STATE OF INDIANA ) BEFORE THE INDIANA DEPARTMENT
) SS: OF ENVIRONMENTAL MANAGEMENT
COUNTY OF MARION )
COMMISSIONER OF THE DEPARTMENT )
OF ENVIRONMENTAL MANAGEMENT, )
)
Complainant, )
)
v. ) CAUSE NO. A-3632
)
EVANSVILLE-VANDERBURGH COUNTY )
SCHOOL CORPORATION, )
)
Respondent. )
5. Respondent implemented an asbestos removal project at Perry Heights Middle
School in Evansville, Indiana on or about June 24, 1996, to which the
requirements of 326 IAC 14-10 applied, pursuant to 326 IAC 14-10-1(c).
6. Rule 326 IAC 14-10-4(11)(B) which requires: For any RACM or suspect RACM,
when an ongoing asbestos project is interrupted for any non emergency situation,
all RACM that was disturbed, stripped or removed must be wetted and placed into
leak-tight wrapping and stored in a manner consistent with 326 IAC 14-10-
4(11)(A). If the RACM that was stripped, disturbed, or removed is not, or cannot
be collected, and placed into leak-tight wrapping and stored during the abatement
interruption, an accredited Indiana worker or supervisor, must remain at the job
site to prevent unauthorized persons from entering the work area. Asbestos
warning signs or labels must be posted on all entrances and exits to the work area.
7. On June 24, 1996, a representative of the Office of Air Management,
IDEM conducted an inspection at Perry Heights Middle School, 5800 Hogue
Road, Evansville, Indiana. The inspector inspected an asbestos abatement project
that was being implemented in the building's boiler room
by employees of
E-VSC. The inspector found the boiler room door open and no barricade tape
in place to restrict access to the boiler room.
The inspector did not observe any
workers in the area.
The inspector entered the containment and observed
asbestos debris on the floor of the containment, a violation of Rule 326 IAC 14-
10-4(11)(B).
8. The project supervisor for the asbestos removal project involved in the violations
is Richard W. Brown, Indiana accreditation number 194805024.
9. In recognition of the settlement reached, Respondent waives any right to
administrative and judicial review of this Agreed Order.
3. Respondent is assessed a civil penalty of Two Thousand Five Hundred Dollars
($2,500.00). Within thirty (30) days of the effective date of the Agreed Order, the
Respondent shall pay a cash penalty of Five Hundred Dollars ($500.00). The
payment shall be submitted to the Asbestos Trust Fund, as directed by paragraph
4. In lieu of payment of the remaining Civil Penalty, the Respondent shall
perform and complete the Supplemental Environmental Project ("SEP"), as
described in Exhibit A. Exhibit A is hereby incorporated by reference and made a
part of this Agreed Order. The total funds expended on the SEP shall be a
minimum of Six Thousand Dollars ($6,000.00). If the SEP is not completed in
accordance with this agreement and within the specified time period, the
Respondent agrees to pay the remaining amount of the Civil Penalty, plus interest
at the rate established by IC 24-4.6-1-101, to the Asbestos Trust Fund. Payment
of the remaining Civil Penalty shall be submitted within fifteen (15) days from
receipt of a notice to pay from IDEM. Interest on the remaining Civil Penalty
shall be paid from the effective date of this Agreed Order.
4. Civil penalties are payable by check to the Asbestos Trust Fund. Checks shall
include the Cause Number of this action and shall be mailed to:
Cashier
IDEM
100 N. Senate Avenue
P. O. Box 7060
Indianapolis, IN 46206-7060
By: _________________________ By: _________________________
David P. McIver, Acting Air Section Chief
Office of Enforcement Printed: ______________________
Title: ________________________
Date: ________________________ Date: ________________________
COUNSEL FOR COMPLAINANT: COUNSEL FOR RESPONDENT:
Department of Environmental Management
By: _________________________ By: ________________________
Office of Legal Counsel
Department of Environmental Management
Date: _______________________ Date: ______________________
APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL
MANAGEMENT THIS _____ DAY OF ____________________, 199___.
For the Commissioner:
Signed April 11, 1997
Patrick Carroll
Director
Office of Enforcement
Evansville-Vanderburgh County School County Corporation
Supplemental Environmental Project
Perry Heights Middle School, 5800 Hogue Road, Evansville, Indiana has a combination
asbestos/non-asbestos ceiling tile in the nine basement classrooms. The potential for damage to
the ceiling tile exists as long as the material remains in the building. Evansville-Vanderburgh
County School County Corporation proposes to abate approximately 2500 square feet of ceiling
tile in the three classrooms in the south wing of the lower level. The cost of the abatement,
disposal, air monitoring and sample analysis is estimated to be $6,000.00. The work shall be
completed by August 31, 1997. Advantages to this option include removal of asbestos from
student occupied space and the reduction of the total asbestos in this facility.
The Evansville-Vanderburgh County School County Corporation shall present
documentation of completion of the Supplemental Environmental Project to IDEM. The
documentation must be delivered to IDEM no later than September 30, 1997. The
documentation shall include work records, disposal records and the total project cost. Following
submission of the documentation, a representative of the Office of Air Management, IDEM will
conduct an inspection at Perry Heights Middle School to verify completion of the project.
Converted by Andrew Scriven