The US 24 Fort to Port Project continues to progress on schedule with an anticipated completion date of 2012.
Phase 4 is complete and open at this time. Phase 3 Construction is complete and ends just east of Webster Road. Phases 3 and 2 will not open to the public until Phase 1 is complete and open to traffic.
The interchange at Webster Road is part of Phase 2 construction, which was awarded on 2/25/2010 and has been under construction since this time.
Several Road closures are planned for Phase 1 which is scheduled to be completed by late 2012. Road closure information may be subject to change in accordance to project needs.
- Bruick Road Closure Time: 30 Days
- Doyle Road Closure Time: 45 Days
These are contract durations and notification will be given to announce road closures in advance to actual closure dates. |