[CITE: Squaw Creek v. DNR, 4 CADDNAR 40 (1987)]
[VOLUME 4, PAGE 40]
Cause #: 86-128R
Caption: Squaw Creek v. DNR
Administrative Law Judge: Drew
Attorneys: Joest; Szostek,
DAG
Date: April 27, 1987
ORDER
"Condition
(11) of Permit #S-00009-2, issued to Squaw Creek Coal Company, South Field Mine
in Warrick County, Indiana is affirmed."
FINDINGS OF FACT
1.
On August 11, 1986, the Natural Resources Commission's delegates approved
Permit #S-00009-2 for the Squaw Creek Mine, South Field amendment in Warrick
County, Indiana.
2.
Finding (b) and (1) in the recommendations of the Director, adopted by the
Commission's delegates, in issuing permit #S-00009-2 were
as follows:
(b)
Squaw Creek Coal Company has demonstrated that surface coal mining and
reclamation operations, as required by IC 13-4.1 and the regulations (310 IAC
12), can be accomplished under the mining and reclamation operations plan
contained in the application.
EXCEPTION:
Squaw Creek Coal Company has submitted a plan for restoration of prime farmland
soils. However, the Director herein finds that the requirements of 310 IAC 12
have not been satisfied. Therefore, no prime farmland soils may be disturbed
until Squaw Creek Coal Company submits a revised plan of restoration and the
Director finds compliance with the regulations (310 IAC 12). (1) Squaw Creek
Coal Company has not demonstrated and the Director cannot find, after
consultation with the Secretary of Agriculture, that it has a technological
capability to restore the prime farmland, within a reasonable time, to
equivalent or higher levels of yield as nonmined
prime farmland in the surrounding area under equivalent levels of management.
EXCEPTION:
As cited earlier in finding (b), Squaw Creek Coal Company has not satisfied the
requirements of the regulations (310 IAC 12) to the Director.
3.
Condition (11) imposed by the Commission's delegates on Permit #s-00009-2 was
as follows:
(11)
No mining operations occur and bond not be submitted on lands classified as
prime farmland on the map entitled "Soils Map-Prime Farmland", dated
April 25, 1986, until Squaw Creek Coal Company submits to the Division, and the
Director approves a plan for restoration of prime farmland soils in compliance
with regulations (310 IAC 12).
4.
This decision was served on Squaw Creek by certified mail, return receipt
requested, and was received on August 14, 1986.
5.
On September 15, 1986, Squaw Creek requested review of the Commission's
decision.
6.
IC 4-22-1 and IC 13-4.1 apply to this proceeding.
7.
The Department of Natural Resources is an agency as defined in IC 4-22-1. The Natural
Resources Commission is the ultimate authority of the Department with respect
to the proceedings involving the issuance of surface coal mining permits.
8.
The Commission has jurisdiction over the subject matter and the parties to this
proceeding.
9.
On January 29 and 30, 1986, a hearing was held in Indianapolis pursuant to
notice and the parties presented evidence.
10.
IC 13-4.1-4-3(d) provides:
(d)
In addition to finding the application in compliance with subsection (a), if
the proposed mining area contains prime farmland pursuant to IC
13-4.1-3-3(a)(16), the Director shall, after consultation with the United
States Secretary of Agriculture and pursuant to rules adopted by the
Commission, grant a permit to mine on prime farmland if the Director finds in
writing that the operator has the technological capability to restore that
mined area, within a reasonable time, to equivalent or higher levels of yield
as nonmined prime farmland in the surrounding area
under equivalent levels of management and can meet the soil reconstruction
standards in IC 13-4.1-8-1(7). However, this subsection does not apply to any
existing surface coal mining operations which held a valid permit on August 3,
1977, with continuous permits since that date.
11.
The area permitted under Permit #S-00009-2 contained some prime farmland which
was not exempted from the
[VOLUME 4, PAGE 41]
requirements of IC 13-4.1 by the
exclusion set forth in IC 13-4.1-4-3(d).
12.
This dispute involves the adequacy of Squaw Creek's proposed prime farmland
restoration plan (hereinafter "the plan") submitted in connection
with its #S-00009-2 permit application.
13.
Squaw Creek's plan proposes to replace the subsoil in prime farmland areas with
a substitute material referred to by Squaw Creek as "Conditioned graded
cast overburden" which is defined by Squaw Creek as graded cast overburden
meeting the following criteria: a) a pH of 6.0 or higher; b) no acid or toxic
material present; c) high available water holding capacity; d) a slake-durability
index of 0-40; e) not more than 15 percent unweatherable
rock with no rocks greater than four inches in size.
14.
The original plan submitted by Squaw Creek called for topsoil replacement of
8-12 inches of a mixture of A and B horizon material (i.e. a mixture of topsoil
and upper subsoil) over the conditioned graded cast overburden. It was this
plan that was initially disapproved on August 11, 1986 when condition (11)
(which required Squaw Creek's plan to be in accordance with regulations found
in 310 IAC 12) was imposed on its #S-00009-2 permit.
15.
In discussions with the Division of Reclamation staff subsequent to the
submission of the #S-00009-2 plan, Squaw Creek indicated that it intended to
revise its proposed plan to provide for replacement of 15-20 inches of the A/B
mixture over conditioned graded cast overburden. On January 12, 1987, both
parties stipulated that such revision would be reflected in the permit
application documents. As modified the #S-000092 plan was substantially
identical to the #S-00009 plan as approved by the Director in July, 1984.[FOOTNOTE 1]
16.
Permit #S-00009-2 is an amendment to Permit #S-00009 approved by the Natural
Resources Commission and issued by the Director to Squaw Creek for its Squaw
Creek Mine, South Field in October, 1983. Permit #s-00009 was originally issued
subject to a condition similar to condition (11) on permit #S-00009-2 which is
in dispute in this proceeding. However, on July 23, 1984, the Director approved
a plan for Squaw Creek's agronomist, Randy Staley, testified that in his
opinion as a certified professional agronomist, Squaw Creek's #S-00009-2 prime
farmland modified, would result in the successful restoration of prime farmland
productivity on the prime farmland soils within the #S-00009-2 permit area.
[17.
Editor’s Note: A review of
microfilm did not reveal omitted information.]
18.
Division of Reclamation agronomist, Steven Wade, testified that in his opinion
as a certified professional agronomist, Squaw Creek's #S-00009-2 plan would not
result in the successful restoration of prime farmland productivity in accordance
to the requirements set forth in 310 IAC 12-5-146 (a). He had therefore
recommended that the plan not be approved and the Director's findings on Squaw
Creek's plan had been based on his recommendation.[FOOTNOTE 3]
19. Squaw
Creek maintains that because Respondent failed to approve essentially the same
plan which had previously been approved in its #S-00009 plan,
and because Respondents allegedly failed to give a reasoned justification for
such disapproval, Respondents has acted arbitrarily and capriciously.
20.
In determining whether Respondent's action in disapproving the plan was an
arbitrary and capricious act, Squaw Creek must show that there was no
reasonable basis for Respondent's decision. [Board of Trustees of Public Employees' Retirement Fund v. Baughman,
450 N.E. 2d 95 (Ind. App. 1983)] that Respondent disregarded the facts of the
case, [Johnson v. Moritz, 426 N.E. 2d 448 (Ind. App.. 1981)] or that a
reasonable and honest person could not have reached the same conclusion, [Metropolitan School District of Martinsville
v. Mason, 451 N.E. 2d 349 (Ind. App. 1983)].
21.
Wade testified at the hearing that he had essentially four concerns with Squaw
Creek's proposed use of conditioned graded cast overburden as a substituted subsoil. These concerns include; the
percentage of course fragments found in the proposed subsoil, the level of
toxic materials, the soil's water holding capacity and the soul's moist bulk
density.
22.
Wade's concerns (as stated above) led him to conclude that the subsoil
substitute proposed by Squaw Creek could not achieve the desired productivity
levels required in 310 IAC 12-5-146(a). In particular, Wade believed the 15
percent unweatherable rock proposed by Squaw Creek as
comprising part of the conditioned graded cast overburden was excessive and
that the subsoil should contain no more than 5 percent unweatherable
rock (or "course fragments".)[FOOTNOTE
4]
23.
Comments provided by the Soil Conservation Service (hereinafter the
"SCS") also stated concerns similar to those expressed by Respondent.
In particular, Respondent and the SCS questioned a laboratory analysis
conducted on Squaw
[VOLUME 4, PAGE 42]
Creek's
behalf to determine the water holding capacity of the conditioned graded cast
overburden. The results indicated that the water holding capacity of the
conditioned graded cast overburden was acceptable but both Respondents and the
SCS questioned the procedure by which those results were obtained.
Consequently, Respondent relied on other methods and studios to determine the
water holding capacity of the conditioned graded cast overburden.[FOOTNOTE 5]
24.
Wade also testified that corn growth in the soil types found in Squaw Creek's
#S-00009-2 permitted area had pre-mining productivity levels of 105-115 bushels
of corn per acre. He further testified that corn grown in a subsoil consisting
of graded cast overburden materials would have a projected a yield of 65
bushels per acre. Wade believed that even with the "conditioning" of
the graded cast overburden (as proposed by Squaw Creek) the difference in
yields was too large to overcome in order to achieve acceptable productivity
levels.[FOOTNOTE 6]
25.
During the course of reviewing Squaw Creek's #S-00009-2 permit and prime
farmland restoration plan (both prior to and following Respondent's rejection
of the plan), the parties met on several occasions in an effort to create a
mutually satisfactory plan. During the course of these discussions, both
parties exchanged letters and other memoranda detailing their questions and
responses.[FOOTNOTE 7]
26.
Based on the above finding, Respondent's refusal to approve Squaw Creek's plan
in its #S-00009-2 permit cannot be found to be arbitrary and capricious.
Respondent had a reasonable basis for its decision, its decision was supported
by the facts of the case and a reasonable and honest person could also be said
to have come to a similar conclusion.[FOOTNOTE 8]
27.
An agency's decision can also be considered to be arbitrary and capricious when
that decision is inconsistent with a previous decision made under similar
circumstances. [Donovan
v. Adams Steel Erection, Inc., 766 F. 2d 804, 807 (3rd Cir. 29850].
Squaw Creek maintains that such was the case when Respondent disapproved Squaw
Creek's restoration plan in its #S-00009-2 permit
after approving a similar plan in Squaw Creeks' #S-00009 permit.
28.
Decisions by administrative agencies must be made on a rational basis and
consistently applied. However, once an appropriate decision is made, that does not
preclude an agency from ever altering that decision. An agency may change its
position when circumstances so dictate and it provides a reasoned justification
for its change in positions.
29.
As was the case with the #S-00009-2 permit, the #S-00009 permit also met
initial disapproval before its revised version was finally approved. While some
of the evidence submitted at the hearing appeared to indicate that the #S-00009
plan faced many of the same problems as did the #S-00009-2 plan, no evidence
was put forth to show why Respondent finally approved the #S-00009 restoration
plan.[FOOTNOTE 9]
30.
Throughout the course of its review Squaw Creek's #S-00009-2 plan, Respondent
voiced its continuing concern that the plan would not meet appropriate
productivity levels as required by 310 IAC 12-5-146 (a). Squaw Creek was
undoubtedly aware of such concerns and cannot now claim that Respondent'
s failure to approve its plan was without a reasoned justification.[FOOTNOTE 10]
31. Based
upon the above findings, Respondent did not act arbitrarily and capriciously by
making inconsistent decisions relating to the approval of Squaw Creek's
#S-00009 and #S-00009-2 restoration plan.
32.
Any decision made by an administrative body which is substantially influenced
by a misapplication of the law, cannot by upheld. [Public Service CO. Of Indiana, Inc. v. Review Board
of the Indiana Employment Security Division,
451 N.E. 2d 371, 375 (Ind. App. 1983)]. Squaw Creek contends
that Respondent was under no obligation to justify any differing decisions with
the SCS.
33.
According to IC 13-4.1-4-3 (d), Respondent is required to consult with the
United States Secretary of Agriculture (of which the SCS is a recognized branch
of that agency) when reviewing prime farmland restoration plans. Respondent is
not requires to adopt the SCS's findings but merely to use such consultations
as part of its internal review process.
34.
As previously noted, both Respondent and the SCS voiced mutual concerns as to the
productive capacity of Squaw Creek's proposed plan.,.
This fact alone does not demonstrate that the Respondent gave the SCS's
comments undue differences. Consequently, the decision made by Respondent to
disapprove Squaw Creek's prime. Farmland restoration plan cannot be said to
have been influenced by a misapplication of the law, namely IC 13-4.1-4-3 (d).
[VOLUME 4, PAGE 43]
FOOTNOTES
1. It was further stipulated that the recommendations of Respondent's staff
concerning the disapproval of Squaw Creek's restoration plan would not be
altered, even with the modifications in the plan.
2. Respondent understood, as indicated by testimony given by way of deposition
and at the hearing, that Squaw Creek intended the #S-00009-2 plan be identical
to the one eventually approved in the #S-00009 permit.
3. 310 IAC 12-5-146 (a) requires in part: Sec 146. Prime Farmland: Soil
Removal. (A) Surface Coal Mining and Reclamation operations on prime farmland
shall be conducted to:
(2)
Separately remove the B horizon, or other suitable soul material that will
create a reconstructed soil of greater productive capability than that which
existed before mining.
(3)
Separately remove the underlying C horizons, other strata, or a combination of
horizons or other strata, to be used instead of the B horizon. When replaced,
these combinations shall be equal to, or more favorable for plant growth than,
the B horizon.
4. Both Wade and Staley cited various studies regarding the relative effect the
percentage of course fragments would have on the productive capacity of a soil.
Wade discussed various studies which indicated course fragments decrease a
soil's productivity and Staley referred to other studies which indicated course
fragments could even be beneficial to a soil. However, neither party put forth
any evidence which would prove that any particular study or approach was
clearly in error or based on totally invalid assumptions.
5. The method used by Squaw Creek to determine the conditioned graded cast
overburden's water holding capacity involved removing the course fragments from
the sample and then crushing it. Respondent did not believe this procedure
provided an accurate representation of the subsoil material and therefore
viewed those results as less than reliable.
6. During the course of the hearing, there was testimony regarding a study
being conducted at Peabody Coal Company's Lynnville Mine, located near to and
containing similar soil types as those found at Squaw Creek's South Field Mine.
In this study, corn was being grown directly in unconditioned graded cast
overburden. Wade visited Peabody's test pilot and testified that he saw some
corn growing in the graded cast overburden but that it was at best sparsely
vegetated. Although Squaw Creek is not maintaining that crops grown in graded
cast overburden will have equal or better yields than those grown in
undisturbed prime farmland soils, the fact that some corn can grow under such
conditions is hardly proof that a subsoil consisting
of conditioned graded cast overburden can create productivity levels required
by 310 IAC 12-5-146.
7. While Respondent's main concerns were never addressed in any one particular
document or meeting, its concern regarding the potential productivity levels of
the subsoil substitute was clearly expressed throughout the course of review as
evidenced by various documents submitted and testimony given at the hearing.
8. When proving an administrative agency has acted in an arbitrary and
capricious manner, the burden of proof that there is no reasonable basis for
the agency's actions is on the party so claiming. [Baughman, 450 N.E. 2d at 97]
It is also a tenet of administrative law that the reviewing body give deference
to the administrative agency's expertise in the area [Metropolitan School
District, 451 N.E. 2d at 353] and in this sense the arbitrary and capricious
standard is narrow and restricted [Farmer's
Union Central Exchange, Inc. v. F.E.R.C., 734 F. 2d 1486, 1500 (D.C. Cir.
1984)].
[VOLUME 4, PAGE 44]
9. Respondent employed a different agronomist at that time and all memoranda
and notes used by him and his staff concerning the review of Squaw Creek's
#S-00009 restoration plan are no longer present in
Respondent's files.
10. There is no principle that requires perfect consistency in decisions made
by administrative agencies during the course of its review of a particular
problem. So long as it takes account of all relevant factors and its goal is
reasonable (such as making sure that Squaw Creek's #S-00009-2 plan met all
statutory requirements) that agency's decision should be sustained based on the
deferential standard required by the technical nature of the subject matter [Illinois Bell Telephone Co. v. F.C.C.,
740 F. 2d 465 (7th Cir, 1984).]