STATE OF INDIANA ) BEFORE THE INDIANA DEPARTMENT
COMMISSIONER OF THE DEPARTMENT )
) SS: OF ENVIRONMENTAL MANAGEMENT
COUNTY OF MARION )
OF ENVIRONMENTAL MANAGEMENT, )
)
Complainant, )
)
v. )CAUSE NOS. B-2215 and B-2230 or
)1997-4535-W and 1997-4550-W
LEFT GUARD CORP, )
)
Respondent. )
2. The Respondent is Left Guard Corp (hereinafter referred to as "Respondent"). The Respondent
was the owner and developer of the Homestead Hills Subdivision on Homestead Road in Fort
Wayne, Allen County, Indiana, until it sold the site to Bauman Construction, Inc., on January
15, 1997. By contractual agreement, the Respondent was responsible for maintaining the
erosion control measures at the Homestead Hills Subdivision until January 14, 1998. The
Respondent is the owner and developer of the Winchester Ridge Subdivision on Dunkelburg
Road in Fort Wayne, Allen County, Indiana.
3. IDEM has jurisdiction over the parties and the subject matter of this action.
4. 327 IAC 15-5-2 applies to all persons who:
do not obtain an individual NPDES permit under 327 IAC 15-2-6;
b. meet the general permit rule applicability requirements under 327 IAC 15-2-3;
and
c. are involved in construction activity that includes clearing, grading, excavating,
and other land disturbing activities, except operations that result in the
disturbance of less than five (5) acres of total land area and are not part of a
larger common plan of development or sale.
5. 327 IAC 15-5-7 pertains to general conditions for construction activity erosion control
measures. In essence it states that the operator shall develop an erosion control plan in
accordance with the requirements under this section. The following requirements shall be met
on all sites during the period when active land disturbing activities occur:
a. Sediment-laden water, which would otherwise flow from the site, shall be
detained by erosion control practices appropriate to minimize sedimentation in
the receiving stream. No storm water shall be discharged from the site in a
manner causing erosion in the receiving channel at the point of discharge.
b. Appropriate measures shall be taken by the operator to minimize or eliminate
wastes or unused building materials from being carried from a site by run-off.
c. Sediment being tracked from a site onto public or private roadways shall be
minimized.
d. Public or private roadways shall be kept clear of accumulated sediment. Bulk
clearing of accumulated sediment shall not include flushing the area with
water. Cleared sediment shall be returned to the point of likely origin or other
suitable location.
e. All on-site storm drain inlets shall be protected against sedimentation with
barriers meeting acceptable design criteria, standards, and specifications for
that purpose.
f. Storm water drainage from adjacent areas that naturally pass through the site
shall be controlled by diverting it around the disturbed area.
g. Run-off from a disturbed area shall be controlled by one (1) or more of the
measures required under this section.
h. All erosion control measures necessary to meet the requirements of this rule
shall be maintained by the operator.
i. All erosion control measures required to comply with this rule shall meet the
design criteria, standards and specifications for erosion control measures
established by IDEM in guidance documents. The erosion control plan shall
include, but is not limited to, those measures required under this section.
6. IC 13-30-2-1 prohibits, in substance, any person from discharging, emitting, causing, allowing,
or threatening to discharge, emit, cause, or allow any contaminant or waste including any
noxious odor, either alone or in combination with contaminants from other sources, into the
environment or into any publicly-owned treatment works in any form which causes or would
cause pollution which violates rules, standards, or discharge of emission requirements adopted
by the appropriate board pursuant to this article.
7. A Notice of Intent (NOI) letter, received from the Respondent by IDEM on August 19, 1996,
indicated that the Homestead Hills Subdivision construction project involves land disturbing
activity on a total area of twelve (12) acres, thus subjecting the project to the requirements of
327 IAC 15.
8. On October 23, 1996; June 3, June 20, and August 12, 1997; and October 21, 1998,
representatives from the Indiana Department of Natural Resources (IDNR) inspected the
Homestead Hills Subdivision construction site. The following were observed on one or more
occasions:
a. sedimentation leaving the site, in violation of 327 IAC 15-5-7(b)(1) and IC 13-
30-2-1;
b. soil and sedimentation being tracked onto public or private roadways, in
violation of 327 IAC 15-5-7(b)(3) and IC 13-30-2-1;
c. lack of appropriate stabilization and sediment control measures in on-site
drainage channels and outlets, in violation of both 327 IAC 15-5-7(b)(1) and
327 IAC 15-5-7(b)(6)(B);
d. the erosion and sedimentation control plan was not being effectively
implemented, in violation of both 327 IAC 15-5-5(4)(B) and 327 IAC 15-5-
7(b)(6)(B)(ii);
e. inadequately protected storm inlets, in violation of 327 IAC 15-5-7-(b)(5);
f. improperly maintained erosion control measures, in violation of 327 IAC 15-5-
7(c);
g. lack of erosion control measures in appropriate locations, in violation of 327
IAC 15-5-7(d)(3)(C);
h. lack of proper erosion and sediment control measures incorporated into land
disturbing activities, in violation of 327 IAC 15-5-7(d)(3)(D); and
i. areas not stabilized in the specified construction sequence, in violation of 327
IAC 15-5-7-(d)(3)(D).
It was noted during the August 12, 1997, inspection that some of the previously deficient areas
had been graded and mulched, and that the streets had been scraped.
9. On October 24, 1996, and June 4 and June 23, 1997, IDNR sent to the Respondent letters
regarding the violations noted during the inspections conducted at the Homestead Hills
Subdivision construction site on October 23, 1996, and June 3 and June 20, 1997, respectively.
10. On January 15, 1997, Left Guard, Inc., sold the Homestead Hills Subdivision to Bauman
Construction, Inc. The terms of the sales contract required Left Guard, Inc., to maintain the
erosion control measures at the project construction site for one (1) year from the date of
closing.
11. On July 17, 1997, IDEM issued to the Respondent, via Certified Mail No. Z 336 262 221, a
Warning of Noncompliance (WONC) for the Homestead Hills Subdivision construction site
for the violations noted through the June 20, 1997, inspection. The Respondent received the
WONC on July 21, 1997. No response to the WONC was received from the Respondent.
12. In a letter dated August 6, 1997, in response to a telephone call from IDEM's Office of
Enforcement (OE), the Respondent advised IDEM of improvements that either had been made
or were planning to be made in the near future.
13. An NOI letter, received from the Respondent by IDEM on January 26, 1996, indicated that the
Winchester Ridge Subdivision construction project involves land disturbing activity on a total
area of twenty-eight and one-tenth (28.1) acres, thus subjecting the project to the requirements
of 327 IAC 15.
14. On June 3, August 12, and September 25, 1997; June 8, July 21, and October 21, 1998; and
December 2, 1999; representatives from IDNR inspected the Winchester Ridge Subdivision
construction site. The following were observed on one or more occasions:
a. sedimentation leaving the site, in violation of 327 IAC 15-5-7(b)(1) and IC 13-
30-2-1;
b. soil and sedimentation being tracked onto public or private roadways, in
violation of 327 IAC 15-5-7(b)(3) and IC 13-30-2-1;
c. lack of appropriate stabilization and sediment control measures in on-site
drainage channels and outlets, in violation of both 327 IAC 15-5-7(b)(1) and
327 IAC 15-5-7(b)(6)(B);
d. the erosion and sedimentation control plan was not being effectively
implemented, in violation of both 327 IAC 15-5-5(4)(B) and 327 IAC 15-5-
7(b)(6)(B)(ii);
e. inadequately protected storm inlets, in violation of 327 IAC 15-5-7-(b)(5);
f. improperly maintained erosion control measures, in violation of 327 IAC 15-5-
7(c);
g. lack of erosion control measures in appropriate locations, in violation of 327
IAC 15-5-7(d)(3)(C);
h. lack of proper erosion and sediment control measures incorporated into land
disturbing activities, in violation of 327 IAC 15-5-7(d)(3)(D); and
i. areas not stabilized in the specified construction sequence, in violation of 327
IAC 15-5-7-(d)(3)(D).
During the August 12, 1997, inspection it was noted that the south ditch was being prepared
for seeding. During the September 25, 1997, inspection it was noted that vegetative buffers
had been installed along the front of most of the lots.
15. On June 4, 1997, IDNR sent to the Respondent a letter regarding the violations noted during
the June 3, 1997, inspection conducted at the Winchester Ridge Subdivision construction site.
16. On July 26, 1999, IDNR representatives inspected and found the site to be in compliance.
18. On October 21, 1998, a settlement conference was held with the Respondent. The corrective
measures that needed to be taken by the Respondent at each site were discussed, as was the
proposed penalty. Agreement was reached regarding the corrective measures but not on the
proposed penalty. The Respondent agreed to submit a penalty counter-offer by November 25,
1998.
19. No penalty counter-offer was received by IDEM by November 25, 1998. Subsequent attempts
by IDEM on December 7 and December 15, 1998, to contact the Respondent, through counsel,
and resolve the penalty issue did not produce any results. On December 15, 1998, the
Respondent, through counsel, was advised that a Notice and Order of the Commissioner of the
Indiana Department of Environmental Management (CO) would be drafted to resolve the two
causes. The Respondent was also advised that settlement negotiations could continue, even
though a CO was being drafted, and negotiated settlement could be achieved up until the CO
was formally issued.
20. On March 25, 1999, the CO was issued to the Respondent.
21. On April 19, 1999, the Office of Environmental Adjudication (OEA) and IDEM received the
Respondent's Request for Review of the CO.
22. On June 18, 1999, a pre-hearing conference between the parties was held by the OEA. A
hearing in this matter was scheduled for October 27, 1999.
23. Prior to the scheduled October 27, 1999, hearing, the parties reached agreement regarding the
terms of settlement and agreed to enter into this Agreed Order.
24. In recognition of the settlement reached, the Respondent waives any right to administrative and
judicial review of this Agreed Order.
1. This Agreed Order shall be effective (hereinafter referred to as "effective date") when it is
approved by the Complainant or her delegate, and has been received by the Respondent. This
Agreed Order shall have no force or effect until the effective date.
2. The Respondent shall, within 10 days of the effective date of this Agreed Order, correct any
unsatisfactory erosion control measures in existence as of the effective date of this Agreed
Order to the satisfaction of IDNR.
3. The Respondent shall continue to maintain the erosion control measures and perform regular
erosion control maintenance at the Winchester Ridge Subdivision construction site to the
satisfaction of IDNR.
4. The Respondent is assessed a total Civil Penalty of Nine Thousand Dollars ($9,000). Three
Thousand Dollars ($3,000) of the Civil Penalty shall be attributable to Cause No. B-2215; the
remaining Six Thousand Dollars ($6,000) of the Civil Penalty shall be attributable to Cause
No. B-2230. Said total penalty amount shall be due and payable to the Environmental
Management Special Fund within thirty (30) days of the effective date of this Agreed Order.
5. In the event the following terms and conditions are violated, the Complainant may assess and
the Respondent shall pay a stipulated penalty in the following amounts:
Violation Penalty
Failure to comply with:
Paragraph 2 $500 per each day past the 10-day deadline that
the Respondent fails to correct any
unsatisfactory erosion control measures in
existence as of the effective date to the
satisfaction of IDNR
Paragraph 3 $1000 per each week after receipt of notification from IDNR of unsatisfactory erosion control practices at the Winchester Ridge Subdivision construction site that the Respondent fails to correct the identified
erosion control practices to the satisfaction of
IDNR.
6. Stipulated penalties shall be due and payable within thirty (30) days after the Respondent
receives written notice that the Complainant has determined a stipulated penalty is due.
Assessment and payment of stipulated penalties shall not preclude the Complainant from
seeking any additional relief against the Respondent for violation of the Agreed Order. In lieu
of assessment of the stipulated penalties given above, the Complainant may seek any other
remedies or sanctions available by virtue of the Respondent's violation of this Agreed Order
or Indiana law, including, but not limited to, civil penalties pursuant to IC 13-30-3-4.
7. Civil and stipulated penalties are payable by check to the Environmental Management Special
Fund. Checks shall include the Cause Number of this Agreed Order and shall be mailed to:
Cashier
Indiana Department of Environmental Management
100 North Senate Avenue
P.O. Box 7060
Indianapolis, Indiana 46207-7060
8. In the event that the Civil Penalty required by Section II, Paragraph 4, is not paid within thirty
(30) days of the effective date of this Agreed Order, the Respondent shall pay interest on the
unpaid balance at the rate established by IC 24-4.6-1-101. The interest shall continue to accrue
until the Civil Penalty is paid in full.
9. "Force Majeure", for purposes of this Agreed Order, is defined as any event arising from
causes beyond the control of the Respondent that delays or prevents the performance of any
obligation under this Agreed Order despite Respondent's best efforts to fulfill the obligation.
The requirement that the Respondent exercise "best efforts to fulfill the obligation" includes
using best efforts to anticipate any potential force majeure event and best efforts to address the
effects of any potential force majeure event (1) as it is occurring and (2) following the potential
force majeure event, such that the delay is minimized to the greatest extent possible. "Force
Majeure" does not include financial inability to complete the work required by this Agreed
Order or increases in costs to perform the work.
The Respondent shall notify IDEM by calling within 3 calendar days and by writing no later
than 7 calendar days after any event which the Respondent contends is a force majeure. Such
notification shall describe the anticipated length of the delay, the cause or causes of the delay,
the measures taken or to be taken by the Respondent to minimize the delay, and the timetable
by which these measures will be implemented. The Respondent shall include with any notice
all available documentation supporting their claim that the delay was attributable to a force
majeure. Failure to comply with the above requirements shall preclude the Respondent from
asserting any claim of force majeure for that event. The Respondent shall have the burden of
demonstrating that the event is a force majeure. The decision of whether an event is a force
majeure shall be made by IDEM. Said decision shall be communicated to the Respondent.
If a delay is attributable to a force majeure, IDEM shall extend, in writing, the time period for
performance under this Agreed Order, by the amount of time that is attributable to the event
constituting the force majeure.
10. This Agreed Order shall apply to and be binding upon the Respondent, its officers, directors,
principals, agents, successors, subsidiaries, and assigns. The signatories to this Agreed Order
certify that they are fully authorized to execute this document and legally bind the parties they
represent. No change in ownership, corporate, or partnership status of the Respondent shall
in any way alter the Respondent's status or responsibilities under this Agreed Order.
11. In the event that any terms of this Agreed Order are found to be invalid, the remaining terms
shall remain in full force and effect and shall be construed and enforced as if the Agreed Order
did not contain the invalid terms.
12. The Respondent shall provide a copy of this Agreed Order, if in force, to any subsequent
owners or successors before ownership rights are transferred. The Respondent shall ensure
that all contractors, firms, and other persons performing work under this Agreed Order comply
with the terms of this Agreed Order.
13. Entry into this Agreed Order supersedes the Notice and Order of the Commissioner issued to
the Respondent by IDEM on March 25, 1999.
14. This Agreed Order shall remain in effect until one of the following occurs:
a. this Agreed Order has been in effect for 12 months; or
b. the Respondent submits a Notice of Termination (NOT) for the Winchester Ridge
Subdivision construction site; or
c. the Respondent sells the Winchester Ridge Subdivision construction site and the new
owner has filed a Notice of Intent for the construction site.
TECHNICAL RECOMMENDATION: RESPONDENT:
By: By:
Mark W. Stanifer
Water Enforcement Section Printed:
Office of Enforcement
Department of Environmental Title:
Management
Date: Date:
COUNSEL FOR COMPLAINANT: COUNSEL FOR RESPONDENT:
By: By:
Printed: Printed:
Office of Legal Counsel
Department of Environmental
Management
Date: Date:
APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL
MANAGEMENT THIS DAY OF , .
FOR THE COMMISSIONER:
Original signed on January 25, 2000 by
Felicia A. Robinson
Assistant Commissioner
Office of Enforcement
Converted by Andrew Scriven