STATE OF INDIANA ) BEFORE THE INDIANA DEPARTMENT
) SS: OF ENVIRONMENTAL MANAGEMENT
COUNTY OF MARION )
)
COMMISSIONER OF THE DEPARTMENT )
OF ENVIRONMENTAL MANAGEMENT, )
)
Complainant, )
)
v. ) Case No. 2000-9255-W
)
THE CITY OF BATESVILLE, )
BATESVILLE WASTEWATER UTILITY, )
)
Respondent. )
AGREED ORDER
The Complainant and the Respondent desire to settle and compromise this action without
hearing or adjudication of any issue of fact or law, and consent to the entry of the
following Findings of Fact and Order. Pursuant to IC 13-30-3-3, nothing herein
constitutes an admission by the Respondent of any violation. On this basis, the parties
consent to the following:
I. FINDINGS OF FACT
- Complainant is the Commissioner ("Complainant") of the Indiana Department of
Environmental Management, a department of the State of Indiana created by IC 13-13-1-1.
- Respondent is the City of Batesville, Batesville Wastewater Utility, ("Respondent"),
which owns and operates the wastewater treatment plant (WWTP) and the 100% sanitary
sewer system, located at 25019 Underpass Road, and throughout Batesville, in Franklin
and Ripley Counties, and which is authorized to discharge to Little Laughry Creek, by
National Pollutant Discharge Elimination System (NPDES) Permit No. IN0039268.
- The Indiana Department of Environmental Management ("IDEM") has jurisdiction over
the parties and the subject matter of this action.
- Pursuant to IC 13-30-3-3, IDEM issued a Notice of Violation via Certified Mail to:
The Honorable William Abplanalp, Mayor
The City of Batesville,
Batesville Wastewater Utility
132 South Main Street
Batesville, Indiana 47006
- Record reviews, on February 9, 2000 and July 27, 2000, were conducted by
representatives of IDEM's Office of Water Management. The following violations were
observed at the time of these records' reviews:
- Pursuant to 327 IAC 4-1-3, whenever, in the determination of the commissioner, a
semipublic facility or publically owned treatment works (POTW) has reached or
is approaching 90% of its maximum hydraulic or organic design capacity, the
commissioner shall notify the semipublic facility or POTW that it may be
necessary, because of such condition, to impose a sewer connection ban if action
is not taken by the semipublic facility or POTW to accommodate additional flow
or loading.
On February 7, 1995, pursuant to 327 IAC 4-1-3, Batesville was issued a sewer
ban early warning notification. A record's review indicated that Batesville's
WWTP had reached 93% of its design capacity. The notification explained that if
the hydraulic overloading of the facility was not corrected, a sewer connection ban
may be imposed. At that time Batesville had failed to correct the
inflow/infiltration which caused or contributed to cause the hydraulic overload, in
violation of its NPDES permit.
- Pursuant to 327 IAC 4-1-4, imposition of sewer connection bans, whenever, in the
determination of the commissioner, hydraulic or organic overloading of a
semipublic facility or POTW exists or is impending and the introduction into the
semipublic facility or POTW of additional wastewater from new or existing
sources is likely to result in the discharge or bypassing of insufficiently treated
sewage, the commissioner may impose a ban on further sewer connections to the
semipublic facility or POTW. Such sewer connection bans shall prohibit the
connection or introduction of additional wastewater or sewage into the semipublic
facility or POTW, except as otherwise provided under this article.
Pursuant to 327 IAC 4-1-5, notification of imposition of a sewer connection ban:
- Whenever the commissioner has determined to impose a ban on further
sewer connections to a POTW, the commissioner shall notify the principal
executive officer, the ranking elected official, or the authorized agent or
representative of the POTW of such determination by certified mail, return
receipt requested.
- Whenever the commissioner has determined to impose a ban on further
sewer connections to a semipublic facility, the commissioner shall notify
the owner, chief executive officer, or authorized agent or representative of
the semipublic facility of such determination by certified mail, return
receipt requested.
On January 17, 1996, an imposition of sewer connection ban notification was
issued to the Respondent indicating that the WWTP was hydraulically overloaded.
From the period of November 1, 1994 to October 31, 1995, the Respondent's
WWTP was averaging 110% of its hydraulic capacity of 1.23 million gallons per
day (mgd). During this period, this flow exceeded its hydraulic design capacity
by as much as 2.13 mgd, or 173%. During the same period of November 1, 1994
to October 31, 1995, the Respondent reported, to IDEM, eighty-one (81)
bypassing of treatment events, in violation of its NPDES permit.
- Pursuant to 327 IAC 4-1-6, grounds and procedures for obtaining waivers of
sewer connection bans, requests for connections from new or existing sources to a
semipublic facility or POTW where a sewer connection ban is in effect may be
approved if it is determined by the commissioner that any of certain conditions
exist.
Pursuant to 327 IAC 4-1-8, the following shall be excluded from the requirements
of sewer connection bans:
- Single-family dwellings erected on vacant lots served by an existing
sanitary sewer.
- Projects that possess a valid construction permit issued under 327 IAC 3-2
prior to the imposition of a sewer connection ban.
On February 9, 2000, IDEM requested verification of new sewer connections
occurring since the imposition of the sewer connection ban for commercial
establishments which include the following construction projects: FCN Bank,
Guys and Gals Quarters Hair Salon, Lynch's Car Wash, Maxwell Construction
Office Building, Medical Arts Building, Precision Hair Designs Hair Salon, and
Prestige Portraits. IDEM has no record of the Respondent requesting sewer
connection ban waivers for the above construction projects, in violation of its
NPDES permit and provisions of 327 IAC 4-1-4 and 327 IAC 4-1-6.
- Pursuant to 327 IAC 4-1-11(a), whenever necessary to carry out the provisions of
this article, any person who is or may be reasonably expected to be subject to such
regulatory provisions shall:
- establish and maintain records;
- make reports;
- install, use, and maintain monitoring equipment or methods;
- sample effluents, or other material; and
- provide other information;
at the locations, at the times, and in the manner the commissioner may reasonably
prescribe.
On February 29, 2000, IDEM received a response to its February 9, 2000,
information request letter. The Respondent verified that the construction and
connection to the sewer system had occurred without notifying IDEM. The
Respondent failed to meet the provisions of the sewer connection ban exclusion,
failed to notify IDEM of these construction projects, and failed to obtain a sewer
connection ban waiver for the above construction projects, in violation of
327 IAC 4-1-6, 327 IAC 4-1-8 and 327 IAC 4-1-11(a). The Respondent contends
that it mistakenly believed that the sewer connection ban waivers were not
necessary. The Respondent also contends that it believed that the waivers were
necessary only when IDEM required a construction permit.
On July 12, 2000, representatives of IDEM met with representatives of the City of
Batesville to discuss the sewer connection ban and the Respondent's continued
violations of the ban. On July 27, 2000, the Respondent submitted a follow-up
letter to the July 12, 2000 meeting. The Respondent verified that the construction
projects failed to meet the provisions of the sewer connection ban exclusion. The
Respondent allowed the connection of commercial buildings to its 100% sanitary
sewer system without obtaining sewer connection ban waivers from IDEM. The
Respondent failed to timely notify IDEM of these construction projects and failed
to obtain a sewer connection ban waiver for the following construction projects
prior to commencing construction, in violation of its NPDES permit and
provisions of 327 IAC 4-1-4, 327 IAC 4-1-6, 327 IAC 4-1-8 and 327 IAC 4-1-11(a):
PROJECT DATE BUILDING DATE CONSTRUCTION
NAME/LOCATION PERMIT ISSUED PROJECT COMPLETED
| FCN Bank
1050 N State Road 229 N. |
November 25, 1997 |
June 1, 1998 |
| Guys and Gals Quarters
Hair Salon
22 Saratoga Drive
Prestige Portraits
20 Saratoga Drive |
September 1, 1998
September 1, 1998 |
February 15, 1999
February 15, 1999 |
| Lynch's Car Wash
1124 State Road 229 North |
September 4, 1998 |
February 9, 1999 |
| Medical Arts Building
188 State Road 129 South |
January 24, 2000 |
September 21, 2000 |
| Maxwell Construction
Office Building
92 Progress Drive |
April 13, 1999 |
March 7, 2000
|
| Precision Hair Designs
Hair Salon (Maxwell)
285 Central Avenue |
April 12, 1999 |
September 7, 1999 |
- Since October 31, 2000, when IDEM issued its Notice of Violation, IDEM and the
Respondent have discussed the following additional construction projects which also are
addressed by this Agreed Order:
PROJECT DATE BUILDING DATE CONSTRUCTION
NAME/LOCATION PERMIT ISSUED PROJECT COMPLETED
| Enhanced
Telecommunications
244 State Road 129 South |
January 28, 1998 |
May 11, 1999 |
| Unfinished Furniture Store
24 Saratoga Drive |
September 1, 1998 |
February 15, 1999 |
| Stoinoff Restoration
56 Progress Drive |
November 2, 2000 |
Construction ongoing |
| Margaret Mary Outpatient
Clinic
206 State Road 129 South |
July 1, 1996 |
January 13, 1997 |
| Batesville Dialysis (Renal
Treatment)
232 State Road 129 South |
March 2, 1998 |
July 21, 1998 |
- On December 21, 2000, The Respondent submitted to IDEM a request for sewer ban
termination.
- On January 10, 2001, IDEM sent a letter to the Respondent denying the request for sewer
ban termination. This denial is based on the fact that Batesville has rated the capacity of
the WWTP, as determined in the City's approved Sewer Works Project Facilities Plan, as
1.6 million gallons per day (mgd), IDEM's records indicate that the WWTP's actual
design flow is 1.23 mgd. IDEM's records show that bypassing events have consistently
occurred at flows less than 1.6mgd. It was also determined that currently no additional
"waiver capacity" is available for Batesville because the WWTP is operating at 91%
capacity and the percent capacity does not take into consideration the undetermined
amount of raw wastewater being bypassed from the WWTP and discharged into the
environment.
- In recognition of the settlement reached, Respondent waives any right to administrative
and judicial review of this Agreed Order.
II. ORDER
- This Agreed Order shall be effective ("Effective Date") when it is approved by the
Complainant or her delegate, and has been received by the Respondent. This Agreed
Order shall have no force or effect until the Effective Date.
- Immediately, upon the Effective Date of this Order, the Respondent shall comply with all
terms and conditions of the sewer connection ban issued on January 17, 1996. The
Respondent shall not construct or allow others to construct any connections to its sanitary
sewer system, unless the project is excluded from the requirements of sewer connection
bans under 327 IAC 4-1-8, or unless the Respondent first obtains a sewer connection ban
waiver from IDEM pursuant to 327 IAC 4-1-6, or until IDEM issues a notice of
termination of the sewer ban.
- The Respondent shall submit requests for waivers of the sewer connection ban for all
future projects covered by 327 IAC 4-1-6 that it intends to connect to the sewer until
IDEM terminates the sewer connection ban. All requests shall contain, at a minimum, the
projected flow and pollutant loadings from the proposed connection(s), and the projected
impact upon the WWTP. All waiver requests will be approved or denied by IDEM.
- All submittals required by this Agreed Order, unless notified otherwise in writing, shall
be sent to:
Aletha Lenahan, Enforcement Case Manager
Office of Enforcement
Indiana Department of Environmental Management
100 N. Senate Avenue
P. O. Box 6015
Indianapolis, IN 46206-6015
- Respondent is assessed a civil penalty of Twenty-One Thousand Dollars ($21,000). Said
penalty amount shall be due and payable to the Environmental Management Special Fund
within 30 days of the Effective Date of this Agreed Order.
- In the event the terms and conditions of the following paragraphs are violated, the
Complainant may assess and the Respondent shall pay a stipulated penalty in the
following amount:
VIOLATION PENALTY
Failure to comply with Order paragraph 2 $500 per connection for violation of
the sewer connection ban.
Failure to comply with Order paragraph 3 $200 per week for failure to submit
all requests for waivers of a sewer
connection ban.
- Stipulated penalties shall be due and payable within thirty (30) days after Respondent
receives written notice that the Complainant has determined a stipulated penalty is due.
Assessment and payment of stipulated penalties shall not preclude the Complainant from
seeking any additional relief against the Respondent for violation of the Agreed Order. In
lieu of any of the stipulated penalties given above, the Complainant may seek any other
remedies or sanctions available by virtue of Respondent's violation of this Agreed Order
or Indiana law, including, but not limited to, civil penalties pursuant to IC 13-30-4.
- Civil and stipulated penalties are payable by check to the Environmental Management
Special Fund. Checks shall include the Cause Number of this action and shall be mailed
to:
Cashier
IDEM
100 N. Senate Avenue
P. O. Box 7060
Indianapolis, IN 46207-7060
- In the event that the civil penalty required by Order paragraph 5, is not paid within thirty
(30) days of the Effective Date of this Agreed Order, Respondent shall pay interest on the
unpaid balance at the rate established by IC 24-4.6-1-101. The interest shall continue to
accrue until the civil penalty is paid in full.
- This Agreed Order shall apply to and be binding upon the Respondent, its successors and
assigns. The Respondent's signatories to this Agreed Order certify that they are fully
authorized to execute this document and legally bind the parties they represent. No
change in ownership, corporate, or partnership status of the Respondent shall in any way
alter its status or responsibilities under this Agreed Order.
- In the event that any terms of the Agreed Order are found to be invalid, the remaining
terms shall remain in full force and effect and shall be construed and enforced as if the
Agreed Order did not contain the invalid terms.
- The Respondent shall provide a copy of this Agreed Order, if in force, to any subsequent
owners or successors before ownership rights are transferred. Respondent shall ensure
that all contractors, firms and other persons performing work under this Agreed Order
comply with the terms of this Agreed Order.
- This Agreed Order shall remain in effect until the Respondent has complied with all
terms and conditions outlined in this Agreed Order, as well as Agreed Order, Cause No.
B-1677, including but not limited to the completion of the new WWTP, and successful
completion of the performance period, as well as the completion of the sewer system
rehabilitation.
TECHNICAL RECOMMENDATION: RESPONDENT:
Department of Environmental Management City of Batesville,
The Honorable William Abplanalp, Mayor
By: _________________________ By: ________________________________
Mark W. Stanifer
Chief, Water Enforcement Printed: The Honorable William Abplanalp
Office of Enforcement
Title: Mayor, City of Batesville
Date: ________________________ Date: ______________________________
COUNSEL FOR COMPLAINANT: COUNSEL FOR RESPONDENT:
Department of Environmental Management
By: _________________________ By: ________________________________
Sierra L. Cutts
Attorney, Office of Legal Counsel Printed: Terri A, Czajka
Department of Environmental Management
Title: Attorney, Ice Miller
Legal and Business Advisors
Date: _______________________ Date: ______________________________
APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL
MANAGEMENT THIS DAY OF , 2001.
For the Commissioner:
Signed 3/23/01
___________________________________
Felicia A. Robinson
Assistant Commissioner
Office of Enforcement