IC 13-20-10.5-1
Department approval
Sec. 1. (a) A person may not after June 30, 2011, start:
(1) construction of:
(A) a biomass anaerobic digestion facility; or
(B) a biomass gasification facility; or
(2) expansion of:
(A) a biomass anaerobic digestion facility; or
(B) a biomass gasification facility;
without obtaining prior approval of the department.
(b) A person who proposes to construct or expand a biomass
anaerobic digestion facility or a biomass gasification facility on the
premises of a confined feeding operation must obtain the prior
approval required under subsection (a) through the approval process
for confined feeding operations under IC 13-18-10 and rules
implementing that chapter.
As added by P.L.189-2011, SEC.13.
IC 13-20-10.5-2
Regulation as a solid waste processing facility
Sec. 2. Except as provided in section 3 of this chapter, a biomass
anaerobic digestion facility or a biomass gasification facility for
which the only input is biomass is not subject to regulation as a solid
waste processing facility.
As added by P.L.189-2011, SEC.13.
IC 13-20-10.5-3
Regulation as a solid waste processing facility; department
determination
Sec. 3. (a) The department may determine that a biomass
anaerobic digestion facility or a biomass gasification facility for
which the input is a combination of biomass and solid waste is
subject to regulation as a solid waste processing facility.
(b) Anaerobic digestion and gasification facilities required to
maintain a permit under IC 13-17 are not required to seek approval
under this chapter.
As added by P.L.189-2011, SEC.13.
IC 13-20-10.5-4
Rules
Sec. 4. The board may adopt rules under IC 4-22-2 and IC 13-14-9
to implement this chapter.
As added by P.L.189-2011, SEC.13.