On November 18, 1998, a representative of the Indiana Department of Environmental
Management (IDEM) was driving in the area of Christenburg Road south of Pikes Peak (the
"Site") when he discovered Warford Construction Company installing 1600 feet of 3 inch water
main in a farm field along the side of the road. Construction workers at the Site told the IDEM
representative that George Miller, Water Utility Manager, instructed Warford Construction to put
in the line and he would apply for the permit later. There is no record of a construction permit
application having been submitted to IDEM for review.
The IDEM representative also noted a stream crossing at the Site which had no
encasement and no valving on either side of the stream. The failure to install this equipment in
the water line creates a threat to the public health.
Based on the above noted observations and information you were found in violation of
the following provision of the Indiana Code (IC):
IC 13-18-16-1 Public Water Supplies - Construction Permit Requirement
(a) A permit is required for the construction, installation, or modification of:
(1) sources;
(2) facilities;
(3) equipment; or
(4) devices; of a public water supply, including water distribution systems.
(b) Plans and specifications for the construction, installation, or modification of
sources, facilities, equipment, or devices of a public water supply must be
submitted to the commissioner with a permit application. The plans and
specifications must be complete and of sufficient detail to show all proposed
construction changes, or modifications that may affect the sanitary quality,
chemical quality, or adequacy of the public water supply involved. The applicant
shall supply any additional data or material considered appropriate by the
commissioner to a review of the plans and specifications.
(c) Unless otherwise provided in the rules adopted under section 8(b) of this chapter,
plans and specifications must be submitted to the commissioner with the permit
application for water distribution systems.
(d) Construction, installation, or modification of a public water supply may not begin
until the commissioner has issued a permit under subsection (a).
(e) In determining whether to issue a permit under this section, the commissioner
shall proceed under IC 13-15.
In accordance with IC 13-30-3-3, the Commissioner is required to notify you in writing
that the Commissioner believes a violation exists and offer you an opportunity to enter into an
Agreed Order providing for the actions required to correct the violations and for the payment of a
civil penalty. The Commissioner is not required to extend this offer for more than sixty (60)
days.
If settlement is not reached within sixty (60) days of your receipt of this Notice, the
Commissioner may issue an Order pursuant to IC 13-30-3-4, containing the actions you must
take to achieve compliance, the required time frames, and an appropriate civil penalty. Pursuant
to IC 13-30-4-1, the Commissioner may assess penalties of up to $25,000 per day of any
violation.
Entering into an Agreed Order will prevent the issuance of an Order of the Commissioner under IC 13-30-3-4 or the filing of a civil court action under IC 13-14-2-6. IDEM encourages timely settlement by Agreed Order, thereby saving time and resources. Timely settlement by
Agreed Order may result in a reduced civil penalty. Settlement discussions will also give you the opportunity to present any mitigating factors that may be relevant to the violations. In addition, as provided in IC 13-30-3-3, you may enter into an Agreed Order without admitting that the violation occurred.
For the Commissioner:
Date: December 17, 1998 _________________________
Felicia Robinson George
Assistant Commissioner of Enforcement
cc: Marylin Jupp, Drinking Water Enforcement
U.S. EPA Region 5
Brown County Health Department
Mr. Lennis Baughman, Vice President
Mr. James McDonald, Treasurer
Ms. Sarah Louis Kritzer, Secretary
Mr. Gary Snider, Board Member
Mr. Jack Arnold, Board Member
Mr. Jack Altop, Board Member
Mr. Ed Brown, Board Member
Brown County Water Utility Board Members
Mr. Lennis Baughman, Vice President
Brown County Water Utility Board
346 East Hurdle Road
Morgantown, IN 46160
Mr. James McDonald, Treasurer
5463 Beanblossom Road
Morgantown, IN 46160
Ms. Sarah Louis Kritzer, Secretary
4737 South SR 135
Nashville, IN 47448
Mr. Gary Snider, Board Member
6559 N. Spearsville Road
Morgantown, IN 46160
Mr. Jack Arnold, Board Member
8427 N. Spearsville Road
Morgantown, IN 46160
Mr. Jack Altop, Board Member
6660 Railroad Road
Morgantown,. IN 46160
Mr. Ed Brown, Board Member
3780 Yellowood Road
Nashville, IN 47448
Converted by Andrew Scriven