Contractors will work to patch and repave segments of I-465 and I-69 from U.S. 31 all the way down to I-70. 

This work is part of a Marion County Construction Plan that looks to erase winter damage done to area interstates. It's part of a statewide winter damage plan.
 
Work is scheduled to begin next week after Memorial Day. Crews will be doing night and weekend work from the end of May through October. 

Work will be completed in four different segments. Please use the map below for reference. At least one lane in each direction will always be open during this project.

Segments

Segment 1: I-465 E/W from White River Bridge to I-69

  • End of May to Middle of August
  • Crews will work on the eastbound inside lanes first
  • Work will be completed on nights and weekends 
  • 8 p.m. to 6 a.m. the next morning 
  • One lane will always be open in each direction 

Segment 2: I-465 E/W from U.S. 31 to White River Bridge 

  • Beginning of June to Middle of August 
  • Weekend lane closures 
  • 8 p.m. to 6 a.m. Monday morning 
  • One lane will always be open in each direction

Segment 3: I-69 N/S from I-465 to S.R. 37

  • Middle of June to End of July 
  • Work will be completed on nights and weekends
  • 8 p.m. to 6 a.m. the next morning 
  • One lane will always be open in each direction 

Segment 4: I-465 E/W from I-69 to I-70 

  • Beginning of August through October 
  • Work will be completed on nights and weekends 
  • 8 p.m. to 6 a.m. the next morning
  • One lane will always be open in each direction 

NE 465 construction

Crews will be using a machine called a zipper wall in much of this area of construction. The zipper wall allows contractors to work safely behind a concrete barrier wall. The machine moves the barrier wall to make traffic flow better and faster when it's time to move areas of construction.
 
You can watch a video of a zipper wall here
 