CADDNAR
CITE: Moriarity v.
DNR, 14 CADDNAR 41 (2015)]
[VOLUME 14, PAGE 41]
Cause #: 12-094W
Caption: Moriarity v. DNR
Special Administrative Law Judge: Gibbs
Attorneys: Wray (Moriarity);
Wyndham (DNR)
Date: October 2, 2015
[NOTE: ON NOVEMBER 6,
2015, THE PETITIONERS FILED FOR JUDICIAL REVIEW IN THE GRANT SUPERIOR COURT IN
CAUSE NO. 27CO1-1511-PL-000073. ON AUGUST 29, 2016, THE GRANT SUPERIOR COURT
ENTERED ITS ORDER
AFFIRMING THE ADMINISTRATIVE DECISION.
IN DECEMBER 2016, MORIARITY SOUGHT APPEAL. ON FEBRUARY 13, 2018, THE COURT OF APPEALS
ENTERED ITS FINAL
ORDER (Moriarity v. Indiana Department of Natural Resources,
91 NE. 3d 642,645 (Ind. Ct. App. 2018)). ON MARCH 21, 2018, MORIARITY SOUGHT
TRANSFER.]
FINAL ORDER
- John
E. Moriarity and Mae E. Moriarity,
both jointly and severally, are hereby ordered to draw down the water
level in the Moriarity impounded lake to an
elevation of between 840 and 845 feet NAVD. They shall, both jointly
and severally consult with a professional engineer duly licensed in
Indiana pursuant to IC 25-31 qualified in dam construction, maintenance
and safety to develop a safe and appropriate dewatering plan for
accomplishing the draw down as herein ordered.
- The
water level of the impounded lake shall be maintained at between 840 and
845 feet NAVD until the Moriaritys, both jointly
and severally, have complied with the remainder of this Order as set forth
below in Paragraphs 3 and 5.
- John
E. Moriarity and Mae E. Moriarity,
both jointly and severally, are hereby ordered to comply with I.C.
14-27-7.5-9(a) by having their dam inspected by a professional engineer
licensed pursuant to IC 15-31 and qualified in dam construction,
maintenance and safety, and submitting a report of that inspection to the
DNR’s Division of Water within ninety (90) days of the issuance of a final
order in this proceeding. Such engineering inspection shall be
completed as required to fulfill the usual and customary requirements of
the DNR.
- John
E. Moriarity and Mae E. Moriarity,
both jointly and severally, are hereby ordered to comply with I.C.
14-27-7.5-9(b) by completing any maintenance, repair or alteration as
required to fulfill the usual and customary requirements of the DNR.
- In
lieu of compliance with Paragraphs 1 through 4 above, John E. Moriarity and Mae E. Moriarity,
both jointly and severally, under the direction of a professional engineer
pursuant to IC 25-31 and qualified in dam construction, maintenance and
safety, dewater, breach and permanently decommission the dam.
- John
E. Moriarity and Mae E. Moriarity,
both jointly and severally, are hereby ordered to pay the following civil
penalties for their violations of the Dams Safety Act as set forth in the
above Findings of Fact, Conclusions of Law:
a.
$5,000 for not submitting a high hazard inspection report in 2011 as
required by I.C. §14-27-7.5(a)
b. $5,000
for not maintaining and keeping their dam in a state of repair and operating
condition required by the exercise of prudence, due regard for life and
property and the application of sound and accepted technical principles as
required by I.C. §14-27-7.5-9(c).
FINDINGS OF FACT AND
CONCLUSIONS OF LAW
A. Statement of the Proceeding and Jurisdiction
- By their attorneys on
June 13, 2012, Mae E. Moriarity, John E. Moriarity, and John E. Moriarity
and Mae E. Moriarity, Husband and Wife (the “Moriaritys”) filed a “Petition for Administrative
Review” with the Natural Resources Commission (the “Commission”) in which
the Moriaritys sought administrative review of
NOV VTS-3933-DM (the “subject NOV”) issued by the Department of Natural
Resources (the “DNR”). The subject NOV averred the Moriaritys violated IC § 14-27-7.5 (sometimes referred
to as the “Dams Safety Act”) and IC § 14-28-1 (sometimes referred to as
the “Flood Control Act”). The Petition for Administrative Review
initiated a proceeding that is controlled by IC § 4-21.5 (sometimes
referred to as the “Administrative Orders and Procedures Act” or “AOPA”)
and rules adopted by the Commission at 312 IAC § 3-1 to assist with
implementation of AOPA. The Moriaritys and
the DNR are collectively the “parties”.
- Judge Stephen Lucas was
appointed as the administrative law judge under IC § 14-10-2-2.
Judge Lucas served a “Notice of Prehearing Conference” upon the
parties. The initial prehearing conference was conducted as
scheduled in Indianapolis on July 20, 2012. The Moriaritys
appeared by their attorneys and in person. The DNR appeared by its
attorney and through a Division of Water representative.
- On May 7, 2013, Judge
Lucas issued his Modified Interlocutory Order with Respect to Claimants’
Motion for Summary Judgment. Judge Lucas partially granted summary
judgment in favor of the Moriaritys. Judge
Lucas determined that the subject NOV was insufficient as a matter of law
as it pertains to relief sought by the DNR under the Flood Control Act and
312 IAC 10. Further, Judge Lucas concluded that there continued to
be a genuine issue of material fact as to whether the Moriaritys
were in violation of the Dams Safety Act and 312 IAC 10.5. The DNR
has the burden of going forward and the burden of persuasion with respect
to the elements of the subject NOV pertaining to the Dams Safety Act (I.C.
§14-27-7.5 et seq.) and 312 IAC 10.5.
- The final hearing in
this matter began on November 21, 2013, with Judge Lucas presiding.
- The hearing was not
concluded on November 21, 2013 and was reset. For various reasons,
the hearing was continued. Prior to the conclusion of testimony,
Judge Lucas retired from state service.
- On August 15, 2014,
Judge Lucas issued an “Order Setting Panel and for Striking. Upon
the completion of striking, on August 22, 2014, with the express consent
of the parties, Catherine Gibbs was appointed as Special Administrative
Law Judge by Judge Lucas.
- The hearing concluded on
December 2 and 3, 2014, with Special ALJ Gibbs presiding.
- The parties expressly
consented to and waived any objections to Special ALJ Gibbs conducting the
hearing and making findings based upon the testimony given on December 2
and 3, 2014 and the recorded testimony given on November 21, 2013.
- The parties stipulated
to the admissibility of Exhibits 1 through 24.
- The Commission is
the “ultimate authority” under AOPA and IC § 14-10-2-3 for administrative
review of DNR notices of violation, including those under the Dams Safety
Act and the Flood Control Act. Generally, Yoder v. DNR & Bouwkamp, 12 Caddnar 88
(2009).
- The Commission has
jurisdiction over the subject matter and over the persons of the parties.
[VOLUME 14, PAGE 42]
B.
Findings of Fact
- The following findings
of fact were entered by Judge Lucas on May 7, 2013 as part of the Modified
Interlocutory Order with Respect to Claimants’ Motion for Summary
Judgment. Findings of Fact (a) through (g) are expressly adopted
from Judge Lucas’ Modified Order and incorporated into this Order.
a. John
E. Moriarity and Mae E. Moriarty own real property as
Husband and Wife in Section 15 and Section 16, Township 24 North, Range 8 East,
Van Buren Quadrangle, Grant County, Indiana (the “Moriarity
real estate”).
b. The Moriaritys
caused a water impoundment to be constructed on the Moriarity
real estate.
c. The impoundment
was constructed without the prior written approval of the DNR and without a DNR
permit.
d. The impoundment is
formed by a dam that impounds a volume of water which greatly exceeds 100
acre-feet.
e. Because it does
not qualify for an exception under I.C. § 14-27-7.5-1, the dam that forms the
water impoundment is part of a “structure” as defined at I.C. §
14-27.-7.5-5. The structure is in operation and is subject generally to
the Dams Safety Act.
f. The Moriaritys are collectively the “owner” of a structure as
defined at I.C. §14-27-7.5-4.
g. The subject NOV was
issued by the DNR against the Moriaritys on May 14,
2012. A true and accurate copy of the subject NOV is incorporated herein.
- The water impoundment
was constructed sometime between 1998 and 2000.
- On November 21, 2013,
the parties stipulated that the dam structure is more than 20 ft high in some spots and impounds more than a volume
of 100 acre-feet of water.
- On November 21, 2013,
the parties further stipulated that the Moriaritys
did not apply for or obtain a permit to build the dam from the DNR.
- The Moriaritys
stipulated to Ken Smith’s qualifications. Mr. Smith testified that
he observed streams on the Moriarity real
estate.
- Photographs 32, 33, and
34, taken in 2008 and admitted as part of stipulated Exhibit 7, show water
flowing in a defined channel, rather than flowing over the entire surface
of the ground. Exhibit 7, photographs 19, 20, and 21 show the
culvert through which water is flowing in a defined channel.
- Photographs 31, 32, 33,
and 34
show a small wooden footbridge, under which water flows to the lake in a
defined channel.
- Mr. Smith, based on his
observations, believes that this dam qualifies as a high hazard dam.
Exhibit 11, Photograph 138 clearly shows a building in close proximity to
the dam. Further, George Crosby presented uncontroverted testimony
that the road, also seen in Photograph 138, is a heavily traveled
road.
- DNR presented evidence
of the dam’s many deficiencies, which could lead
to a failure. Exhibit 11, Photographs 138 and 139 show a
sinkhole. Exhibit 11, Photographs 140, 141 and 142 show water, a
sign of seepage. Exhibit 11, Photograph 146 provides evidence of
failure to properly compact the soil. Exhibit 11, Photographs 154 and 155
show deficiencies in construction and the materials used for the dam.
Exhibit 11, Photographs 167 and 168 show seepage, again an indication of
deficiencies in the dam construction and design.
- Exhibit 2 shows
intermittent streams in the area of the Moriarity
Lake and on the Moriarity real estate.
- Rodney Neese surveyed Moriarity Lake in 2007. His observations and
survey were documented in Exhibit 6A through 6E. He observed streams
flowing through a pipe in both areas D and area C. He saw streams at
inlet pipes 1 and 2. He observed defined channels at Inlet Pipes 1
and 2. The “V” shapes seen on 6A and 6B are indicative of stream
channels. He concluded that there are streams on the Moriarity real estate.
- Jon Eggen also visited
the Moriarity real estate. He observed
streams and, in particular, he noted a meandering stream channel. These
features were obscured by various activities undertaken at the Lake, including
earthmoving and flooding.
- The DNR witnesses relied
on various maps to determine whether streams exist on the Moriarity real estate, including aerial photography,
soil maps and Stream Stats.
Exhibit 25 and 26 confirm the presence of streams. Exhibit 2 supports the
conclusion that there were intermittent streams going into the Lake. The
DNR witnesses did not rely on topographic maps (Exhibit 1), as the scale
of this Exhibit does not show sufficient details. The DNR witnesses did
not use Exhibit 16, Streams and Lakes of Indiana, to determine whether
streams exist on the Moriarity real estate, as
this Exhibit did not provide sufficient detail and further was not meant
to be a reliable source of accurate information. Exhibit 17 was also not
used to determine if streams existed on Moriarity
real estate. This Exhibit was specifically restricted to drainage
areas of at least five miles. No one contended that this applied to the Moriarity real estate. Exhibit 18 was used to
determine the owner of the Moriarity real
estate.
- Gary Miller qualified as
a hydraulic engineer. While he did not visit the Moriarity
real estate, he reviewed the materials available on the Moriarity real estate, including the aerial
photographs and Stream Stats. He concluded after a review of all
documents that there were streams in the Moriarity
Lake, based on the following definition: a channel which captures surface
water runoff into channel for flow.
- Suzanne Dealy testified that she did a breach analysis of this
impoundment. The analysis confirmed that the impoundment constituted
a high hazard dam. Ms. Dealy’s conclusions
were submitted as Exhibit 24.
- George Crosby also
testified for the DNR. His conclusions were that the Moriarity
Lake was created by damming streams. During his visits to the Property, he
observed flowing water in defined channels in the area B.
- The U.S. Geological
Survey examined the soil survey maps and concluded that there were seven
(7) first-order intermittent channel segments and one (1) second-order
intermittent channel segments that crossed the Moriarity
real estate. Exhibit 23.
- Exhibit 11, Photograph
138 evidences the proximity of the dam to a church and a road, which Mr.
Crosby describes as a high traffic road.
- Heather Bobich testified for the Moriaritys
regarding the presence of streams on the Moriarity
real estate. She used regulatory guidance by the Army Corps of
Engineers, which defines a stream as a landform with an ordinary high
water mark. This is the only definition she used in her conclusion
that no streams existed on the Moriarity real
estate. She used Stream Stats to delineate the watershed.
She noted that 2012 was a hot and very dry year.
[VOLUME 14, PAGE 43]
- She visited the Moriarity real estate in 2012. She inspected the Moriarity real estate for dry stream beds or other
indications of streams that met the morphology of a stream. She
observed no channels or ordinary high water marks. In her opinion, an
ordinary high water mark is essential to identification of streams.
She did not observe a barren wave swept shore near the lake. She reviewed
the photographs admitted as Exhibit 7. Her conclusions were that the
photographs showed standing water or wetlands. She further testified
that none of the photographs showed a continuous ordinary high water mark.
- She also relied on her
observations of plant growth in determining whether streams existed on the
Moriarity real estate. She opined that one
indication of a stream would be a change in plant growth. She did not see
such a change in the plant growth in the photographs admitted into
evidence.
- She did not observe any
landform with a channel with defined banks, cut by erosion of water
through turf or soil with a bottom over which water flows for a
substantial period of the year or any landforms indicative of a
watercourse as defined in I.C.§ 14-8-2-304. She did not see any channels,
remnants or evidence of intermittent or ephemeral streams.
- John Moriarity
contacted the local area plan commission, the Army Corps of Engineers and
the Indiana Department of Environmental Management to determine the
requirements that these agencies might impose. He complied with
instructions from the IDEM. He also contacted the DNR in 2002 requesting
information regarding whether a permit was needed and what type of permit
was needed. Further, after consultation with the DNR, he undertook
modifications to the dam, such as the removal of trees and modifications
to the spillway. The Moriaritys established a
wildlife habitat on the Moriarity real estate.
- Scott Dierks reviewed the breach analysis conducted by
Suzanne Dealy. He found deficiencies in
the analysis. One deficiency was the assumption about the water
elevation. The DNR surveyor noted that the low point of dam is 858.7
feet. The analysis assumes the low point is 861 feet before the
Probable Maximum Precipitation (PMP) rain event occurs. The affect of this error would be to overstate the depth
of water and velocity of the water released in a breach.
- Mr. Dierks
also testified about Exhibit O. This Exhibit demonstrates an error
in the breach modeling. His analysis of the cross-sections prepared by the
DNR demonstrates that the DNR model failed to use complete water paths in
two (2) of the three (3) modeled flow paths. Exhibit P, which he prepared,
projects the continuation of water flow in the topography around the Moriarity Lake.
- He pointed out that the affect of these errors would be to lower the depth and
velocity of a flood as a result of a dam failure. Further, he pointed out
the breach analysis does not account for the effect the overflow path
shown in area G on Exhibit 6D would have on the depth and velocity of a
breach.
- He concluded that the
DNR’s breach analysis does not present a scientifically valid projection
of what would occur in the event of a breach because of alleged errors in:
(1) the starting surface elevation in the lake; (2) the height to which
water would rise in the lake; and (3) how water moves across the landscape.
He concluded that the effect of a breach is overstated due to assumptions
used in the model. However, he did not determine which classification this
dam fell under or whether the dam was a high hazard dam based on the
assumptions he would have used in place of the assumptions used by the
DNR.
- Ms. Delay rebutted some
of these points. She stated that elevation of 861 was provided by
the survey conducted by Mr. Neese. She further explained the principle of
ineffective flow. This principle reflects that water will not
effectively flow across areas where pooling occurs and accounts for the
vertical walls shown in Exhibit O. She stated that the breach analysis
takes ineffective flow into account. She included only the effective
flow area in determining whether the dam was a high hazard dam. The
model thus reflects the effective flow area for breach locations and flow
paths she modeled.
C.
Conclusions of Law
- The
Subject NOV was issued by the DNR pursuant to its authority under I.C. §14-25.5.
- The Commission is the
“ultimate authority” under AOPA and IC § 14-10-2-3 for administrative
review of DNR notices of violation, including those under the Dams Safety
Act and the Flood Control Act. Generally, Yoder v. DNR & Bouwkamp, 12 Caddnar 88
(2009).
- The Commission has
jurisdiction over the subject matter and over the persons of the parties.
- I.C. §14-27-7.5 is
referred to for purposes of this proceeding as the Dams Safety Act.
- Judge
Lucas concluded that the subject NOV was insufficient as a matter of law
as it pertains to relief sought by the DNR under the Flood Control Act and
312 IAC 10. This conclusion is expressly incorporated herein.
- All
of the witnesses offered by the DNR and Ms. Bobich
and Mr. Dierks are qualified to testify as
experts and are highly credible.
- Through
stipulations made at the hearing, the Moriaritys concede that this impoundment is a
“structure” as the Moriarity Lake impounds a
volume of more than 100 acre-feet of water and exceeds 20 feet in height
in spots.
- The
initial issue that must be addressed is whether the structure is subject
to the requirements of the Dams Safety Act. The DNR “has, on behalf
of the state, jurisdiction and supervision over the maintenance and repair
of structures in, on, or along the rivers, streams, and lakes of
Indiana”. I.C. §14-27-7.5-8(1)(a).
- The
DNR has the burden of proving that the structure is “in, on, or along the
rivers, streams and lakes of Indiana”.
- The
parties present differing interpretations of “in, on, or along the rivers,
streams and lakes of Indiana”. The Moriaritys
argue that the word “of” should be interpreted as meaning
possession. They presented the testimony of Dr. Colleen Warren that
the word “of” means possession, not location. While Dr. Warren is
qualified to testify as to her area of expertise, she is not an
attorney. There are specific rules for the interpretation of statutes,
which Dr. Warren did not apply in reaching her conclusion that “of”, as
used in the context of the statute, means possession. Therefore, her
testimony was not persuasive.
- In
statutory construction, “our primary goal is to ascertain and give effect
to the intent of the legislature. Gray v. D & G, Inc., 938
N.E.2d 256, 259 (Ind. Ct. App. 2010). The language of the statute itself
is the best evidence of legislative intent, and we must give all words
their plain and ordinary meaning unless otherwise indicated by statute. Id.
Furthermore, we presume that the legislature intended statutory language
to be applied in a logical manner consistent with the statute’s underlying
policies and goals. Id. However, we will not interpret a statute
which is clear and unambiguous on its face; rather, we will give such a
statute its apparent and obvious meaning. Ind. State Bd. of Health v.
Journal-Gazette Co, 608 N.E.2d. 989, 992 (Ind. Ct. App. 1993),
adopted, 619 N.E.2d 273 (Ind. 1993).” United States Steel Corp.,
et al v. Northern Indiana Public Service Corp. 951 N.E.2d 542,
552, (Ind. Ct. App. 2011).
- In
addition, “Statutory provisions cannot be read standing alone; instead,
they must be construed in light of the entire act of which they are a
part.” Deaton v. City of Greenwood, 582 N.E.2d 882, 885 (Ind.
Ct. App. 1991); Bourbon Mini-Mart v. IDEM, 806 N.E.2d 14, 20; 2004
Ind. App. LEXIS 586 (Ind. Ct. App. 2004).
- While
possession may be one of the definitions for “of”, it is not the exclusive
definition. In keeping with the primary purpose of statutory
interpretation, the language of the statute must be applied in a logical
manner. Chapter 7.5 requires the owners of structures to comply with
specific requirements, including, but not limited to, permitting,
reporting, inspections and maintenance. I.C. §14-27-7.5-4 defines “owner”,
as “an individual, a firm, a partnership, a copartnership,
a lessee, an association, a corporation, an executor, an administrator, a
trustee, the state, an agency of the state, a municipal corporation, a
political subdivision of the state, a legal entity, a drainage district, a
levee district, a conservancy district, any other district established by
law, or any other person who has a right, a title, or an interest in or to
the property upon which the structure is located.” If one applied
the Moriaritys’ definition, that is, that the
chapter only applies to structures on streams owned by the State of
Indiana, I.C. §14-27-7.5-4 would be completely superfluous.
[VOLUME 14, PAGE 44]
- “Further,
if a court determines that the statute or rule is ambiguous, it may look
to the agency’s interpretation for evidence of the legislative
intent. The Indiana Supreme Court, in Shell Oil v. Meyer, 705 N.E.2d 962, 976 (Ind. 1998) held,
“However, administrative interpretation may provide a guide to legislative
intent. ‘A long adhered to administrative interpretation dating from
the legislative enactment, with no subsequent change having been made in
the statute involved, raises a presumption of legislative acquiescence
which is strongly persuasive upon the courts." Board of
Sch. Trustees v. Marion Teachers Ass'n, 530
N.E.2d 309, 311 (Ind. Ct. App. 1988); accord Baker v.
Compton, 247 Ind. 39, 42, 211 N.E.2d 162, 164 (1965).
DNR’s long standing interpretation has been that it has jurisdiction over
privately owned structures that meet the requirements in I.C.
§14-27-7.5-8(1)(a).
- The
Special ALJ concludes that the legislature intended the Dams Safety Act to
apply to any structure in, on or along the rivers, streams or lakes owned
by any entity that falls under the definition contained in I.C.
§14-27-7.5-4, including, but not limited to, the State of Indiana.
- The
Dams Safety Act applies to the Moriarity
structure.
- The
parties also do not agree as to the definition of “stream”. The
DNR’s witnesses all provided definitions of “stream” as flowing water
through a defined channel. The DNR’s definition is consistent with
the definitions provided by the parties as Exhibit 3, which includes
definitions from both standard English
dictionaries and technical dictionaries. The Moriaritys
argue that Ms. Bobich’s definition should be
used. She relies upon the Army Corps of Engineers’ definition.
However, it is not necessary to use a technical definition of
“stream”. The legislature chose to use the word “stream” and chose
not to define it. As “stream” has a common meaning, the failure to
define it supports the conclusion that the legislative intent must have
been to use the plain and ordinary meaning. Further, the DNR’s
long standing interpretation relies on the ordinary and common meaning of
stream. Applying the rules of statutory construction, “stream” is
clear and unambiguous and requires no further interpretation.
-
The Moriaritys argue that due process requires
“ascertainable standards” and that the statute does not comply with this requirement.
“In order to satisfy due process, an administrative decision must be in
accord with previously stated, ascertainable standards.” Podgor v. Indiana University, 178 Ind.App. at 258, 381 N.E.2d
1274 at 1283 (Ind.App. 1978). “This
requirement is to make certain that administrative decisions are fair,
orderly and consistent rather than irrational and arbitrary. The
standards should be written with sufficient precision to give fair warning
as to what the agency will consider in making its decision.” Id.
- Given
that the word “stream” should be given its plain and ordinary meaning, the
Moriaritys’ arguments that the statute does not
present an “ascertainable standard” must fail.
- Mr. Smith, Mr. Crosby,
Mr. Neese, Mr. Eggen and Mr. Miller all testified that they observed
streams on the Moriarity real estate. The
water features in areas A, B, D of Exhibit 6D are streams. The fact
that water does not flow constantly is not determinative. Nor is
size. Moreover, Exhibit 23 provides additional support for the conclusion
that streams exist on the Moriarity real estate.
The DNR proved by a preponderance of the evidence that the structure is
built “in, on, or along the rivers, streams, and lakes of Indiana”.
- Further evidence in
support of this conclusion are the culverts that were present to create
dry crossings across the stream channels and the presence of tree lines,
as shown in Exhibit 7, Photographs 35 and 36.
- The
DNR has met its burden in showing that the Moriarity
Lake is a structure built on a stream of Indiana. Therefore, the DNR has
jurisdiction over the maintenance and repair of this structure.
- Having
concluded that the Moriarity impoundment is on a
stream of the State of Indiana, it is not necessary to determine whether
the impoundment is also a lake. However, for the sake of clarity, the
question is whether the structure is a “lake” will be addressed. As
applicable to the Dams Safety Act and 312 IAC 10.5, lake means “a
reasonably permanent body of water substantially at rest in a depression
in the surface of the earth, if both the depression and the body of water
are of natural origin or part of a watercourse. If part of a
watercourse, a lake may be formed by damming a river or stream.” 312
IAC 1-1-21(a).
- A
“watercourse” is a running stream of water fed from permanent or natural
sources. There must be a stream, usually flowing in a particular
direction, though it need not flow continuously. It may be sometimes
dry but must flow in a definite channel having a bed or banks. Black’s Law Dictionary, Sixth
Edition (1990).
- There
is no contention that this is a natural lake. However, the lake was
formed by damming the streams that were observed on the Moriarity real estate. These streams fall within
the definition of watercourse. The Moriarity
impoundment is consistent with definition of “lake”.
- The
next issue is whether the structure was properly classified as a high
hazard dam. I.C. §14-27-7.5-8(b)(1) states that a “High hazard” dam
includes a “structure the failure of which may cause the loss of life and
serious damage to homes, industrial and commercial buildings, public
utilities, major highways, or railroads.” If the structure is a high
hazard dam, I.C. §14-27-7.5-9 sets out the duties with which the owner
must comply, including, having a professional engineer inspect the
structure and report to the DNR.
- 312
IAC 10.5-3-1 states:
(a) The division
shall assign whether a dam is classified as:
(1)
high hazard;
(2)
significant hazard; or
(3)
low hazard;
based
on best information available.
(b) In making the
determination of assignment under subsection (a), the division shall apply
existing U.S. Army Corps of Engineers Phase 1 reports and other appropriate
documentation.
(c) The division
may also consider observations of the dam and the vicinity of the dam,
including the risk posed to human life and property if the dam fails.
(1) If an
uncontrolled release of the structure's contents due to a failure of the
structure may result in any of the following, the dam shall be considered high
hazard:
(A)
The loss of human life.
(B)
Serious damage to:
(i) homes;
(ii)
industrial and commercial buildings; or
(iii)
public utilities.
(C) Interruption
of service for more than one (1) day on any of the following:
(i) A county road, state two-lane highway, or U.S. highway
serving as the only access to a community.
(ii) A multilane
divided state or U.S. highway, including an interstate highway.
(D) Interruption
of service for more than one (1) day on an operating railroad.
(E) Interruption
of service to an interstate or intrastate utility, power or communication line
serving a town, community, or significant military and commercial facility, in
which disruption of power and communication would adversely affect the economy,
safety, and general well-being of the area for more than one (1) day.
(2) If an
uncontrolled release of the structure's contents due to a failure of the
structure may result in any of the following, the dam shall be considered
significant hazard:
(A)
Damage to isolated homes.
(B) Interruption
of service for not more than one (1) day on any of the following:
(i) A county road, state two-lane highway, or U.S. highway
serving as the only access to a community
(ii) A multilane
divided state or U.S. highway, including an interstate highway.
(C) Interruption
of service for not more than one (1) day on an operating railroad.
(D) Damage to
important utilities where service would be interrupted for not more than one
(1) day, but either of the
following may occur:
(i) Buried lines can be exposed by erosion.
(ii) Towers,
poles, and aboveground lines can be damaged by undermining or debris loading.
[VOLUME 14,
PAGE 45]
- The Moriaritys
moved to strike Suzanne Delay’s testimony regarding the breach
analysis. While there was sufficient evidence presented to call into
question some of Ms. Delay’s conclusions, there is no basis for striking
her testimony. Any evidence of inconsistencies in the report goes to
the weight of the evidence, not its admissibility.
- Further, even without
Ms. Delay’s testimony, there is sufficient evidence to support the DNR’s
conclusion that this is a high hazard dam. Visual classification is
appropriate in accordance with the rule, as stated above. Mr. Smith
and Mr. Crosby testified that there is a strong possibility that damage
could be done to nearby structures if the dam would fail. Because of
the proximity of the dam to the structures, there is a strong likelihood
that serious damage to homes and commercial buildings would result.
Exhibit 10, Photograph 181 and Exhibit 11, Photograph 138, shows the
proximity of a house and other structures to the dam. The maps in Exhibit
6 show the proximity of a county road (CR 200S/E. 28th Street)
to the dam. The DNR presented uncontroverted evidence that this is a high
traffic road.
- The next issue that must
be addressed is whether the Moriaritys violated
the requirements of the Dams Safety Act. The parties have stipulated
that the Moriaritys did not apply for a permit
for this dam. Further, the DNR presented uncontroverted evidence
that the Moriaritys did not comply with the
requirement to have a professional engineer inspect the dam every two (2)
years and submit a report to the DNR (I.C. §14-27-7.5-9(a)).
- The
DNR is authorized to assess civil penalties for violations of I.C. §14-27.
The NOV seeks an initial civil penalty of Thirty Five Thousand Dollars
($35,000) from the Moriaritys. The DNR assessed
a $10,000 fine for failure to obtain a permit (I.C. §14-27-7.5-8); a
$5,000 fine for failure to file an inspection report for a high hazard dam
(I.C. §14-27-7.5-9) in 2005, 2007, 2009 and 2011; and a $5,000 fine for
failure to “perform recommended maintenance, repairs, or alterations to
the structure.” I.C. §4-27-7.5-9(c)(2). The
DNR presented no evidence regarding the basis for the penalties
assessed.
- In
assessing civil penalties, there are four (4) factors which the Commission
considers. These are (1) whether the initial offense was deliberate;
(2) whether a violation continued unabated after notice by the Department;
(3) whether the person committing the violation worked in good faith to
remedy the harm; and (4) what immediate or potential harm was presented by
the violation to persons, property or the environment?
- Additional
factors that can be considered include: (1) whether the failure to
comply was willful or malicious; (2) whether the violator had corrected or
attempted to correct the violations; (3) whether the violator took any
abatement actions; and (4) whether actual environmental harm is occurring
or that such harm is imminent.
- The
following are mitigating factors. It is clear that the Moriaritys
made attempts to determine if permits were necessary by contacting the
local plan commission, the Army Corps of Engineers, the Indiana Department
of Environmental Management and the DNR. The DNR was not able to identify
specifically which permit the Moriaritys needed
for the construction of this lake. Further, the Moriaritys
attempted to correct some of the deficiencies that earlier DNR inspections
had identified. In addition, the Moriaritys
set aside a portion of the property as a wildlife habitat indicating that
the failure to comply with the DNR’s demands was not malicious.
- As
the effective date of the Dams Safety Act is 2002 and the dam was
constructed in 2000, no penalty is assessed for failure to obtain a
permit.
- The
Subject NOV is divided into two (2) parts. Part A attempts to
resurrect an enforcement action begun in 2007 and concluded in 2010 (Cause
No. 08-137W).
This enforcement action resulted in an order against John Moriarity only and in favor of the DNR. The DNR
attempted to enforce the order in Grant County. Grant County
Superior Court issued its Order Dismissing Case Due to Improperly Named
Defendant and Inability to Join Party Needed for Just Adjudication on
October 11, 2011. The Court refused to enforce the order as the
property is held by the Moriaritys as tenants by
the entirety and the order from the Commission was against John Moriarity alone. No penalties will be assessed for
violations that were the subject of this previous order.
- Part
B of the Subject NOV was based on an inspection done on November 21,
2011. The Moriaritys were aware that the
DNR considered this to be a high hazard dam, however, they failed to
comply with the requirement that a professional engineer inspect the dam
and submit a report to the DNR. Further, the Moriaritys
were aware that the DNR had found several alleged deficiencies and had
failed to take action to correct these deficiencies.
- In
the DNR’s proposed Findings and Conclusions, the DNR proposes an order
assessing a penalty of $763,200 based on continuing penalties assessed for
each day that the Moriaritys failed to comply
with the NOV. However, I.C. §14-25.5-2-3 states that the NOV
“becomes effective without a proceeding under IC 4-21.5-3 unless a
person requests administrative review under IC 4-21.5-3-6 within
thirty (30) days after receipt of the notice.” Emphasis added.
As the Moriaritys requested administrative
review, the continuing penalties did not accrue during the time this
matter was pending before the Natural Resources Commission.
- Mr. Smith’s and Mr.
Crosby’s testimony proves by a preponderance of the evidence that the dam
has deficiencies that require correction.