of Crosby and Exhibit E, pages 6 and 13, and J-1.

 

76    Smith and Crosby concur that Forest Lake Dam is in a progressive state of failure. See testimony of Crosby and Smith.

 

77    In 2015, Smith met with Walthers, the Richards,[8] and the Richards’ professional engineer. A discussion concerning mitigation occurred so that the conditions seen on that day could be addressed due to impending rain. Lowering the water was stressed by the Richards’ engineer. Toward this end, Walthers removed two sections of the drawdown pipe in the lake to assist with the lowering of the lake. While minimal temporary measures were taken by Walthers at that time, the underlying violations have not been resolved. Contrary to Walthers’ desires, the Richards’ professional engineer worked with a contractor to alter the auxiliary spillway in order to reduce pressure on the primary spillway. See testimony of Smith and Exhibit E.

 

78    Forest Lake Dam was not properly designed or constructed and has not been appropriately maintained, which has resulted in placing people at risk downstream. Crosby asserted during the administrative hearing that Forest Lake Dam, in its current state, should be redesigned and reconstructed or decommissioned. See testimony of Crosby.

 

79    Smith determined that, with appropriate permits, the lake could be placed at a low water level, which would allow permitted redesign and reconstruction to occur. In recognition of the ongoing expenses of dam maintenance, an alternative would be for the dam to be decommissioned, a onetime cost. Decommissioning may be the least costly alternative. See testimony of Smith.

 

80    Crosby has observed that long term dam upkeep is expensive and commonly the costs associated with ownership are often spread out through mechanisms such as dam ownership by an association. See testimony of Crosby.

 

81    Crosby has determined that, if 2016 has a wet spring, it is not unlikely that Forest Lake Dam will experience a breach. Upon a breach, there is a high likelihood that an uncontrolled discharge would result in serious consequences downstream. Consequences could include a reduction in the values of downstream properties, property damage, as well as other consequences. Short of a full breach, in the event of an additional emergency event, people downstream may need to be evacuated, resulting in relocation costs. While the dam has not yet breached, the dam is in a progressive state of failure. See testimony of Crosby.

 

 

Findings of Fact-Walthers as appropriate NOV recipient

 

82    Walthers acknowledges that he owns 6.8 acres in Hendricks County, Indiana. He estimates his ownership interests encompass approximately 90% of the Forest Lake Dam structure, including the primary and auxiliary spillways for the dam, as well as the lake bed of Forest Lake. Walthers formerly owned but has now sold a residence that was on or near the lake. See testimony of Walthers.

 

83    Walthers states that the DNR “demand”, to rebuild the dam, is something he cannot afford. Decommissioning the lake is also cost prohibitive and he will require a court order to take that action, as lake dwellers, whose property values fall, and individuals whose wells are impacted, will consider litigation. He does not want to be in the position of being the one who makes changes to the dam. Walthers has neighbors who will hold him responsible for consequences of dewatering the dam. Walthers concluded, without a supporting basis for his conclusion, that DNR must decommission the dam and own the impact of the resultant changes. See testimony of Walthers.

 

84    Walthers believes that owners should take care of their property and that a dam owner should be responsible for a dam they own, with qualifications. He claims interference above and below the dam.

 

[VOLUME 14, PAGE 63]

 

a       Above the dam, he claims that the State of Indiana, Hendricks County, the town of Avon, the highway department and factories have interfered. See testimony of Walthers.

i)      Walthers believes that interference came in the form of increased storm water flowing into Forest Lake. Walthers asserts that if Hendricks County and the town of Avon, had not grown and added schools and subdivisions, and widened state highways, his “farm pond” and “dam” would have had few changes in the last 50 years. Walthers presented no evidence of his assertion, except for his personal observations and perceptions that the water flowing into Forest Lake has increased over time. See testimony of Walthers.

ii)    Walthers presents the question, “How can your office and the state of Indiana hold an individual responsible for an increase in surface water drainage of which I have no control? I feel my property rights, my civil rights and due processes are being aggressively violated by the Indiana Department of Natural Resource”. See testimony of Walthers.

iii)  Eggen reports that DNR has no authority to regulate the volume of surface water entering the watershed of Forest Lake. See testimony of Eggen. 

 

b       Below the dam, Walthers claims interference through the approval of the subdivision of Thornridge. See testimony of Walthers and Exhibit 3.

 

i)      DNR did not approve the residences within Thornridge. See testimony of Eggen and Exhibit 3. 

ii)    Walthers presented insufficient evidence of any other Thornridge approval that he determined would constitute “interference” with his property.

c       Walthers presented insufficient evidence of other actions, which he determined to be “interference” with his property.

 

85    Anecdotally, Walthers argued at the administrative hearing that there are other owners of Forest Lake Dam, the Richards. In fact, those owners were identified on the NOV at issue in this administrative cause. The Richards withdrew their request to contest the NOV. Walthers continues to contest the NOV but indicated his desire to “have the same deal”. See testimony of Walthers.

 

86    Walthers stated at the administrative hearing: “When you have people that come in from downtown that threaten you with $10,000 fines, $1,000 a day until we jump high enough and do whatever they ask me to do. And that was, that was when I walked away. Then in addition to that when I walked away, I had to sell my home because I was out of money and I was trying to sell my home before the neighborhood would go dead.” He informed the purchasers that there would probably be no lake ….”  He asserted that his plans are to “give everything up that he can” and “get out of town”. See testimony of Walthers.

 

87    Walthers stated that he would like for the State of Indiana to “meet their responsibility.” See testimony of Walthers.

 

 

Conclusions of Law

 

88    The jurisdiction of DNR[9]: is defined by IC 14-27-7.5-8(a) as follows:

 

i)      The department:

(1)  has, on behalf of the state, jurisdiction and supervision over the maintenance and repair of structures in, on, or along the rivers, streams, and lakes of Indiana;

(2)  shall exercise care to see that the structures are maintained in a good and sufficient state of repair and operating condition to fully perform the intended purpose;

(3)  shall grant permits for the construction and operation of structures in, on, or along the rivers, streams, and lakes of Indiana;

(4)  may adopt rules under IC 4-22-2 for permitting, maintenance, and operation that are necessary for the purposes of this chapter; and

(5)  may vary the standards for permits, maintenance, and operation, giving due consideration to the following:

(A) The type and location of the structure.

(B) The hazards to which the structure is or may be exposed.

(C) The peril to life or property if the structure fails to perform the structure's function.

IC 14-27-7.5-8(a).

 

89    The authority of DNR, to regulate dams in Indiana, both at the time of the NOV and the administrative hearing, is limited to dams that are not excluded by IC 14-27-7.5-1(B):

 

This chapter does not apply to the following:

(1)  A structure that meets the following conditions:…

(B) Has a drainage area above the dam of not more than one (1) square mile.

(C) Does not exceed twenty (20) feet in height.

(D) Does not impound a volume of more than one hundred (100) acre-feet of water….

       IC 14-27-7.5(B).

 

90    DNR is authorized to “Ascertain, determine, designate and define natural drainage and reclamation areas. …Prepare computations of the probable maximum quantity of water likely to be collected from a drainage or reclamation area…..  IC 14-27-1-1(4) and (5).

 

91    Forest Lake Dam is a structure, as defined by 312 IAC 14-27-7.5-5.

 

92    Forest Lake Dam is on or along a stream.

 

93    Forest Lake Dam has a drainage area above the dam of over one square mile.

 

94    The authority for DNR to regulate dams includes Forest Lake Dam.

 

95     As to the hazard classification, DNR may assign a rating, known as a hazard classification to a dam; “based on the potential consequences resulting from the uncontrolled release of its contents due to a failure or misoperation of the structure.” IC 14-27-7.5-2. 

 

96     Dam classifications are determined based on “best available information” to be “high hazard”, significant hazard” or “low hazard. IC 14-27-7.5-8[10] and 312 IAC 10.5-3-1.

 

97     When making the determination to classify a dam, DNR “…may consider observations of the dam and the vicinity of the dam, including the risk posed to human life and property if the dam fails.” 312 IAC 10.5-3-1(c)(1).

 

[VOLUME 14, PAGE 64]

 

98    A dam owner may request reconsideration of a hazard classification. “(b) The dam owner or other affected person may submit any technical information or reports that were not previously available to the division. (c) The dam owner's or other affected person's professional engineer may develop and submit a maximum breach inundation area and current damage evaluation assessing the downstream area affected by a dam breach. (1) If the maximum breach inundation area and current damage evaluation predicts any of the following, the dam shall be classified as high hazard: (A) Flood depths greater than one (1) foot in any occupied quarters. (B) Loss of human life may occur. (C) Interruption of service for more than one (1) day on any of the following: (i) A county road, state two-lane highway, or U.S. highway serving as the only access to a community. (ii) A multilane divided state or U.S. highway, including an interstate highway. (D) Interruption of service for more than one (1) day on an operating railroad. (E) Damage to any occupied quarters where the flow velocity at the building compromises the integrity of the structure for human occupation. (F) Interruption of service to an interstate or intrastate, utility, power or communication line serving a town, community, or significant military and commercial facility, in which disruption of power and communication would adversely affect the economy, safety, and general well-being of the area for more than one (1) day.” 312 IAC 10.5-3-2.

 

99    Walthers’ challenge in this proceeding is considered a request for reconsideration of the hazard classification. However, Walthers presented no technical information or report that was not previously available to the Division of Water to refute the classification. In addition, Walthers failed to present an assessment of the maximum breach inundation area prepared by a dam owner’s professional engineer.

 

100           An uncontrolled breach of the Forest Lake Dam would result in flood depths greater than one (1) foot within, on or about, 12 occupied quarters, as defined by 312 IAC 10.5-2-9, within the maximum breach inundation area, defined by 312 IAC 10.5-2-7. 312 IAC 10.5-3-2(c)(1)(A).

 

101           The Forest Lake Dam is properly classified as a high hazard dam.

 

102           The owners of a high hazard dam are required to file inspection reports. The reports are specifically identified in IC 14-27-7.5-9(a), which states:

 

The owner of a high hazard structure shall:

(1)  have a professional engineer licensed under IC 25-31 make an engineering inspection of the high hazard structure at least one (1) time every two (2) years;

(2)  submit a report of the inspection in a form approved by the department to the department. The report must include at least the following information:

(A) An evaluation of the structure's condition, spillway capacity, operational adequacy, and structural integrity.

(B) A determination of whether deficiencies exist that could lead to the failure of the structure, and recommendations for maintenance, repairs, and alterations to the structure to eliminate deficiencies, including a recommended schedule for necessary upgrades to the structure.

IC 14-27-7.5-9(a).

 

103           A professional engineer is “an individual who, because of special knowledge of the: (1) mathematical and physical sciences; and (2) principles and methods of engineering analysis and design; that are acquired by education and practical experience, is qualified to engage in the practice of engineering, as attested by the individual's registration as a professional engineer and license to practice engineering in Indiana under IC 25-31. 312 IAC 10.5-2-11.

 

104           No engineering inspection reports have been submitted by Walthers’ professional engineer licensed under IC 25-31.

 

105           DNR is obliged to issue a notice of violation under IC 14-27-7.5-11 to the owner of a high hazard dam who fails to “have the structure inspected…” or who fails to “perform recommended maintenance, repairs, or alterations to the structure…” or who fails to “biennially submit the inspection report…” IC 14-27-7.5-9(c).

 

106           The NOV issued by DNR, reflects the deficiency by the owners of Forest Lake Dam to have the dam properly inspected and to file required reports.

 

107           The deficiencies are accurately assessed in that no inspection reports have been submitted to DNR and the evidence supports the issuance of the NOV on that basis.

 

108           The NOV identifies an additional violation to be that Forest Lake Dam is an unsafe, unauthorized dam.

 

109           Forest Lake Dam was not initially permitted when it was constructed.

 

110           Walthers has performed unpermitted and improper alterations to the Forest Lake Dam.

 

111           The owner of a structure, defined by 14-27.5-5 as a dam[11] and its appurtenant works[12], regulated under IC 14-27-7.5, “shall maintain and keep the structure in the state of repair and operating condition required by the following: (1) The exercise of prudence. (2) Due regard for life and property. (3) The application of sound and accepted technical principles.” IC 14-27-7.5-7(a).

 

112           For a dam classified as a high hazard dam, following a required inspection, if the “licensed professional engineer who conducted the inspection determines that maintenance, repairs, or alterations to a high hazard structure are necessary to remedy deficiencies in the structure, the owner shall perform the recommended maintenance, repairs, or alterations. If the owner does not “perform the recommended maintenance, repairs or alterations to the structure” DNR is obligated to issue a NOV to the owner of the owner of the high hazard structure. IC 14-27-7.5-9(b) and (c).

 

113           If DNR finds that a structure is “ (1) not sufficiently strong; (2) not maintained in a good and sufficient state of repair or operating condition; (3) not designed to remain safe during infrequent loading events; or (4) unsafe and dangerous to life and property; the department may issue a notice of violation under IC 14-25.5-2.” IC 14-27-7.5-11.

 

114           DNR inspected the Forest Lake Dam and discovered, as supported by the evidence submitted during the hearing, that Forest Lake Dam is “(1) not sufficiently strong; (2) not maintained in a good and sufficient state of repair or operating condition; (3) not designed to remain safe during infrequent loading events; or (4) unsafe and dangerous to life and property…”, consistent with the requirements set forth in IC 14-27-7.5-11.

 

[VOLUME 14, PAGE 65]

 

115           Before the issuance of the NOV, DNR staff observed that the Forest Lake Dam was not found to be in a minimally acceptable state of repair and notified Walthers in writing on February 28, 2013.

 

116           On August 22, 2013, DNR issued the NOV in writing, detailing the violations of IC 14-27-7.5. The violations within the NOV are supported by the evidence presented at the administrative hearing. Forest Lake Dam is incorrectly designed, improperly maintained and in a progressive state of failure.

 

117           As it relates to the regulation of dams in Indiana, an owner “means an individual… who has a right, a title, or an interest in or to the property upon which the structure is located.” IC 14-27-7.5-4.

 

118           Walthers is an owner of real property which includes approximately 90% of the structure of  Forest Lake Dam, including the lakebed of Forest Lake, the primary and auxiliary spillways as well as a substantial portion of the embankment.  

 

119           Due to his ownership interests, the NOV should have been addressed to Walthers. The NOV was addressed to Walthers.  

 

120           Walthers’ argues that he should bear less than the full responsibility assessed to high hazard dam owners because DNR approved a downstream subdivision. This issue is not critically considered because the evidence does not support a conclusion that DNR approved the subdivision below the dam.

 

121           Walthers’ argues that he should bear less than the full responsibility assessed to dam owners due to the increase in surface water within the watershed of Forest Lake Dam over time. Walthers failed to provide evidence sufficient to support a finding that there has been an increase in surface water to the watershed, or drainage area, of Forest Lake Dam. Even if there is an increase, such an increase would not reduce Walthers’ responsibility as an owner of the dam as documented within the NOV.[13]

 

122           Walthers argues that he should bear less than full responsibility due to parts of the dam being owned by one or more other owners. Walthers and the Richards were identified in the NOV. The Richards settled their dispute with DNR and were dismissed from this proceeding. DNR’s authority to issue an NOV extends only to dam owners. Walthers did not identify any owner who was not named in the NOV.



[1] The Richards withdrew their request for administrative review prior to hearing. While some information regarding the Richards is included and relevant to this decision, Walthers is the sole remaining Petitioner.

[2] The Petitioners are also referred to as the Claimants throughout this proceeding.

[3] The parties were advised of AOPA’s prohibition against ex parte communication with the ALJ within the September 5, 2014, written notice setting the prehearing conference, orally during the prehearing conference and in the ALJ’s order summary of the prehearing conference. On August 4, 2015, following ex parte communication by Walthers to the ALJ, the communication was disclosed and distributed as required by IC 4-21.5-3-11(e). On August 13, 2015, following ex parte communications by Lisa Walthers, two additional disclosures with distribution were made by the ALJ, as required by IC 4-21.5-3-11(e).

 

[4] The Agreed Settlement and Stipulation of Dismissal states “Ronald and Carolyn Richards (Richards) and the Department of Natural Resources (DNR) hereby agree and stipulate to the dismissal of the Richards from this administrative action, with prejudice, as well as from any further action relating to the underlying Notice of Violation dated August 22, 2013 (VTS-DM-3951) and the purported regulated structure. Richards and DNR have resolved these matters via settlement.”

[5] Findings of fact that may be construed as conclusions of law and conclusions of law that may be construed as findings of fact are so deemed.

[6] DNR’s exhibits are identified by letters. Petitioner Walthers’ exhibits are identified by numbers.

[7] Walthers asserted that the watershed has increased but a reasonable conclusion is that Walthers assertion related to an increase in the volume of water within the watershed, not the area of the watershed, due to development above the dam.

[8] The Richards were parties to this proceeding at the time.

[9] The “department” referenced in IC 14-27-7.5-8 is the Department of Natural Resources, referenced as “DNR” in this decision.

[10] IC 14-27-7.5-8(b) requires the classification of three levels as follows: “…The hazard classification system must include the following classes of structures: (1) High hazard: A structure the failure of which may cause the loss of life and serious damage to homes, industrial and commercial buildings, public utilities, major highways, or railroads. (2) Significant hazard: A structure the failure of which may damage isolated homes and highways, or cause the temporary interruption of public utility services. (3) Low hazard: A structure the failure of which may damage farm buildings, agricultural land, or local roads.”

[11]‘"Dam" means an artificial manmade barrier, including appurtenant works, that meets the conditions as given in IC14-27-7.5-1”. 312 IAC 10.5-2-3.

[12] "Appurtenant works" means auxiliary features of a dam that are reasonably required for the safe and proper operation of the structure. The term may include each of the following: (1) The spillway system. (2) Outlet works. (3) Gates and valves. (4) Tunnels. (5) Conduits. (6) Levees. (7) Embankments. 312 IAC 10.5-2-2.

 

[13] The Commission’s jurisdiction in this case is limited to the NOV. This decision does not consider any redress Walthers may have with respect to any other claim. This decision expressly does not advance any position on any matter beyond the scope of this administrative review and the jurisdiction of the Commission.