This map shows the footprint of the selected alternative for the U.S. 31 Kokomo Corridor Project as detailed in the Record of Decision and Final Environmental Impact Statement. Below it is a map detailing the differences in Alternative J Modified - the preferred alternative - as published in the Supplemental Draft Environmental Impact Statement (October 2006) and the Draft Environmental Impact Statement (March 2006). Please view the ROD, FEIS, SDEIS and DEIS for more detailed alternative information. Detailed contract map with current letting information:
This map shows the footprint for Alternative J Modified evaluated in the October 2006 U.S. 31 Kokomo Corridor Project Supplemental Draft Environmental Impact Statement. The map key shows the primary changes from Alternative J as detailed in the April 2005 Draft Environmental Impact Statement. To view detailed maps, roll over the sections of Alternative J Modified below and click on a highlighted section. A detailed description of Alternative J Modified is below the map. Please view the SDEIS and DEIS for more detailed alternative information. About Alternative J Modified
Alternative J Modified calls for the following cross-streets along the corridor to be closed with no access to the new corridor:
Alternative J Modified calls for overpasses at the following cross streets:
Alternative J Modified calls for underpasses at the following cross streets:
Please view DEIS Appendix A: Environmental Features Maps for more detailed DEIS alternative information. INFORMATION FROM THE NOVEMBER 15th, 2007 PUBLIC INFORMATION MEETING: Aerial Maps (53.3 megabytes) Maps displayed at the meeting:
|
|
|
|