CADDNAR


[CITE: Solar Sources, Inc., v. DNR, DOR, 4 CADDNAR 60 (1988)]

 

[VOLUME 4, PAGE 60]

 

Cause #: 87-019R

Caption: Solar Sources, Inc., v DNR, DOR
Administrative Law Judge: Drew
Attorneys: Runnells; Szostek, DAG
Date: January 26, 1988

ORDER

 

Notice of Violation #N70304-S-00109 is vacated.

FINDINGS OF FACT

 

1. On March 31, 1987, Solar Sources, Inc. (The "Claimant") requested administrative review regarding the issuance of Notice of Violation #N70304-S-00109.

 

2. IC 4-22-1 and IC 1 3-4.1-11-8 (The Surface Coal Mining Act) apply to this proceeding.

 

3. The Department of Natural Resources (the "Department") is an agency as defined in IC 4-22-1. The Director is the ultimate authority for the Department with respect to this proceeding.

 

4. The Director has jurisdiction over the subject matter and the parties to this action.

 

5. Notice of hearing was given to: Mary M. Runnells, Attorney for Solar Sources; Felson Bowman, Resident Agent; Steven Szostek, Deputy Attorney General; Elizabeth Holder, Warrick County Recorder.

 

6. On May, 1987, a hearing was conducted pursuant to IC 13-4.1, IC 4-22-1, and 310 IAC 0.5.

 

7. The Claimant holds permit S-00109 to conduct surface coal mining activities in Warrick County, Indiana at its Pit # 17.

 

8. On March 4, 1987, an authorized representative of the Director cited Claimant with Notice of Violation #N70304-S-00109 for failure to reclaim the affected area to the approved postmining land use or obtain approval for an alternate use in violation of 310 IAC 12-5-68(A)(1) and (2), (c)(2) and (4).

 

9. The affected area involves 9.6 acres of non-prime farmland on property owned by Enos Wagler and permitted to the Claimant under permit S-00109. According to the permit, the affected area is to be reclaimed in pasture and hay.

 

10. During an inspection conducted by Respondent on November 18, 1986, five turkey barns were observed in various stages of construction on the area in question. The inspector was then informed by the landowner's wife that the affected area had been sold to Mr. Denny Hughes.[FOOTNOTE 1].

 

11. As of November 18, 1987, Claimant had not submitted a request for a postmining land use change in accordance with 310 IAC 12-5-68.

 

12. Monthly inspection reports between November, 1986 and February, 1987, commented on the progress of the barns' construction and Claimant's progress toward filing its request for a postmining land use change. The February inspection report gave claimant until the 27th to file all necessary paperwork.

 

13. On March 4, 1987, Respondent issued Notice of Violation #N70304-S-00109 citing Claimant with failing to obtain approval for a postmining land use change.

 

14. Claimant does not contend that construction of the barns on the affected area does not require conformance to 310 IAC 12-5-68. Claimant does contend, however, the issuance of the Notice of Violation was premature.

 

15. It is uncontroverted that Claimant was unaware of the affected area's change in ownership or the construction of the turkey barns until it received Respondent's November 18, inspection report.[FOOTNOTE 2]

 

16. After receiving the November inspection report, Claimant notified Mr. Hughes that a request for a postmining land use change was required and listed all the information Claimant believed necessary to complete the request.[FOOTNOTE 3].

 

17. Between November and March, Claimant and Respondent conversed several times regarding the status of Claimant's postmining land use change request. Respondent was also informed of Claimant's ongoing problems in contacting Hughes and obtaining the proper information from him.[FOOTNOTE 4]

 

18. No evidence was presented showing environmental harm resulted from the change in land use on the affected area. In fact, Respondent allowed Claimant several extensions (until April 20, 1987) for filing its request.

 

19. 310 IAC 12-4-7 (e) states:

 

(e) The bond liability of the permittee shall include only those actions which the operator is obliged to take under the permit. Actions of third parties which are beyond the control of the operator and for which the operator is not responsible under the permit need not be covered by the bond.

 

20. As

 

[VOLUME 4, PAGE 61]

 

previously noted, there is no disagreement between the parties that Claimant was without knowledge of the eventual purchase and land use change of the affected area. Neither has any evidence been presented which would show Claimant had any control over the actions of the third party (in this case, Mr. Hughes and the Perdue-Shenandoah Corporation).

 

21. Claimant, at the time the Notice of Violation was issued, had not requested a bond release for the area in question.

 

22. At the hearing, Respondent's representative testified that requests for bond release may be denied id a specified land use has not been met, as opposed to issuing a Notice of Violation.[FOOTNOTE 5]

 

23. Claimant was in the process of preparing all necessary documentation to complete its request to Respondent for a postmining land use change and Respondent was kept informed of its progress. There is no evidence that any environmental problems occurred on the affected area nor was Claimant in a position to control the actions of the third party.


FOOTNOTES

 
1. The property was actually sold on November 10, 1986, to Double H & T, Inc., a company on contract with the Perdue-Shenandoah Corporation of which Mr. Hughes is the housing manager.

2. George Boyles, Reclamation Manager for Claimant, testified that he visited the site on November 8 and noted that the site was being properly vegetated and proceeding according to the reclamation plans.

3. Claimant's representative, George Boyles, testified that he believed it was his responsibility to complete the necessary documentation and it was Hughes' responsibility to supply the appropriate information.

4. Testimony given at the hearing indicated Hughes was seldom in his office. Testimony also revealed that Hughes had difficulty in locating certain documents or sent to Boyles incomplete information.

5. Claimant contends that the Notice of Violation was prematurely written because Claimant had yet to ask for a bond release on the affected area. Once that occurred, then Respondent would have been free to deny its request based upon Claimant's failure to reclaim the area in accordance with the permit. Claimant therefore contends that Respondent acted prematurely by issuing the Notice of Violation before Claimant even asked for a bond release. Claimant's argument implies that in a situation such as this, where a land use change has occurred without the proper approval of the regulating authority, the issuance of a Notice of Violation is inappropriate and the regulating authority must consequently suspend any action it would normally take until a bond release has been requested. This should not be the case, nor should this recommendation be so constructed. However, within the narrow parameters of this particular cause, where there has been no showing of nay negative environmental impact, where numerous time extensions were granted by the regulating authority and, in fact, where several months passed before a Notice of Violation was issued and where the Claimant was without knowledge or control of a third party's actions, all those factors combine to indicate the Notice of Violation was prematurely issued.