CADDNAR


[CITE: T. Lusher, Jr. v. DNR, 11 CADDNAR 137 (2007)]

 

[VOLUME 11, PAGE 137]

 

Cause #: 04-133W

Caption: T. Lusher, Jr. v. DNR

Administrative Law Judge: Lucas

Attorneys: Paulen; Knotek

Date: April 19, 2007

 

FINAL ORDER

 

(1) The denial of application PL-19,410, for an after-the-fact license to place a steel sheet piling seawall on Simonton Lake in Elkhart County, is affirmed.

 

(2) Notice of Violation No. V-4038-PL is affirmed with the following sanctions ordered:

 

(A) A civil penalty is assessed against Timothy Lusher and in favor of the Department of Natural Resources in the total amount of $75,000.

 

(B) In addition to the civil penalty, the following action is ordered for mitigation of the violation:

(1) Timothy Lusher shall remove the 265-foot steel sheet piling seawall and all fill that was placed in association with the steel sheet piling seawall as depicted in drawing enclosed with the NOV.

(2) To minimize erosion, Timothy Lusher shall stabilize and revegetate all bare and disturbed areas landward of the shoreline with a mixture of grasses (excluding all varieties of tall fescue) and legumes as soon as possible upon completion of removal.

(3) Timothy Lusher shall complete mitigation by September 1, 2007.

(4) Timothy Lusher shall inform the DNR as soon as mitigation is completed.

 

(C) If the mitigation required under Part (2)(B) is performed in a timely fashion, the civil penalty shall be reduced to a total of $1,000.

 

 

FINDINGS OF FACT AND CONCLUSIONS OF LAW

 

A. Jurisdiction and Statement of the Case

 

1.      Timothy Lusher (“T. Lusher”) filed a “Petition for Administrative Review” with the Natural Resources Commission (the “Commission”) of Notice of Violation No. V-4038-PL (the “NOV”) on June 30, 2004.  The NOV alleged a violation with respect to construction on or within the shoreline of Simonton Lake,[1] a public freshwater lake under IC 14-26-2 (sometimes referred to as the “Lakes Preservation Act”) and rules adopted at 312 IAC 11-1 through 312 IAC 11-5 (the “Lakes Preservation Act rules”).

 

[VOLUME 11, PAGE 138]

 

2.      More particularly, the NOV provided in substantive part as follows:

 

TO:      Mr. Timothy Lusher

            51292 County Road 109

            Elkhart, Indiana 46514-6251

 

            Mr. Kevin Mellot

            2612 South Main Street

            Goshen, Indiana 46526-5415

 

The [DNR’s] Division of Water hereby issues this enforcement action pursuant to Indiana Code 14-26-2 as follows:

 

Nature of Violation

 

On or about May 14, 2003, a representative of the [DNR] observed that a steel sheet piling seawall had been constructed across 265 feet of the lake frontage of 51292 County Road 109 without the prior written approval from Department of Natural Resources.  The seawall was constructed lakeward of the legal shoreline and the fill was placed in the lake.  On or about February 3, 2004 the Division of Water denied your after-the-fact permit application for the construction of 265 feet of steel sheet piling seawall.  The seawall and fill are located in the Maple Grove [Subdivision] near Elkhart in Osolo Township, Elkhart County in the NE1/4 of Section 16, Township 38 North, Range 5 East (UTM North 4622303, UTM East 586830).  This activity was completed in violation of Indiana Code 14-26-2.

 

Finding

 

This site is located in an area of special concern.  Pursuant to IAC 312 11-4-2, a new seawall located in an area of special concern must be comprised of either or both bioengineered material or glacial stone.  Pursuant to IC 14-26-2 a permit is required for the placement of a seawall within or along the legally established shoreline of a public freshwater lake.  The existing steel sheet piling seawall and fill were not authorized and have resulted in significant environmental harm to the natural resources and natural scenic beauty of the lake and violates Indiana Code 14-26-2.  The fill also encroaches on the waters of the lake thereby removing this area from the lake and use by the public and violates Indiana Code IC 14-26-2.

 

Action Appropriate to Mitigate the Violation

 

The [DNR] has determined that the following action is appropriate to mitigate the violation:

 

1)      [T. Lusher] and/or his authorized representative shall remove the 265 feet of steel sheet piling seawall and all fill that is lakeward of the lake’s legal shoreline as depicted on the enclosed drawing.

2)      [T. Lusher] and/or his authorized representative shall stabilize and revegetate all bare and disturbed areas landward of the shoreline with a mixture of grasses (excluding all varieties of tall fescue) and legumes as soon as possible upon completion to prevent any erosion.

3)      All work must be completed within 90 days of the receipt of this notice.

4)      Contact our Violations Section at either our toll free number 1-877-928-3755 or (317) 232-1460 after restoration is completed.

 

[VOLUME 11, PAGE 139]

 

For further information regarding the mitigation needed, time frames for accomplishing the mitigation or penalty assessment, please contact Mr. James Hebenstreit P.E., Assistant Director of the Division of Water at (317) 232-4165.

 

Civil Penalty Assessment/Permit Revocation

 

Pursuant to Indiana Code 14-25.5, a person who fails to mitigate a violation within the time set forth above is liable for a civil penalty.  The [DNR] may assess a penalty of not more than ten thousand dollars ($10,000) for a violation.  Each day during which a violation continues may be considered a separate violation for purposes of assessing a civil penalty.

 

Notice of Right to Appeal and Administrative Review

 

This [NOV] will become final thirty (30) days after receipt unless a party makes a timely request for administrative review under I.C. 4-21.5-3-6.

 

In order to qualify for administrative review, a party must file a written request for appeal within thirty (30) days after receipt of this notice at the following address:

 

Director of Division of Hearings

Natural Resources commission

402 West Washington Street, Room W-272

Indianapolis, Indiana 46204

 

3.      The request for administrative review described in Finding 1 was assigned to a Commission administrative law judge and designated as Administrative Cause Number 04-133W (“this proceeding”).  A “Notice of Prehearing Conference”, with a copy of the request for administrative review attached, was forward to the attorneys for T. Lusher and to the attorney for the DNR on July 2, 2004.  Service was successfully made in this proceeding upon both of the parties under IC 4-21.5 (sometimes referred to the “Administrative Orders and Procedures Act” or “AOPA”) and rules adopted by the Commission at 312 IAC 3-1 to assist with its implementation of AOPA.

 

4.      For the same steel sheet piling seawall that was the subject of the NOV, T. Lusher filed an application for an after-the-fact license (the “after-the-fact license”), and the DNR denied the application.  The site of the NOV and of the after-the-fact license is the “subject property”.

 

[VOLUME 11, PAGE 140]

 

5.      The denial of the application was described by the DNR’s Division of Water as follows:

 

APPLICATION #:             PL-19410

LAKE:                               Simonton Lake

APPLICANT:                    Timothy Lusher

                                          51292 County Road 109

                                          Elkhart, IN 46514-6251

DESCRIPTION:                 A steel sheet piling seawall was constructed across 265’ of the applicant’s frontage.  The seawall was placed lakeward of the legal shoreline.  Details of the project are contained in information and plans received at the Division of Water on December 2, 2002, December 12, 2002, January 24, 2003, May 14, 2003, and December 1, 2003.

LOCATION:                      51292 County Road 109 Maple Grove Subdivision near Elkhart, Osolo Township, Elkhart County SW1/4, NW1/4, NE1/4, Section 16, T38N, R5E, Elkhart Quadrangle

                                          UTM Coordinates: Downstream 4622396 North, 586800 East

DENIED BY:                     James J Hebenstreit, P.E., Assistant Director

                                          Division of Water

DENIED ON:                     February 03, 2004

 

6.      The DNR identified its denial reasons as follows:

 

(1)   Pursuant to IC 14-26-2, the DNR is responsible for regulating construction activities within Indiana’s public freshwater lakes; as such, the is charged with preserving and protecting the waters of the lakes for the sue of Indiana’s citizens; the DNR holds and controls all public freshwater lakes in trust for the use of all the citizens of Indiana; the placement of fill in the lake prevents the public from use of this area.

(2)   Pursuant to 312 IAC 11-4-2, if a new seawall is to be placed in an “area of special concern”, the seawall must be comprised of glacial stone or bioengineered materials.

(3)   Direct and cumulative impacts on the natural resources and natural scenic beauty of the lake.

 

7.      On December 20, 2006, a hearing was conducted as scheduled in this proceeding (concurrently with Administrative Cause Number 04-123W) at Columbia City, Indiana.  At the opening of the hearing, the parties agreed that evidence would be received both as to the denial of the after-the-fact license and as to the NOV.

 

8.      The Commission is the “ultimate authority” for the DNR under AOPA with respect to any administrative review for an order arising from the Lakes Preservation Act.  IC 4-21.5-1-15 and IC 14-10-2-3.  Included is administrative review of a notice of violation, issued under IC 14-25.5-4, which alleges a violation of the Lakes Preservation Act.  See, by illustration, IC 14-25.5-4-1(4)(C).

 

[VOLUME 11, PAGE 141]

 

9.      In this proceeding, the Commission has jurisdiction under AOPA for administrative review of the NOV and of the denial of the after-the-fact license.  The Commission also has jurisdiction under AOPA over the persons of T. Lusher and the DNR.

 

B. History of Construction at the Subject Property and Surrounding Area

 

10.  Arthur Lusher, Jr. testified he moved with his parents to the vicinity of the subject property when he was a child.  He recalled that his father, Arthur Lusher, Sr., obtained permits in 1957 and 1965 to deepen the bed of Simonton Lake along portions of the shoreline at the subject property.  A similar permit in 1964 authorized deepening of the lake and the removal of “minor projections of the land into the lake”.  See, also, three documents entitled “Permit or Approval to Alter the Shore Line or Bed of a Public Fresh Water Lake” that were included within Exhibit Joint II. 

                          

11.  Arthur Lusher, Jr. testified the dredging was performed using a “big crane” that was positioned on the land to “swung the bucket out, dug it out,…the dirt was dumped on the property adjacent, behind the lake.”[2]  The fill raised the level of the property landward of the shoreline so “you could build on it.”  Prior to this activity, “it was pretty much all swamp.”  Doing so created a defined shoreline and provided a channel.

 

12.  T. Lusher testified that his recollection was similar to the recollection of his brother, Arthur Lusher, Jr., with respect to the permitting and construction activities by their father, Arthur Lusher, Sr., in the late 1950s and 1960s, although T. Lusher is younger than Arthur Lusher, Jr. and he has less detailed recollection for this period.

 

13.  As a result of the dredging, there is today a near-shore channel or boat lane that is used regularly by the general public for navigation within Simonton Lake.

 

14.  Within 200 feet of the shoreline of most public freshwater lakes, including Simonton Lake, a person must not operate a motorboat in excess of idle speed.  IC 14-15-3-17.  “Idle speed” means the slowest possible speed, not exceeding five miles per hour, which maintains steerage so that the wake or wash created by a boat is minimal.  IC 14-8-2-129.

 

15.  For the near-shore channel that is adjacent to the subject property, boats are subject to an idle speed limit.

 

[VOLUME 11, PAGE 142]

 

16.  Arthur Lusher, Jr. testified that his father operated a chicken and rabbit farm in a barn located near the subject property.  The barn was destroyed by a fire and not rebuilt.  The concrete floor and footers were broken and dragged to the shoreline.  The footers were approximately twelve inches wide by 14 to 16 inches deep, and the floor five to six inches thick.  “We placed them along the shoreline, as best we could, and stabilized them with pipes” on the lakeward side.  In some places, the concrete pieces were single, and in others they were “stacked two high”, and they were configured “parallel to the shoreline”.  He testified the concrete pieces reduced shoreline erosion, “but still the boats [using the channel] washed it out.”  The concrete pieces were placed along the entirety of his parents’ property, which today includes the subject property and the property owned by Arthur Lusher, Jr.

 

17.  Arthur Lusher, Jr. testified that he and his wife determined to contract with Kevin Mellot[3] to construct a steel sheet piling seawall along the shoreline of the subject property.  He subsequently contacted his brother, T. Lusher, and a contract was entered with Mellot that included the subject property as well.  Arthur Lusher, Jr. testified that “After Kevin Mellot started this job he had said that we would need a permit.  At that particular time, he came across as though the DNR was very slow in issuing permits—approximately six months to ten months or so.  He said that we could put it in and we could issue— this was after he had already started this particular seawall, which was mine— that we could file an after-the-fact permit that he was sure would be granted, that he had been granted others in the past.”  Construction took place in 2002.

 

18.  T. Lusher testified the initial contacts with Mellot for a sheet steel piling seawall were made by his brother.  T. Lusher filed the after-the-fact application with the DNR after being advised by Mellot that an application was required and that Mellot “helped a little bit to explain how to do it.”  T. Lusher testified the steel sheet piling seawall varied from seven to eleven inches higher than the former seawall of “chunks of cement” and that it was placed immediately lakeward of the existing seawall. 

 

C. Application of the Statutory and Regulatory Program

 

19.  Neil Ledet is a District Fisheries Biologist for the DNR’s Division of Fish and Wildlife whose geographic responsibilities include public freshwater lakes in Elkhart County.  He has been employed with the DNR since March 1976 and assigned to the District which includes Elkhart County since early 1982.

 

[VOLUME 11, PAGE 143]

 

20.  Ledet is responsible for conducting lake and stream fish surveys for the counties in his District, including Simonton Lake in Elkhart County.  Since 1989, his responsibilities have also included reviewing applications for licenses that are required by the Lakes Preservation Act.

 

21.  The DNR has performed fish surveys on Simonton Lake since the middle-1980s.  These surveys indicate the predominant species are bluegill, red-ear sunfish, largemouth bass, yellow perch and other warm-water species typical of public freshwater lakes in northern Indiana.

 

22.  Ledet is the only person to testify who has expertise in fisheries biology.

 

23.  Ledet testified he has been to the subject property at least three times pertaining to the after-the-fact license application and the NOV. 

 

24.  As defined in 312 IAC 11-2-21, “seawall” means a manmade structure placed along the shoreline or water line of a public freshwater lake for the purpose of shoreline stabilization.

 

25.  Licensing requirements for the placement of a new seawall are provided at 312 IAC 11-4-2.  A written license under the Lakes Preservation Act and the Lakes Preservation Act rules for the construction or placement of a seawall within or along the shoreline or water line of a public freshwater lake.  “(c) If the new seawall is to be placed in an area of special concern, the seawall must be comprised of either or both of the following: (1) Bioengineered materials.  Glacial stone.”

 

26.  Ledet testified that the DNR attempts to evaluate an application for an after-the-fact license in the same manner as an application made before construction activities take place, but “it does become more difficult because the site has been altered prior to our inspection.” 

 

27.  Ledet asked T. Lusher for any documentation that T. Lusher could provide concerning the site conditions that existed along the shoreline of the subject property before the sheet steel seawall was constructed.  T. Lusher provided no such documentation.

 

28.  The DNR is not legally prohibited from issuing an after-the-fact license for activities in or along waterways.  At the same time, an applicant must not gain an advantage in the licensure process because natural resources were destroyed and are less obviously ascertainable as a result of the unlicensed activities.  Shoaff Mullin, and DeVille v. Ft. Wayne Zoological Society and DNR, 8 Caddnar 157 (2000).[4] 

 

[VOLUME 11, PAGE 144]

 

29.  Ledet testified that from the perspective of fisheries biologist, the placement of a steel sheet piling seawall is one of the most damaging alterations that can take place.  “It’s there forever,” and the site “can never really recover unless…the structures are removed.  Usually, it results in construction-wall backfilling.”  The placement of a steel sheet piling seawall “can result in the loss of native vegetation that occurred along the shoreline.  That vegetation, and even some of the woody material that might have been present, provides important habitat for fisheries in those lakes.”  Also, “if there’s a lot of wave action that continually bounces off the wall, it results in scouring of the lake…at the toe of that wall, re-suspending materials and releasing nutrients back into the water [and] contributing to water turbidity.”

 

30.  On cross-examination, Ledet was asked to compare the environmental impacts of a broken concrete seawall and those of a bulkhead steel sheet piling seawall.  He testified, “[T]he bulkhead steel sheet piling seawall is a permanent alteration that requires backfill [and] the loss of…vegetation associated with that.  Concrete placed along the shoreline still doesn’t necessarily remove all of the vegetation as a result of the filling, and it doesn’t provide the same type of wave impact from wave energy back on the wall. They are very different.”  He later testified, “We know that when you build a bulkhead seawall that fish species are greatly reduced compared to…areas that do not have bulkhead seawalls.”

 

31.  With respect to his inspection of the subject property dated May 14, 2003, Ledet reported: “Wetland vegetation is present in various quantities along this entire shoreline and did exist in larger amounts at the project site prior to the illegal work.”  Indiana Department of Natural Resources/Division of Water Application Tracking System, Beth L. Tallon, Environmental Scientist (Aug. 8, 2003) from Exhibit Joint II.

 

32.  Ledet testified he followed the Lakes Preservation Act rules in determining whether a license should be granted under the Lakes Preservation Act.  His examinations of the subject property after the placement of the new seawall revealed a limited surviving presence of wetland species, but he did not designate the site with the most restrictive regulatory classification of “significant wetland”.  Instead, he classified the portion of Simonton Lake which is adjacent to the subject property as “at least an ‘area of special concern’”.  He testified the Lakes Preservation Act rules prohibited the approval of a steel sheet piling seawall in an “area of special concern”.

 

33.  As defined in 312 IAC 11-2-2, “area of special concern” means an area that contains at least one (1) of the following characteristics:

(1) An altered shoreline where bulkhead seawalls are at least two hundred fifty (250) feet apart.

(2) Bogs, fens, muck flats, sand flats, or marl beaches identified by the division of nature preserves in the Natural Community Classification System.

(3) More than six hundred twenty-five (625) square feet of contiguous emergent vegetation or rooted vegetation with floating leaves.

 

[VOLUME 11, PAGE 145]

 

34.  Ledet testified he determined the portion of Simonton Lake adjacent to the subject property is an “area of special concern” because it qualified, under 312 IAC 11-2-2(1), as an “altered shoreline where bulkhead seawalls” are at least 250 feet apart.

 

35.  Ledet testified that, pursuant to 312 IAC 11-2-2(1), a site can qualify as an “area of special concern” even where manmade alterations have taken place.  By illustration, these could include dredging, a neighboring glacial stone seawall or a beach.  This interpretation is consistent with the language of subdivision (1) that identifies an “altered shoreline” as being qualified.

 

36.  The sheet steel piling seawall constructed along the subject property is approximately 265 feet long.

 

37.  On cross-examination, Ledet testified the nearest bulkhead seawall was located in, and near the mouth of, a manmade channel that is south of the subject property.

 

38.  T. Lusher testified the nearest bulkhead seawall was approximately 215 feet south of the subject property, and, similarly to the one that T. Lusher caused to be placed, was constructed of sheet steel piling.

 

39.  The bulkhead seawall south of the subject property described in Finding 37 and in Finding 38 is the same steel sheet piling seawall.  The parties agreed that this seawall is a bulkhead seawall.

 

40.  Arthur Lusher testified that the area south of his seawall and north of the subject seawall was “open” and contained no seawall. 

 

41.  On cross-examination, Ledet testified there was a “wood timber wall” immediately north of the property owned by Arthur Lusher, Jr.  Arthur Lusher, Jr. also testified to the existence of this neighbor’s wooden seawall, although he indicated there was a drain between the two seawalls. 

 

42.  T. Lusher and the DNR seemingly disagree as to whether the “wood timber wall” immediately north of Arthur Lusher, Jr.’s property constitutes a “bulkhead seawall” under the rules in effect during construction activities at issue in this proceeding.

 

43.  Simultaneously with the placement of the sheet steel piling seawall at the subject property, Arthur Lusher, Jr. caused an 85-foot long sheet steel piling seawall to be placed at property owned by Arthur Lusher, Jr.  The Arthur Lusher, Jr. property is located generally north of the subject property.  Another property also intervenes between the Arthur Lusher, Jr. property and the subject property.

 

[VOLUME 11, PAGE 146]

 

44.  As defined in 312 IAC 11-2-5 and applicable to this proceeding, “bulkhead seawall” means an impervious, vertical, or near vertical shoreline protection structure.

 

45.  Effective June 1, 2005, 312 IAC 11-2-5 was amended to its current language.  Pursuant to 312 IAC 11-2-5(a), “bulkhead seawall” now means a vertical, or near vertical, solid concrete, steel sheet piling, or vinyl piling structure, which has the purpose of shoreline protection.  Pursuant to 312 IAC 11-2-5(b), a timber seawall may now also qualify as a “bulkhead seawall”, if constructed before January 1, 1991, and if the property owner establishes a series of criteria in a written assessment by a registered professional engineer, licensed professional geologist or soil scientist with expertise in shoreline protection and wave dynamics.

 

46.  The 2005 amendments eliminated the rule requirement that a structure be “impervious” in order to qualify as a bulkhead seawall.  Instead, amended 312 IAC 11-2-5 requires that a structure be constructed of solid concrete, steel sheet piling, vinyl piling, or, in limited circumstances, timber.

 

47.  On cross-examination, Ledet testified that under the pre-2005 definition, “impervious” meant “solid, where water doesn’t flow freely from one side to the other.”  Within this definition, he considered a seawall constructed of poured concrete, steel sheet piling, vinyl piling, or, in limited circumstances, timber, to be a bulkhead seawall.  He did not consider a seawall constructed of engineered stone, stacked rubber tires, wood cribbed and rocks, hog wire fencing and sandbags or vertical concrete pipe to qualify as a “bulkhead seawall”.

 

48.  The evidence is inconclusive as to whether the wood timber seawall, located immediately north of the Arthur Lusher, Jr. property, was impervious so as to satisfy the pre-2005 definition (or, for that matter, whether it would satisfy the criteria for a timber seawall for the post-2005 definition).  For the purposes of this proceeding, the assumption is made most favorable to T. Lusher that the wood timber seawall qualifies as a bulkhead seawall.  Even so, there is a distance well in excess of 250 feet between the wood timber seawall and the sheet steel seawall that was located 215 feet south of the subject property.

 

49.  Ledet testified that, prior to review of the after-the-fact license application, he had performed fish surveys within Simonton Lake and adjacent to the subject property.  He recalled observing broken concrete pieces along the shoreline, but these were not what he considered to be a “bulkhead seawall”.  He testified a seawall constructed of broken or stacked concrete could provide shoreline protection, but this type of seawall was not approved for rules which became effective in March 1999.[5]  Ledet did not know when the concrete pieces were placed along the shoreline of the subject property.

 

[VOLUME 11, PAGE 147]

 

50.  Neither the former seawall on the subject property nor the former seawall on the Arthur Lusher, Jr. property qualifies as a bulkhead seawall.  They were not impervious but rather in the nature of riprap and had greater structural commonality to a glacial stone seawall than to a sheet steel seawall or a concrete seawall.  The former seawalls were more sieve than fortress, and the erosion problems experienced by T. Lusher illustrated they were an ineffective sieve.  Wave action in rebound from the former seawall would be at least somewhat dispersed by the irregular surface of the wall.

 

51.  By contrast, the new sheet steel seawall is a substantial barrier.  The new seawall is practically if not absolutely impervious.  The new seawall is substantially higher.  Wave action in rebound from the new seawall is likely to be less dispersed than from the irregular concrete pieces that constituted the former seawall.  From the perspective of fisheries biology, the placement of a steel sheet piling seawall resulted in significant environmental harm.  The structure is permanent, and the area cannot recover unless the sheet steel seawall is removed.  Placement of a sheet steel seawall, rather than the use of bioengineered materials or glacial stone, contravened and thwarted the purpose of the Commission’s regulatory program.  The new steel sheet piling seawall and fill have resulted in significant environmental harm to the natural resources and natural scenic beauty of Simonton Lake in violation of the Lakes Preservation Act. 

 

52.  Ledet testified that filling the lake also reduces the area that would be available for public use.  The placement of fill could violate the public trust that is protected under the Lakes Preservation Act, although he conceded the T. Lusher “fill area was relatively small compared to some other wall that may have been built ten or 15 feet out into the lake.”  On cross-examination, he reflected that the DNR determined had T. Lusher’s steel sheet piling seawall was approximately six inches lakeward of the previous crushed concrete seawall.

 

53.  The evidence supports a finding that the construction of the sheet steel seawall encroaches on the public waters of Simonton Lake and is a violation of the public trust doctrine.  The area of encroachment is nominal and would not, in itself, support the NOV or preclude approval of the after-the-fact license.

 

54.  A. Lusher has not shown by a preponderance of the evidence that the after-the-fact license was wrongfully denied by the DNR.

 

[VOLUME 11, PAGE 148]

 

55.  The DNR has shown by a preponderance of the evidence that the NOV was properly issued.

 

 

D. Sanctions for NOV

 

56.   As indicated in the NOV, a civil penalty should be assessed against T. Lusher under IC 14-25.5.

 

57.  “In addition to other penalties prescribed by” the Lakes Preservation Act, the director [of the DNR] may impose a civil penalty under IC 14-25.5-4.”  IC 14-26-2-22.

 

58.  As provided in IC 14-25.5-4-4, a “civil penalty” assessed under IC 25.5-4-3 “is subject to IC 4-21.5-3-6 and becomes effective without a proceeding under IC 4-21.5-3 unless a person requests administrative review within thirty (30) days after receipt of the notice of assessment.”

 

59.  As provided in IC 14-25.5-4-3 and applicable to this proceeding, the DNR “may assess a civil penalty of not more than ten thousand dollars ($10,000) for a violation” of the Lakes Preservation Act.  Each day during which a violation continues may be considered a separate violation for purposes of assessing a civil penalty.

 

60.  In considering what civil penalty to assess, the Commission must properly consider the totality of the circumstances.  The seriousness of the violation should be considered, as well as any aggravating or mitigating factors. DNR and I & M v. Pheasant Ridge Development. Co., Inc., 10 Caddnar 187 (2006).

 

61.  The maximum civil penalty must be reserved for the most serious violations.

 

62.  In considering the seriousness of a violation, the Commission shall determine whether there is posed an imminent danger to persons, property, or the environment. 

 

63.  The violations by T. Lusher have not been shown to pose danger to persons or property, but they have caused significant harm to the environment. 

 

64.  A DNR fisheries biologist testified that the construction of the steel sheet piling seawall is one of the most damaging alterations that can take place within a public freshwater lake.  “It’s there forever,” and the site “can never really recover unless” the seawall and backfill are removed.  The placement of a steel sheet piling seawall “can result in the loss of native vegetation that occurred along the shoreline.  That vegetation, and even some of the woody material that might have been present, provides important habitat for fisheries in those lakes.”  Also, “if there’s a lot of wave action that continually bounces off the wall, it results in scouring of the lake…at the toe of that wall, re-suspending materials and releasing nutrients back into the water [and] contributing to water turbidity.”

 

[VOLUME 11, PAGE 149]

 

65.  An unlicensed 265-foot steel sheet seawall has been in existence at the subject property since 2002.

 

66.  For the violation resulting from improper and unlicensed construction of the steel sheet piling seawall, a significant civil penalty must properly be assessed against T. Lusher.

 

67.  As aggravating factors, the Commission shall properly consider whether the violation was deliberate, continuing in nature, or of extended duration.

 

68.  The violation was deliberate, but there is also a reasonable inference T. Lusher was encouraged and even pressured by his contractor to commit the violation.  The violation was of a continuing nature.  The duration was essentially concurrent with the administrative adjudication, so duration is not considered an aggravating factor.

 

69.  Mitigating factors include that a person sought in good faith to abate the violation.  Because the violation at issue here results in an adverse condition but one that is relatively stable, mitigation may properly be viewed as a prospective opportunity.

 

70.  Of a maximum $10,000 daily civil penalty for violation, the circumstances support a civil penalty of $750 daily in the total amount of $75,000.

 

71.  In addition to the civil penalty, the following action is appropriate for mitigation of the violation:

(1) T. Lusher should remove the 265-foot steel sheet piling seawall and all fill that was placed in association with the steel sheet piling seawall as depicted in drawing enclosed with the NOV.

(2) To minimize erosion, T. Lusher should stabilize and revegetate all bare and disturbed areas landward of the shoreline with a mixture of grasses (excluding all varieties of tall fescue) and legumes as soon as possible upon completion of removal.

(3) Mitigation should be completed by September 1, 2007.

(4) T. Lusher should inform the DNR as soon as mitigation is completed.

 

72.  If the mitigation required under Finding 71 is performed in a timely fashion, the civil penalty should be reduced to a total of $1,000.



[1] Simonton Lake is shaped somewhat like a barbell.  The site of this proceeding is on the portion of Simonton Lake that is locally known as the “East Basin of Simonton Lake” or “Little Simonton Lake”.

 

[2] The court reporter has not been requested to prepare a transcript of testimony at hearing.  If a witness is shown as being quoted in these findings, the statement is as nearly verbatim as could be determined by the administrative law judge.  If a transcript is subsequently prepared that indicates different wording, the transcript shall be considered the official record and a quotation as paraphrasing of witness testimony.

 

[3] Although named in the NOV, Kevin Mellot did not seek administrative review and did not participate in this proceeding.  This Final Order shall not be construed to relieve any claim for relief either of the parties may have against Mellot.

[4] As provided in IC 4-21.5-3-32, an agency is required to index final orders and may rely upon indexed orders as precedent. Caddnar was adopted by the Commission in November 1988 as the index of agency decisions anticipated in AOPA.  Barbee Villa Condominium Owners Assoc. v. Shrock, 10 Caddnar 23 (2005).  Amendments made to AOPA in 1997 also direct the Commission to address agency precedents cited by the parties where a proceeding is governed by IC 25.  IC 4-21.5-3-27(c).  Application of these statutory directives supports consistency and predictability for the Commission’s administrative decisions under the Lakes Preservation Act.

[5] The propriety of the former seawall is not at issue in this proceeding but appears to have qualified under 312 IAC 11 as a lawful nonconforming use.