ISCBA > Convention Center Expansion > Timeline Convention Center Expansion Project Timeline

  • All Anticipated Bid Packages
    • Late 2007-Early 2008
  • Logistics, Dome Demolition, Utility Relocation
    • Bids Late 2007
  • Excavation, Concrete, Structural Steel, Vertical Conveyances
    • Bids Early 2008
  • Enclosure and Finish Scopes
    • Bids Spring 2008
  • Anticipated Dome Demolition
    • Summer 2008
  • New Construction Begins
    • Fall 2008
  • Convention Center Expansion Completion
    • Late 2010