STATE OF INDIANA

COUNTY OF MARION

)
)
)


SS:

BEFORE THE INDIANA DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT

 

COMMISSIONER OF THE DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT,

Complainant,

v.

UMH BROADMORE, LLC,

Respondent.

)
)
)
)
)
)
)
)
)
)






Case No. 2024-29995-W

 

 

AGREED ORDER

 

Complainant and Respondent desire to settle and compromise this action without hearing or adjudication of any issue of fact or law, and consent to the entry of the following Findings of Fact and Order. Pursuant to Indiana Code (IC) 13-30-3-3, entry into the terms of this Agreed Order does not constitute an admission of any violation contained herein. Respondent's entry into this Agreed Order shall not constitute a waiver of any defense, legal or equitable, which Respondent may have in any future administrative or judicial proceeding, except a proceeding to enforce this order.

 

 

I. FINDINGS OF FACT

 

1.            Complainant is the Commissioner (Complainant) of the Indiana Department of Environmental Management (IDEM), a department of the State of Indiana created by IC 13-13-1-1.

 

2.            UMH Broadmore, LLC (Respondent), owns/operates the Broadmore Estates Manufactured Housing Community Wastewater Treatment Plant, located at 58874 State Road 15, Goshen, Elkhart County, Indiana (the Site).

 

Respondent owns/operates a community public water system (PWS) with PWSID No. IN5220012, serving 972 persons. The PWS is located at 900 Broadmore Estates, Goshen, Elkhart County, Indiana.

 

3.            Respondent is authorized by its National Pollutant Discharge Elimination System (NPDES) Permit No. IN0038989 (the Permit) to discharge wastewater treated in accordance with the terms and conditions of the Permit from the Wastewater Treatment Plant (WWTP) into the receiving stream named Park Creek, located within the Lake Michigan drainage basin, from Outfall 001.

 

4.            IDEM has jurisdiction over the parties and the subject matter of this action pursuant to IC 13-30-3.

 

5.            Pursuant to IC 13-30-3-3, IDEM issued a Notice of Violation (NOV) via Certified Mail/personal service to:

 

Corporation Service Company, Registered Agent

 

Jeffrey Yorick, Vice President for

Engineering

UMH IN Broadmore, LLC

 

UMH Properties, Inc.

135 North Pennsylvania Street, Suite 1610

 

150 Clay Street, Suite

450

Indianapolis, IN 46204

 

Morgantown, West Virginia 26501

 

6.            During an investigation conducted by a representative of IDEM, violations were found, as described below.

 

7.            327 Indiana Administrative Code (IAC) 5-2-8(1), states the permittee shall comply with all terms and conditions of the Permit. Any permit noncompliance constitutes a violation of the Clean Water Act and Indiana Code (IC) 13 and is grounds for enforcement action by IDEM.

 

8.            Pursuant to Part I.A.1 of the Permit, the permittee is required to comply with the monitoring requirements contained in the Permit, including effluent limitations.

 

Discharge Monitoring Reports (DMRs) and Monthly Reports of Operation (MROs) submitted by Respondent for the period of August 2021 through January 2024 revealed violations of effluent limitations contained in Part I.A.1 of the Permit as follows:

 

A.       The minimum daily average concentration limitation for dissolved oxygen was not met during December 2022.

B.       The maximum weekly average concentration limitation for total suspended solids (TSS) was exceeded during January, May, July, October, November, and December 2023, and January 2024.

C.       The monthly average concentration limitation for TSS was exceeded during May, October, November, and December 2023, and January 2024.

D.       The maximum weekly average loading limitation for TSS was exceeded during May, July, October, November, and December 2023, and January 2024.

E.       The maximum monthly average loading limitation for TSS was exceeded during May, September, October, November, and December 2023, and January 2024.

F.        The daily maximum concentration limitation for ammonia (as nitrogen) was exceeded during December 2021, November 2022, January, February, March, April, May, June, July, August, September, October, November, and December 2023, and January 2024.

G.       The monthly average concentration limitation for ammonia (as nitrogen) was exceeded during November 2022, January, February, March, April, May, June, July, August, September, October, November, and December 2023, and January 2024.

H.       The daily maximum loading limitation for ammonia (as nitrogen) was November 2022, January, February, May, June, July, August, September, October, November, and December 2023, and January 2024.

I.         The monthly average loading limitation for ammonia (as nitrogen) was exceeded during November 2022, January, February, May, June, July, August, September, October, November, and December 2023, and January 2024.

J.        The daily maximum concentration limitation for E. coli was exceeded during August 2021, September 2022, April, May, June, July, August, September, and October 2023.

K.       The monthly geometric mean limitation for E. coli was exceeded during April, May, June, July, August, September, and October 2023.

L.        The maximum weekly average concentration limitation for BOD was exceeded during March, April, May, June, July, August, and September 2023, and January 2024.

M.      The maximum monthly average concentration limitation for BOD was exceeded during March, April, May, June, July, August, September, and October 2023, and January 2024.

N.       The maximum weekly average loading limitation for BOD was exceeded during May, June, July, August, September, and October 2023, and January 2024.

O.       The maximum monthly average loading limitation for BOD was exceeded during May, June, July, August, September, and October 2023, and January 2024.

 

Respondent failed to comply with the effluent limitations from Outfall 001 contained in the Permit, in violation of Part I.A.1 of the Permit.

 

9.         Pursuant to IC 13-18-4-5, a person may not: (1) throw, run, drain, or otherwise dispose; or (2) cause, permit, or suffer to be thrown, run, drained, allowed to seep, or otherwise disposed; into any of the streams or waters of Indiana any organic or inorganic matter that causes or contributes to a polluted condition of any of the streams or waters of Indiana.

 

Pursuant to IC 13-30-2-1(1), it is unlawful for any person to discharge, emit, cause or allow any contaminant or waste, including any noxious odor, either alone or in combination with contaminants from other sources in the environment in any form that causes or would cause pollution that violates or would violate rules, standards, or discharge or emission requirements adopted by the appropriate board under the environmental management laws.

 

Pursuant to 327 IAC 5-2-2, any discharge of pollutants into waters of the State, as a point source discharge, is prohibited unless in conformity with a valid NPDES permit obtained from IDEM prior to the discharge.

 

Pursuant to 327 IAC 2-1.5-8(b)(1) and Part I.A.2 of the Permit, all surface waters within the Great Lakes system at all times and at all places, including waters within the mixing zone, shall meet the minimum conditions of being free from substances, materials, floating debris, oil or scum attributable to municipal, industrial, agricultural, and other land use practices or other discharges that do any of the following:

 

            a.         will settle to form putrescent or otherwise objectionable deposits;

b.         are in amounts sufficient to be unsightly or deleterious;

c.         produce color, visible oil sheen, odor, or other conditions in such degree as to create a nuisance;

d.         are in concentrations or combinations that will cause or contribute to the growth of aquatic plants or algae to such degree as to create a nuisance, be unsightly, or otherwise impair the designated uses; or

e.         are in amounts sufficient to be acutely toxic to, or to otherwise severely injure or kill aquatic life, other animals, plants, or humans.

 

During the inspections on December 2, 2022, and December 5, 2022, IDEM staff observed and documented the mixing zone at Outfall 001 showed evidence of accumulated sludge.

 

During the inspection on January 22, 2024, IDEM staff observed and documented the PWS south treatment plant discharged backwash into a nearby creek without a permit.

 

The unpermitted discharges noted above are in violation of IC 13-18-4-5, IC 13-30-2-1(1), 327 IAC 5-2-2, 327 IAC 2-1.5-8(b)(1), and Part I.A.2 of the Permit.

 

10.         Pursuant to Part I.B.6 of the Permit, the permittee shall record and maintain records of all monitoring information on activities under the Permit.

 

During the inspection on July 25, 2022, IDEM staff observed and documented a lack of documentation for pH meter calibration, in violation of Part I.B.6 of the Permit.

 

11.         Pursuant to 327 IAC 5-2-8(9) and Part II.B.1 of the Permit, the permittee shall at all times maintain in good working order and efficiently operate all facilities and systems (and related appurtenances) for the collection and treatment which are installed or used by the permittee and which are necessary for achieving compliance with the terms and conditions of the permit.

During the inspection on July 25, 2022, IDEM staff observed and documented inadequate maintenance and operation of the facilities, specifically:

 

A.   The concrete lid covering the wet well demonstrated deterioration and it is considered to be a safety hazard;

B.   The air distribution line was broken;

C.   Influent was flowing into the WWTP, but there was not enough activated sludge to adequately treat the wastewater;

D.   One of the two blowers was old and was not operating at full capacity;

E.   Plant operators reported maintaining the aeration system with enough air often requires diverting air from other units of treatment;

F.    A records review indicated that during warmer weather months the aeration tanks struggle to maintain dissolved oxygen at 2 milligram per liter (mg/l); and,

G.   The WWTP was located inside a pole barn with low light that created poor overall visibility and made it difficult for IDEM staff to thoroughly inspect all units of treatment.

 

During the inspection(s) on December 2, 2022, IDEM staff observed and documented inadequate maintenance and operation of the facilities, specifically:

 

H.   The concrete lid covering the wet well still demonstrated deterioration and it is considered to be a safety hazard;

I.     One of the two blowers was not in service;

J.    The mixed liquor appeared a dark-gray color and there appeared to be a high inventory of solids;

K.   The clarifier showed no settling, and a sludge blanket floated on the surface;

L.    The deficiencies in sludge settling caused sludge to surge through the effluent primary post-aeration basin;

M.  The lift station located about 30 meters south of Outfall 001 showed accumulated sludge, floatable trash, and grease; and,

N.   The WWTP was holding excessive solids throughout the treatment plant.

 

Each in violation of 327 IAC 5-2-8(9) and Part II.B.1 of the Permit.

12.         Pursuant to Part II.B.4 of the Permit, solids, sludges, filter backwash, or other pollutants removed from or resulting from treatment or control of wastewaters shall be disposed of in a manner such as to prevent any pollutant from such materials from entering waters of the State and to be in compliance with all Indiana statutes and regulations relative to liquid and/or solid waste disposal.

 

During the inspection on December 2, 2022, IDEM staff observed and documented the digester was at full capacity and the WWTP was holding excessive solids throughout the WWTP, in violation of Part II.B.4 of the Permit.

 

13.         Pursuant to Part II.B.6 of the Permit, any overflow or release of sanitary wastewater from the wastewater treatment facilities or collection system that results in a discharge to waters of the state and is not specifically authorized by this permit is expressly prohibited.

 

During inspections on March 22, 2023, May 17, 2023, and January 14, 2024, IDEM staff observed and documented that Respondent had releases of sanitary wastewater to waters of the State, not specifically authorized by the Permit, in violation of Part II.B.6 of the Permit.

 

14.         Pursuant to 327 IAC 8-2-44(d), a water system shall deliver a consumer notification of lead tap water monitoring results to person served by the water system at sites that are tested. A water system shall provide the consumer notification as soon as practical, but not later than 30 days after the system learns of the lead tap water monitoring results.

 

IDEM records indicate that Respondent failed to provide a consumer notification to persons served by the water system at sites that are tested in 2021, in violation of 327 IAC 8-2-44(d).

 

15.         327 IAC 8-2-8.2(e) states IDEM shall evaluate each PWS during a sanitary survey to determine if deficiencies exist.

 

327 IAC 8-2-8.2(f) states significant deficiencies are conditions found during a sanitary survey that have a potential to cause an immediate risk to human health; or any deficiency that was found during a previous sanitary survey but has not been corrected; or the PWS is not in compliance with a correction schedule approved by the commissioner.

 

Pursuant to 327 IAC 8-2-8.2(h), PWSs using ground water shall respond in writing to any deficiency that was found during a sanitary survey that is reported to the PWS using ground water by the commissioner. Response requirements are as follows:

1.            The response must:

A.           be made within thirty (30) days of receipt of the report; and

B.           indicate:

i.              how the PWS will address deficiencies found during the sanitary survey; and

ii.            on what schedule the PWS will address deficiencies found during the sanitary survey.

 

On March 11, 2024, a sanitary survey was conducted by IDEM at the Site in which significant deficiencies were found. An Inspection Summary Letter dated March 15, 2024, was sent to the Respondent requiring a written response to IDEM within 30 days. No written response has been received to date. Respondent has failed to meet the response due date, in violation of 327 IAC 8-2-8.2(h).

 

16.         On July 25, 2022, December 5, 2022, and January 22, 2024, IDEM sent Inspection Summary Letter(s) to Respondent outlining violations at the WWTP. The letters required a response detailing actions taken to correct the violations. IDEM received responses to the letter(s) explaining compliance actions Respondent took or would take to address the violations. However, the responses did not adequately address the violations noted above at the WWTP.

 

17.         Orders of the Commissioner are subject to administrative review by the Office of Environmental Adjudication under IC 4-21.5; however, in recognition of the settlement reached, Respondent acknowledges notice of this right and waives any right to administrative and judicial review of this Agreed Order.

 

 

II. ORDER

 

1.            This Agreed Order shall be effective (Effective Date) when it is adopted by Complainant or Complainant’s delegate (as evidenced by signature), and the adopted Agreed Order has been received by Respondent. This Agreed Order shall have no force or effect until the Effective Date. In addition to addressing the violations cited in Paragraphs 8 through 15 of the Findings of Fact above, this Agreed Order also addresses any additional violations of these same rules that may have occurred subsequent to the issuance of the NOV and prior to the Effective Date.

 

2.            Respondent shall comply with rules and statutes listed in the findings above at issue.

 

3.            Respondent shall report any release of sanitary wastewater to waters of the State, not specifically authorized by the Permit, in accordance with Part II.C.3 of the Permit.

 

4.            Within 30 days of the Effective Date, Respondent shall develop and submit to IDEM for approval a Compliance Plan (CP) which identifies actions that Respondent will take to achieve and maintain compliance with its Permit, specifically including the actions Respondent will take to:

 

A.   Achieve and maintain compliance with effluent limitations contained in the Permit, specifically dissolved oxygen, TSS, ammonia (as nitrogen), E. coli, and BOD;

B.   Assure proper removal, storage and disposal of sludge solids;

C.   Evaluate all units of treatment, including lift stations;

D.   Repair or replace equipment as needed;

E.   Improve visibility of the treatment plant;

F.    Maintain documentation for pH calibration and for demonstrating compliance with solids and sludge removal and disposal requirements;

G.   Supply an adequate volume of air to applicable units of treatment;

H.   Develop and implement a preventative maintenance program for WWTP equipment, and document all maintenance (preventative and repair) in a permanent record;

I.     Develop and implement a preventative maintenance program for the sanitary sewer collection system, which includes methods and milestone dates for locating and eliminating sources of inflow and infiltration (I/I) in the sewer system; and,

J.    Prevent unauthorized discharge from the south water treatment plant by either:

                                          i.    Connecting to and redirecting the backwash wastewater to the WWTP; or,

                                        ii.    Obtain an NPDES Permit for discharge to a receiving stream.

 

The CP shall include an implementation and completion schedule, including specific milestone dates.

 

Respondent shall notify IDEM in writing of variations to the approved CP.

 

5.            Respondent shall, after completion of the work required pursuant to the approved CP from Paragraph 4 above, demonstrate 12 consecutive months of compliance (Compliance Demonstration) with the terms and conditions of the Permit.

 

6.            In the event that violation(s) occur during the Compliance Demonstration, within 30 days of the violation, Respondent shall develop and submit to IDEM, for approval, an Additional Action Plan (AAP) which identifies the additional actions that Respondent will take to achieve and maintain compliance with the terms and conditions of the Permit. The AAP, if required, shall include an implementation and completion schedule, including specific milestone dates.

 

7.            The plans required by Order Paragraphs 4 and 6 are subject to IDEM approval. In the event IDEM determines that any plan or any modified plan submitted by Respondent is deficient or otherwise unacceptable, Respondent shall revise and resubmit the plan to IDEM in accordance with IDEM’s notice. After three submissions of such plan by Respondent, IDEM may seek civil enforcement of this Order.

 

8.            Respondent, upon receipt of written notification from IDEM, shall immediately implement the approved plan(s) and adhere to the milestone dates therein. The approved CP and AAP shall be incorporated into the Agreed Order and shall be deemed an enforceable part thereof.

 

Following completion of the actions included in the AAP, the 12-month Compliance Demonstration, as specified in Paragraph 5 above, will re-start. Failure to achieve compliance at the conclusion of work under an AAP may subject Respondent to additional enforcement action.

 

9.            Beginning upon receipt of approval of the CP or AAP and continuing until the successful completion of implementation of the approved CP or AAP, Respondent shall submit to IDEM regular progress reports identifying compliance actions implemented and completion of each required milestone in the CP or AAP. The frequency of progress report submittals shall be specified in IDEM’s written notification to Respondent of the plan approval and will be based on the proposed milestones in the approved plan(s).

 

10.         Beginning on the Effective Date and continuing until the successful completion of the approved CP, Respondent shall, at all times, operate its existing WWTP as efficiently and effectively as possible.

 

11.         Within 30 days of receiving the lead and copper results, Respondent shall deliver the Consumer Notice of Lead Results in Drinking Water Form (attached) to persons served by the water system.

 

12.         Within 10 days of issuing the Consumer Notice of Lead Results in Drinking Water Form to persons served by the water system, Respondent shall send IDEM a signed Certification Form for Consumer Notice of Lead Results (attached).

 

13.         Within 30 days of the Effective Date, Respondent shall respond in writing to all deficiencies noted in the Sanitary Survey conducted on March 11, 2024. The response must indicate:

1.    how Respondent will address deficiencies found during the sanitary survey; and

2.    on what schedule (milestone dates) Respondent will address deficiencies found during the sanitary survey.

 

14.         The written response required by Order Paragraph 13 is subject to IDEM approval. In the event IDEM determines that the written response submitted by Respondent is deficient or otherwise unacceptable, Respondent shall revise and resubmit the written response to IDEM in accordance with IDEM’s notice. After three submissions of such written response by Respondent, IDEM may seek civil enforcement of this Order.

 

15.         Respondent, upon receipt of written notification from IDEM, shall immediately implement the approved written response and adhere to the milestone dates therein. The approved written response shall be incorporated into the Agreed Order and shall be deemed an enforceable part thereof.

 

16.         Within 10 days of each required milestone included in the written response, Respondent shall submit to IDEM a written progress report or notification of completion for each milestone.

 

17.         All submittals required by this Agreed Order, unless Respondent is notified otherwise in writing by IDEM, shall be sent to:

 

Grant Chaddock, Enforcement Case Manager

Office of Water Quality – IGCN 1255

Indiana Department of Environmental Management

100 North Senate Avenue

Indianapolis, IN 46204-2251

 

18.         Respondent is assessed and agrees to pay a civil penalty of Thirty-One Thousand Six Hundred Dollars ($31,600). Respondent shall pay the civil penalty by the due date printed on the invoice, as attached. 

 

Civil and stipulated penalties are payable to the “Environmental Management Special Fund” by mail, phone, or online following the instructions below:

 

Mail:

Civil and stipulated penalties are payable by check to the “Environmental Management Special Fund.” Checks shall include the Case Number 2024-29995-W of this action and shall be mailed to:

 

Indiana Department of Environmental Management

Accounts Receivable

IGCN, Room 1340

100 North Senate Avenue

Indianapolis, IN 46204

 

Online:

Accounts Receivable is accepting payments online by e-Check, Master Card, Visa, or Discover.  Please visit www.IN.gov/IDEM.  Under Online Services, click Online Payment options and follow the prompts.  A processing fee of $1 plus 1.99% will be charged for credit card payments.  A processing fee of $1 will be charged for e-Check payments.  The Case Number 2024-29995-W of this action is required to complete the process.

 

Phone:

Accounts Receivable also accepts payments by phone at 317-234-3099.  Follow the instructions for Master Card, Visa, or Discover payments.  A processing fee of $1 plus 1.99% will be charged for credit card payments.  A processing fee of $1 will be charged for e-Check payments.  The Case Number 2024-29995-W is required to complete the process. 

 

19.         In the event the terms and conditions of the following paragraphs are violated, IDEM may assess and Respondent shall pay the corresponding stipulated penalty:

 

Paragraph

Violation

Stipulated Penalty

3

Failure to report any release of sanitary wastewater to waters of the State, not specifically authorized by the Permit.

$500 per week late, or part thereof.

4

Failure to submit the CP within the required time period.

$250 per week late, or part thereof.

5

For violations of terms and conditions of the Permit during the Compliance Demonstration.

$400 per violation

6

Failure to submit the AAP, if required, within the given time period.

$500 per week late, or part thereof.

7

Failure to modify the CP and/or AAP, if required, within the given time period.

$500 per week late, or part thereof.

8

Failure to meet and/or implement any milestone date set forth in the approved CP or AAP.

$500 per week late, or part thereof.

9

Failure to submit to IDEM a written progress report as specified in the CP or AAP approval letter.

$150 per week late, or part thereof.

10

Failure to operate the WWTP as efficiently and effectively as possible prior to Compliance Demonstration.

$200 per violation.

11

Failure to deliver the Consumer Notice of Lead Results in Drinking Water form to persons served.

$300 per week, or part thereof.

12

Failure to send to IDEM the Certification Form for Consumer Notice of Lead Results.

$300 per week, or part thereof.

13

Failure to submit a written response within the required time period.

$250 per week, or part thereof.

14

Failure to modify the written response, if required, within the given time period.

$300 per week late, or part thereof.

15

Failure to meet and/or implement any milestone date set forth in the approved written response.

$350 per week late, or part thereof.

16

Failure to submit to IDEM a written progress report or notification of completion of each milestone, within the given time period.

$150 per week late, or part thereof.

 

20.         Stipulated penalties shall be due and payable no later than the 30th day after Respondent receives written notice that IDEM has determined a stipulated penalty is due, the 30th day being a “Due Date.” IDEM may notify Respondent at any time that a stipulated penalty is due. Failure to notify Respondent in writing in a timely manner of a stipulated penalty assessment shall not waive IDEM’s right to collect such stipulated penalty or preclude IDEM from seeking additional relief against Respondent for violation of this Agreed Order. Neither assessment nor payment of stipulated penalties shall preclude IDEM from seeking additional relief against Respondent for a violation of this Agreed Order. Such additional relief includes any remedies or sanctions available pursuant to Indiana law, including, but not limited to, civil penalties pursuant to IC 13-30-4.

 

21.         This Agreed Order shall apply to and be binding upon Respondent, its successors and assigns. Respondent’s signatories to this Agreed Order certify that they are fully authorized to execute this Agreed Order and legally bind the party they represent. No change in ownership, corporate, or partnership status of Respondent shall in any way alter its status or responsibilities under this Agreed Order.

 

22.         In the event that the monies due to IDEM pursuant to this Agreed Order are not paid on or before the Due Date, Respondent shall pay interest on the unpaid balance and any accrued interest at the rate established by IC 24-4.6-1. The interest shall be computed as having accrued from the Due Date until the date that Respondent pays any unpaid balance. The interest shall continue to accrue on the first of each month until the civil penalty and any interest accrued are paid in full. Such interest shall be payable to the “Environmental Management Special Fund,” and shall be payable to IDEM in the manner specified above.

 

23.         In the event that any terms of this Agreed Order are found to be invalid, the remaining terms shall remain in full force and effect and shall be construed and enforced as if this Agreed Order did not contain the invalid terms.

 

24.         Respondent shall provide a copy of this Agreed Order, if in force, to any subsequent owners or successors before ownership rights are transferred. Respondent shall ensure that all contractors, firms and other persons performing work under this Agreed Order comply with the terms of this Agreed Order.

 

25.         This Agreed Order is not and shall not be interpreted to be a permit or a modification of an existing permit. This Agreed Order, and IDEM’s review or approval of any submittal made by Respondent pursuant to this Agreed Order, shall not in any way relieve Respondent of its obligation to comply with the requirements of its applicable permits or any applicable Federal or State law or regulation.

 

26.         Complainant does not, by his approval of this Agreed Order, warrant or aver in any manner that Respondent’s compliance with any aspect of this Agreed Order will result in compliance with the provisions of any permit, order, or any applicable Federal or State law or regulation. Additionally, IDEM or anyone acting on its behalf shall not be held liable for any costs or penalties Respondent may incur as a result of Respondent’s efforts to comply with this Agreed Order.

 

27.         Nothing in this Agreed Order shall prevent or limit IDEM’s rights to obtain penalties or injunctive relief under any applicable Federal or State law or regulation, except that IDEM may not, and hereby waives its right to, seek additional civil penalties for the same violations specified in the Notice of Violation.

 

28.         Nothing in this Agreed Order shall prevent IDEM (or anyone acting on its behalf) from communicating with the United States Environmental Protection Agency (US EPA) or any other agency or entity about any matters relating to this enforcement action. IDEM or anyone acting on its behalf shall not be held liable for any costs or penalties Respondent may incur as a result of such communications with the US EPA or any other agency or entity.

 

29.         This Agreed Order shall remain in effect until Respondent has complied with the terms and conditions of this Agreed Order and IDEM issues a Resolution of Case (close out) letter to Respondent.

 

 

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK.


 

TECHNICAL RECOMMENDATION:

Department of Environmental Management

RESPONDENT:

UMC Broadmore, LLC

By:

 

By:

 

 

 

Amari Farren, Chief

Printed:

 

 

Water Enforcement Section

Title:

 

 

Office of Water Quality

 

 

 

 

 

 

 

 

 

 

 

 

Date:

 

Date:

 

 

 

 

 

 

 

 

COUNSEL FOR RESPONDENT:

By:

 

Date:

 

APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL

MANAGEMENT THIS

DAY OF

, 20__.

 

For the Commissioner:

 

 

 

 

 

Martha Clark Mettler

Assistant Commissioner

Office of Water Quality