Case
No. 2004-14107-W |
|||
|
|
|
) |
|
||||
|
CITY
OF |
|
) |
|
||||
|
|
|
) |
|
||||
|
Respondent. |
|
) |
|
||||
The Complainant and the
Respondent desire to settle and compromise this action without hearing or
adjudication of any issue of fact or law, and consent to the entry of the
following Findings of Fact and Order.
Pursuant to IC 13-30-3-3, entry into the terms of this Agreed Order does
not constitute an admission of any violation contained herein. Respondent’s entry into this Agreed Order
shall not constitute a waiver of any defense, legal or equitable, which the
Respondent may have in any future administrative or judicial proceeding, except
a proceeding to enforce this order.
I. FINDINGS OF FACT
1.
Complainant is the Commissioner (hereinafter referred to as
“Complainant”) of the Indiana Department of Environmental Management, a
department of the State of
2.
The Respondent is the City of
3.
The Indiana Department of Environmental Management (“IDEM”)
has jurisdiction over the parties and subject matter of this action.
4.
Pursuant to IC 13-30-3-3, IDEM issued a Notice of Violation (“NOV”) via Certified Mail to Donnie Hastings,
Mayor, City of
5.
An inspection and record reviews were conducted on the dates
specified below by a representative of IDEM’s Office of Water Quality. The
violations described in the following paragraphs were in existence or observed
at the time of the inspection and record reviews and were cited in the NOV.
6.
Attachment A of the Permit identifies the
following sanitary sewer system overflow points in the sanitary portion of the
sewer system and prohibits them from discharging to waters of the state at any time:
|
Outfall |
Location |
Receiving Stream |
|
001 |
|
|
|
003 |
Cochran Lift Station |
Stoney Lonesome Creek |
|
004 |
|
Hogan Creek |
|
005 |
|
Hogan Creek |
Pursuant to Attachment A of the Permit, should any discharge occur,
the Respondent is required to notify the Indiana Department of Environmental
Management within 24 hours, by calling 317/232-8795 during regular business
hours or 317/233-7745 during non-business hours, and in writing within five
days of the event. The correspondence
shall include the duration and cause of discharge as well as remedial action
taken to eliminate it.
7.
Pursuant to 327
8.
An IDEM investigation was conducted at the Site on March 23,
2004. Remnants of raw sewage were
observed in Stoney Lonesome Creek, directly adjacent to the Sanitary Sewer
Overflow (“SSO”) Outfall #003. No SSO bypass report had been received by
IDEM for the discharge. A review of
records at Respondent’s Utilities Office indicated numerous incidents of SSO
discharge events at all of the SSO Outfalls listed in Attachment A of the
Permit during 2002, 2003, and 2004, and these events had not been reported to IDEM as required by Attachment A of the Permit,
in violation of IAC 327 5-2-8(1), Part II.A.1 of the Permit and Attachment A of
the Permit.
9.
Respondent did report to IDEM discharges from
SSO Outfall 003 at the
10.
Pursuant to 327 IAC 2-1-6(a)(1), all waters at all times and
at all places, including the mixing zone, shall meet the minimum conditions of
being free from substances, materials, floating debris, oil or scum
attributable to municipal, industrial, agricultural, and other land use
practices, or other discharges:
A)
that will settle to form putrescent or otherwise
objectionable deposits;
B)
that are in amounts sufficient to be unsightly or deleterious;
C)
that produce color, visible oil sheen, odor, or other
conditions in such degree as to create a nuisance;
D)
which are in amounts sufficient to be acutely toxic to, or
to otherwise severely injure or kill aquatic life, other animals, plants or humans;
and
E)
which are in concentrations or combinations that will cause
or contribute to the growth of aquatic plants or algae to such a degree as to
create a nuisance, be unsightly, or otherwise impair the designated uses.
11.
Pursuant to IC 13-18-4-5, it is unlawful for any person to
throw, run, drain, or otherwise dispose into any of the streams or waters of
Indiana; or cause, permit, or suffer to be thrown, run, drained, allowed to
seep, or otherwise disposed into any waters; any organic or inorganic matter
that causes or contributes to a polluted condition of any waters, as determined
by a rule of the board adopted under IC 13-18-4-1 and IC 13-18-4-3.
12.
An IDEM investigation was conducted on March 23, 2004. Remnants of raw sewage were observed in
Stoney Lonesome Creek, directly adjacent to SSO Outfall #003. A review of records at Respondent’s Utilities
Office indicated numerous incidents of SSO discharge events at all of the SSO
Outfalls listed in Attachment A of the Permit during 2002, 2003, and 2004. The
sewage discharges are deleterious, form putrescent or
otherwise objectionable deposits, and produce conditions in such degree as to
create a nuisance, in violation of 327 IAC 2-1-6. Furthermore, because the Respondent allowed
sewage to pollute waters of the state, and because the Respondent violated 327
IAC 2-1-6, which is a rule adopted by the Water Pollution Control Board
pursuant to IC 13-18-3, the Respondent is in violation of IC 13-18-4-5.
13.
Pursuant to IC 13-30-2-1, a person may not discharge, emit,
cause, allow, or threaten to discharge, emit, cause, or allow any contaminant
or waste including any noxious odor, either alone or in combination with
contaminants from other sources, into the environment in any form which causes
or would cause pollution which violates rules, standards, or discharge or
emission requirements adopted by the appropriate board under the environmental
management laws.
14.
An IDEM investigation was conducted on March 23, 2004. Remnants of raw sewage were observed in
Stoney Lonesome Creek, directly adjacent to SSO Outfall #003. A review of records at Respondent’s Utilities
Office indicated numerous incidents of SSO discharge events at all of the SSO
Outfalls listed in Attachment A of the Permit during 2002, 2003, and 2004. Because the Respondent allowed sewage to
pollute waters of the state, and because the Respondent violated 327 IAC 2-1-6,
which is a rule adopted by the Water Pollution Control Board pursuant to environmental management laws, the Respondent is in
violation of IC 13-30-2-1.
15.
Part I.A.3 of the Permit identifies five
Combined Sewer Overflow (“CSO”) outfalls in the Respondent’s sewage collection
system, identified as Outfalls 002, 006, 007, 008, and 009.
16.
On February 10, 2005, Respondent met with representatives of IDEM’s Office
of Water Quality concerning its Combined Sewer Overflow Long Term Control Plan (“LTCP”) submitted to IDEM on September 30, 2004, to
address CSO Outfalls 002, 006, 007, 008, and 009. The LTCP contains,
among other elements, a “Sewer Improvement and Separation Plan” that will be
implemented over a ten-year period in three phases. Full implementation of the Sewer Improvement and Separation
Plan is expected to result in 100% separation of sanitary and storm sewers, and
the elimination of all CSO discharges.
The Sewer Improvement and Separation Plan is attached to this Agreed
Order, designated as Attachment 1.
Additionally, the LTCP contains a Post Construction Compliance
Monitoring Plan that sets forth the actions that will be taken by the
Respondent to evaluate whether implementation of the Sewer Improvement and
Separation Plan results in the elimination of all CSO discharges. The Post Construction Compliance Monitoring
Plan is attached to this Agreed Order, designated as Attachment 2.
17.
On September 26, 2005, Respondent and IDEM held a settlement
conference in which the LTCP implementation schedules and compliance issues
were reviewed.
18.
In recognition of the settlement reached, the Respondent waives
any right to administrative and judicial review of this Agreed Order.
II. ORDER
1.
This Agreed Order shall be effective (“Effective Date”) when
it is approved by the Complainant or his delegate, and has been received by the
Respondent. This Agreed Order shall have
no force or effect until the Effective Date.
2.
The Respondent shall comply with 327 IAC 2-1-6(a)(1), IC
13-18-4-5, IC 13-30-2-1 and the Permit.
3.
Beginning on the Effective Date of this Agreed Order, and
continuing until implementation of the Compliance Plan required pursuant to
Order Paragraph 4 is complete, the Respondent shall, at all times, operate its
existing sewage collection system as efficiently and effectively as possible.
4.
Within 120 days of the Effective Date of this Agreed Order,
the Respondent shall develop and submit to IDEM for its approval a compliance
plan (“CP”) that includes, but is not limited
to, the following:
A.
A description of the actions that the Respondent will take
and management systems that the Respondent will develop and implement to
achieve and maintain continuous compliance with the prohibition of discharges from
Sanitary Sewer Overflow Outfalls 001 Decatur Street, 003 Cochran Street, 004
West Fourth Street, and 005 West Side lift stations contained in Attachment A
of the Permit;
B.
A description of the actions that the Respondent will take
to ensure that the collection system is at all times efficiently operated and
maintained in good working order. Such
actions shall include, but not be limited to, identification and reduction of
inflow and infiltration sources, including stormwater connections to the
collection system, to maintain compliance with the NPDES Permit; and
C.
A schedule for initiation and completion of all actions
described in the CP, including specific milestone dates.
5.
The Respondent shall, upon completion of implementation of
the portion of the CP required by Order Paragraph 4.A, be subject to the
stipulated penalties specified in Order Paragraph 23 below for violation of the
prohibition to discharge from SSO points identified in Attachment A of the
Permit.
6.
The Respondent shall, within 12 months of the completion of
the portion of the CP required by Order Paragraph 4.A (Performance Period),
demonstrate for a period of 10 consecutive months, compliance with the
prohibition of discharges from SSO’s
identified in Attachment A of the Permit.
In the event that a discharge violation occurs during the Performance
Period, the Respondent shall, within 60 days of becoming aware of the violation,
submit to IDEM for its approval, an SSO Elimination Compliance Plan, that
includes a description of the additional actions that the Respondent will take
to achieve and maintain continuous compliance with the Permit and a schedule,
including specific milestone dates for initiating and completing such actions.
7.
The plans required by Order Paragraphs 4. and 6. are subject
to IDEM approval. In the event that IDEM
determines any plan to be deficient or otherwise unapprovable, the Respondent
shall, upon written notice by IDEM, revise and resubmit the plan, in accordance
with IDEM’s written notice. If, after
three submissions of the plan by the Respondent, IDEM finds the plan to be
deficient or otherwise unapprovable, IDEM may require the Respondent to revise
and resubmit the plan, or alternatively, may modify and approve the plan, in
which case the Respondent shall implement the plan as modified and approved by
IDEM.
8.
Upon approval by IDEM, any plan required pursuant to this
Agreed Order shall be incorporated into the Agreed Order and shall be deemed an
enforceable part thereof. The
Respondent, upon receipt of written approval from IDEM, shall immediately
implement the approved plan and adhere to the schedule contained therein.
9.
The Respondent shall notify IDEM, in writing, within 10 days
of completion of each action or milestone contained in any plan approved by
IDEM pursuant to this Agreed Order. The notification shall include a
description of the action completed and the date it was completed.
10.
Within 30 days of the Effective Date of this Agreed Order,
the Respondent shall determine whether it has sufficient legal authority to:
A.
implement and enforce its sewer use ordinances, service
agreements and/or other legally binding documents;
B.
require that all sewers and connections be properly designed
and constructed;
C.
test and inspect all new and rehabilitated sewers, including
both collector sewers and service laterals;
D.
regulate flows from satellite collection systems (if any);
and
E.
prohibit the connection or introduction of stormwater
sources to the sanitary collection system.
11.
In the event that the Respondent determines that it does not
have the legal authority described in Order Paragraph 10, the Respondent shall
take all necessary steps to obtain such legal authority.
12.
Within 120 days of the Effective Date of this Agreed Order,
the Respondent shall submit to IDEM a statement certifying that it has the
legal authority described in Order Paragraph 10.
13.
Beginning on the Effective Date, the Respondent shall inspect
its sanitary sewer overflow outfall portion of its sewage collection system
during and/or after precipitation events, in order to determine whether a
discharge has occurred. The Respondent shall document its inspections by
recording the following:
A.
the date and time of the inspection;
B.
the name of the person(s) conducting the inspection;
C.
the date the precipitation event began;
D.
the time the precipitation event began (estimated or actual)
and, for inspections conducted after the precipitation event, the time the
precipitation event ended (estimated or actual), and the volume (estimated or
actual) of the precipitation event;
E.
observations as to whether a discharge from the sanitary
collection system occurred, is occurring, or is about to occur, and if so the
location of the discharge/impending discharge; and
F.
the remedial measures taken in the event that a discharge is
found to have occurred, to be occurring, or about to occur.
The Respondent shall maintain the required documentation at the Utility Office
and shall make such documentation available to IDEM representatives for
inspection and/or copying upon request.
14.
Beginning on the Effective Date, in the event that a
discharge from the sanitary sewer portion of its collection system occurs the
Respondent shall report overflows and perform a response, as follows:
A.
take all reasonable actions to cease the discharge as soon
as possible;
B.
properly clean the affected area;
C.
remove and properly dispose of sewage and debris from the
affected area;
D.
report the discharge event as follows
(i)
Within 24 hours of the Respondent’s discovery of the
discharge, the Respondent shall provide verbal notification of the event to
IDEM, at 317/232-8795 (or 317/232-8694) during regular business hours or
317/233-7745 during non-business hours;
(ii)
Within five days of the Respondent’s discovery of the
discharge, the Respondent shall submit written notification of the discharge to
IDEM. The notification shall include the
following information: the duration and cause of the discharge and the remedial
action taken to eliminate it;
(iii)
The Respondent shall report the duration and estimated
volume of the discharge on the Discharge Monitoring Report and the Monthly
Report of Operation; and
E.
document all actions taken to cease the discharge and to
remediate the affected areas, maintain copies of the documentation at the WWTP,
and make such documentation available to IDEM representatives for inspection
and/or copying upon request.
15.
The Respondent shall implement the Sewer
Improvement and Separation Plan set forth in Attachment 1, in accordance with
the schedule contained therein.
16.
The Respondent shall implement the Post
Construction Compliance Monitoring Plan set forth in Attachment 2, in
accordance with the schedule contained therein.
17.
Within 60 days after completion of each phase of the Sewer
Improvement and Separation Plan and the associated portions of the Post
Construction Compliance Monitoring Plan, the Respondent shall submit to IDEM,
for review and approval, a report that
contains a summary of the data gathered as a result of the post construction
compliance monitoring and an evaluation of the success of the phase in
eliminating CSO discharges. The
Respondent shall adequately address any IDEM comments
regarding the report, within the timeframe required by IDEM. The Respondent’s obligations under this
provision include, but are not limited to, gathering additional post
construction compliance monitoring data in the event that IDEM deems necessary.
18.
In the event that data resulting from implementation of the
Post Construction Compliance Monitoring Plan, or other information indicates
that any phase of the Sewer Improvement and Separation Plan is not adequate to
eliminate CSO discharges, the Respondent shall, within 90 days of becoming
aware of such inadequacy, develop and submit to IDEM, for approval, a CSO
Compliance Plan (CP) that identifies:
a.
the additional measures that will be implemented by the
Respondent in order to eliminate CSO discharges; and
b.
the post construction compliance monitoring program that
will be implemented by the Respondent in order to determine whether the
additional measures, upon implementation, are adequate to eliminate CSO
discharges, along with a schedule, that includes specific milestone dates, for
implementation of the post construction compliance monitoring.
19.
The CSO CP is subject to IDEM approval. Following receipt of the CSO CP, IDEM may, in
writing: (a) approve all of or any portion of the CSO CP; (b) approve all or a
portion of the CSO CP upon specified conditions; (c) disapprove of all or any
portion of the CSO CP, notifying the Respondent of deficiencies in the CP and
granting the Respondent additional time within which to correct the
deficiencies; (d) modify the submission to correct deficiencies; or (e) reject
all or any portion of the CP.
20.
The Respondent, upon receipt of written
notification from IDEM of approval of the CSO CP, shall immediately implement
the approved CSO CP and adhere to the schedules contained therein. The approved CSO CP shall be incorporated
into this Agreed Order and shall be deemed an enforceable part thereof.
21.
All submittals required by this Agreed Order, unless
notified otherwise in writing, shall be sent to:
|
Paul
Cluxton, Enforcement Case Manager |
|
Indiana
Department of Environmental Management |
|
Office
of Enforcement – Mail Code 60-02 |
|
|
|
|
22.
The Respondent is assessed a civil penalty of Five Thousand
One Hundred Dollars ($5,100). The civil
penalty shall be paid in the following manner:
|
Amount Due |
Date Due |
|
$1,275 |
within 90 days of the Effective Date of this Agreed
Order |
|
$1,275 |
within 180 days of the Effective Date |
|
$1,275 |
within 270 days of the Effective Date |
|
$1,275 |
within 365 days of the Effective Date |
Said penalty amount shall be due and payable to the Environmental
Management Special Fund, reference Case 2004-14107-W on the check, and mail to
the address in Paragraph 25 of this Agreed Order.
23.
In the event the terms and conditions of the following Order
paragraphs are violated, the Complainant may assess and the Respondent shall
pay a stipulated penalty in the following amount:
|
Order Paragraph Number |
Violation
|
Penalty Amount |
|
4 |
Failure
to submit the CP, as required. |
$250 per each week or
part thereof late |
|
5 |
Violation
of SSO discharge prohibition contained in Attachment A of the Permit,
subsequent to completion of implementation of the portion of the CP required
pursuant to Order Paragraph 4.A. |
$1000 per violation |
|
6 |
Failure
to submit SSO Elimination Compliance Plan, if required. |
$250 per each week or
part thereof late |
|
7 |
Failure
to revise and resubmit any plan required pursuant to this Agreed Order, as
required. |
$250 per each week or
part thereof late |
|
8 |
Failure
to implement an approved plan, or to meet any milestone date set forth in any
approved plan. |
$500 per each week or
part thereof late |
|
9 |
Failure
to notify IDEM, in writing, within 10 days of completion of each action
contained in the approved action plan. |
$250 per each week or part thereof late |
|
12 |
Failure
to timely submit certification statement. |
$250 per each week late |
|
13 |
Failure
to inspect sanitary collection system, as required. |
$500 per violation |
|
13 |
Failure
to document inspections of sanitary collection system or make documentation
available to IDEM, as required. |
$500 per violation |
|
14 |
Failure
to take all reasonable actions to cease the discharge as soon as possible;
properly clean the affected area; remove and properly dispose of sewage and
debris from the affected area; or report the discharge event, as required. |
$500
per violation |
|
14 |
Failure
to document action taken to cease the discharge and to remediate the affected
areas, or make documentation available to IDEM, as required. |
$500
per violation |
|
15 |
Failure to implement the Sewer Improvement and Separation Plan
and adhere to the milestone dates set forth in the schedule. |
$500 per each week or part thereof late |
|
16 |
Failure to implement the Post Construction Compliance Monitoring
Plan and adhere to the milestone dates set forth in the schedule. |
$500 per each week or part thereof late |
|
17 |
Failure to timely submit report/data. |
$500 per each week or part thereof late |
|
17 |
Failure to timely address any IDEM written concerns prior to
approval of determination of success. |
$500 per each week or part thereof late |
|
18 |
Failure to timely submit a complete and sufficient CSO CP. |
$500 per each week or part thereof late |
|
19 |
Failure to timely revise and resubmit the CSO CP in accordance
with written notice by IDEM. |
$500 per each week or part thereof late |
|
20 |
Failure to comply with any milestone date contained in the
schedules set forth in the CSO CP. |
$500 per each week or part thereof late |
24.
Stipulated penalties shall be due and payable within thirty
days after the Respondent receives written notice that the Complainant has
determined a stipulated penalty is due.
Assessment and payment of stipulated penalties shall not preclude the
Complainant from seeking any additional relief against the Respondent for
violation of the Agreed Order. In lieu
of any of the stipulated penalties given above, the Complainant may seek any
other remedies or sanctions available by virtue of the Respondent’s violation
of this Agreed Order, or
25.
Civil and stipulated penalties are payable by check to the
Environmental Management Special Fund.
Checks shall include the Case Number of this action and shall be mailed
to:
|
Indiana
Department of Environmental Management |
|
Cashiers
Office – Mail Code 50-10C |
|
|
|
|
26.
In the event that the civil penalty required by Order
Paragraph 22, is not paid within 30 days of the Effective Date of this Agreed
Order, the Respondent shall pay interest on the unpaid balance at the rate
established by IC 24-4.6-1-101. The
interest shall continue to accrue until the civil penalty is paid in full.
27.
This Agreed Order shall apply to and be binding upon the
Respondent, its successors, and assigns.
The Respondent’s signatories to this Agreed Order certify that they are
fully authorized to execute this document and legally bind the parties they
represent. No change in ownership,
corporate, or partnership status of the Respondent shall in any way alter its
status or responsibilities under this Agreed Order.
28.
In the event that any terms of the Agreed Order are found to
be invalid, the remaining terms shall remain in full force and effect and shall
be construed and enforced as if the Agreed Order did not contain the invalid
terms.
29.
The Respondent shall provide a copy of this Agreed Order, if
in force, to any subsequent owners or successors before ownership rights are
transferred. The Respondent shall ensure
that all contractors, firms and other persons performing work under this Agreed
Order comply with the terms of this Agreed Order.
30.
This Agreed Order is not and shall not be interpreted to be
a permit or a modification of an existing permit. This Agreed Order, and IDEM’s review or
approval of any submittal made by the Respondent pursuant to this Agreed Order,
shall not in any way relieve the Respondent of its obligation to comply with
the requirements of any applicable permit or order or with any other applicable
federal or state law or regulation.
31.
The Complainant does not, by its approval of this Agreed
Order, warrant or aver in any manner that the Respondent’s compliance with any
aspect of this Agreed Order will result in compliance with the provisions of
any permit or order or any applicable federal or state law or regulation. Additionally, IDEM or anyone acting on its
behalf shall not be held liable for any costs or penalties the Respondent may
incur as a result of Respondent’s efforts to comply with this Agreed Order.
32.
Nothing in this Agreed Order shall prevent or limit IDEM’s
rights to obtain penalties or injunctive relief under any applicable federal or
state law or regulation, except that IDEM may not seek additional civil
penalties for the violations specified in the Notice of Violation.
33.
Nothing in this Agreed Order shall prevent IDEM or anyone
acting on its behalf from communicating with the United States Environmental
Protection Agency (“EPA”) or any other agency or entity about any matters
relating to this enforcement action.
IDEM or anyone acting on its behalf shall not be held liable for any
costs or penalties the Respondent may incur as a result of such communications
with the EPA or any other agency or entity.
34.
"Force Majeure" for purposes of this Agreed Order,
is defined as any event arising from causes totally beyond the control and
without fault of the Respondent that delays or prevents the performance of any
obligation under this Agreed Order despite Respondent’s best efforts to fulfill
the obligation. The requirement that the
Respondent exercise "best efforts to fulfill the obligation" includes
using best efforts to anticipate any potential force majeure event and best
efforts to address the effects of any potential force majeure event (1) as it
is occurring and (2) following the potential force majeure event, such that the
delay is minimized to the greatest extent possible. "Force Majeure" does not include
changed business or economic conditions, financial inability to complete the
work required by this Agreed Order, or increases in costs to perform the work.
The Respondent shall notify IDEM by calling the case manager within three (3)
calendar days and by writing no later than seven (7) calendar days after it has
knowledge of any event which the Respondent contends is a force majeure. Such notification shall describe the
anticipated length of the delay, the cause or causes of the delay, the measures
taken or to be taken by the Respondent to minimize the delay, and the timetable
by which these measures will be implemented.
The Respondent shall include with any notice all available documentation
supporting its claim that the delay was attributable to a force majeure. Failure to comply with the above requirements
shall preclude Respondent from asserting any claim of force majeure for that
event. The Respondent shall have the
burden of demonstrating that the event is a force majeure. The decision of whether an event is a force
majeure shall be made by IDEM.
IDEM agrees that, if a delay is attributable to a force majeure, IDEM shall
extend, in writing, the time period for performance under this Agreed Order, by
the amount of time that is directly attributable to the event constituting the
force majeure.
35.
This Agreed Order shall remain in effect until the
Respondent has complied with the terms of Order Paragraphs 3 through 26 and
IDEM issues a Close-Out letter to the Respondent.
|
TECHNICAL RECOMMENDATION: |
|
RESPONDENT: |
||||||||
|
Department of
Environmental Management |
|
City of |
||||||||
|
|
|
|
||||||||
|
By: |
___________________ |
|
By: |
Hon. Donnie Hastings,
Mayor |
||||||
|
|
Mark W. Stanifer, Chief |
|
|
City of |
||||||
|
|
Water Enforcement Section |
|
|
|
||||||
|
|
Office of Enforcement |
|
|
|
||||||
|
|
|
|
|
|
||||||
|
Date: |
____________________ |
|
Date: |
____________________ |
||||||
|
|
|
|
||||||||
|
COUNSEL FOR COMPLAINANT: |
|
COUNSEL FOR RESPONDENT: |
||||||||
|
Department of
Environmental Management |
|
|
||||||||
|
|
|
|
||||||||
|
By: |
______________________ |
|
By: |
________________ |
||||||
|
|
Joseph H.
Merrick |
|
|
|
||||||
|
|
Office of Legal Counsel |
|
|
|
||||||
|
|
|
|
|
|
||||||
|
Date: |
_____________________ |
|
Date: |
________________ |
||||||
|
|
|
|
|
|
||||||
|
APPROVED AND ADOPTED BY
THE INDIANA DEPARTMENT OF ENVIRONMENTAL |
||||||||||
|
MANAGEMENT
THIS |
|
DAY OF |
|
, 200 |
|
. |
||||
|
|
||||||||||
|
|
For The Commissioner: |
|||||||||
|
|
|
|||||||||
|
|
(Signed November 4, 2005) |
|||||||||
|
|
Matthew T. Klein |
|||||||||
|
|
Assistant Commissioner |
|||||||||
|
|
of Compliance and
Enforcement |
|||||||||
Attachment 1
Sewer
Improvement and Separation Plan
Description
The first phase of the project involves the upgrade
of the Cochran PS and the construction of the new forcemain. By implementing this phase, flows collected
upstream of the combined system will be rerouted directly to the Moore Street
Station. Overflows at each existing CSO
point will therefore be reduced. By
implementing this phase first, lines in the separated system will be accurately
sized for twenty-year design flows. If
the installation of the new forcemain was implemented last, sanitary lines in
the downtown area would be overly sized to accommodate flows until the new
forcemain was installed. This would
require higher capital construction costs.
This phase is expected to be constructed in year three (3) of the ten
(10) year schedule.
Each sensitive area identified in this report is a
priority for CSO removal. The City’s CSO’s are located relatively close
together and each sensitive area identified is downstream of the combined sewer
overflow region, with the exception of Area Nos.1 and 2, located next to, and
across the river from, the CSOs. Since
each area of priority is downstream of or coincident with the CSO discharge
points, and the distance from that area to each CSO is similar, each area could
be impacted by a discharge event. The
best way to prioritize CSOs for removal, therefore, is not by location, but by
discharge quantity. By implementing the
upgrade of the Cochran station and the new forcemain project as Phase 1, the
majority of sanitary flows through the downtown area will be rerouted and
therefore eliminated from overflowing.
The new forcemain will greatly reduce both overflow volumes and
contaminant levels.
Separation efforts comprise two of the project’s
three phases – Phases 2 and 3. The
second phase of the project will be constructed in approximately year six (6)
and will involve separating the southern portion of the system. Phase 2 will comprise approximately 66% of
separation efforts. This phase will route
all sanitary flow to the Importing Street Lift Station and all stormwater to
outfall No. 008.
Phase 3 of the project will separate the remaining
34% of the system, located in the northern downtown area. This phase will also direct sanitary flow to
the Importing Street Station. Stormwater
flows will be directed to outfalls 009 and 002.
CSO 006 will also be plugged and abandoned as part of Phase 3. This final phase will be constructed in
approximately year nine (9).
Schedule
Phase 1
|
Preliminary
|
October-November
2005 |
|
|
Design |
October-March
2006 |
|
|
IDEM
Review |
April-May
2006 |
|
|
Bidding |
June
2006 |
|
|
Notice
of Award/Start Constr. |
August
2006 |
|
|
Construction |
August-May
2007 |
|
|
System
Startup |
June-August
2007 |
|
Phase 2
|
Planning |
September
–February 2009 |
|
|
Design |
February
2009-August 2009 |
|
|
Construction |
August
2009-August 2010 |
|
|
System
Startup |
September-October
2010 |
|
Phase 3
|
Planning |
September-February
2013 |
|
|
Design |
February
2013-August 2013 |
|
|
Construction |
August
2013-August 2014 |
|
|
System
Startup |
September-October
2014 |
|
Attachment 2
Post
Construction Compliance Monitoring Plan
Phase
1 construction will greatly reduce overflows at CSO 002, 006, 007, 008, and
009. During Phase 2 construction, CSO
007 and 008 will be converted to storm sewer outfalls, therefore CSO discharges
at 007 and 008 will be eliminated in their entirety, while discharges at CSOs
009, 002 and 006 will be further reduced.
During Phase 3 construction CSOs 009, 002 and 006 will also be
eliminated. Before, during and after
Phase 1 and 2 construction is completed, the City of
1.
Prior to Construction:
E. coli,
BOD,TSS and Ammonia testing at outfalls to confirm baseline count. Baseline testing has already been completed
at outfalls 002 and 009. Baseline
testing will be completed at Outfalls 006, 007, and 008 prior to Phase 1
construction. This will be done for
different storm events and various seasons as found practical based on project
schedules.
2.
Following Phase I and II construction during Wet Weather
Events:
Sampling
following Phase 1 and Phase 2 construction at Outfalls 002, 006, 007, 008, and
009 during wet weather conditions.
Sampling will begin at the start of a discharge event with samples
collected every 15 minutes for the first hour of the event and hourly
thereafter for the duration of the event.
Sampling will be done for three (3) separate precipitation events in
order to collect data from different types of storms and multiple seasons. Testing will include E.coli, BOD, TSS
and Ammonia.
3.
Annually during and following construction until the Sewer
Improvement and Separation Plan is fully implemented:
E. coli,
BOD, TSS, and Ammonia testing at outfalls to demonstrate improvements during
project implementation.
4.
Following Phase 3 construction during Wet Weather Events:
Phase 3 will effectively eliminate all combined sewer overflows in
Furthermore, for the third phase monitoring, the sampling of three separate
precipitation events shall commence 20 minutes after the rain event
begins. With respect to Outfalls 002,
007, 008, and 009, the end of pipe sampling location shall be indicated on a
map attachment to each summary report as the first available upstream manhole
on each outfall discharge line for Outfalls 002, 007, 008, and 009, because the
end of these pipes are submerged in the Ohio River. With respect to Outfall 006, the post construction
monitoring needs to provide for visual monitoring to determine whether
discharges occur, as this outfall is to be plugged/physically eliminated.