Latest News &
Construction Updates
Contract R-27552, the last of four contracts
on the I-465 NW Project, will begin construction this spring. The
Project will complete the reconstruction of the interchange ramps
at I-465 and West 71st St. and I-465 and West 86th St. The following
is a brief summary of the work to be done.
Construction Activities
• All interchange ramps will be
replaced on new alignments. Additional ramp lanes will be constructed
in most cases.
• 71st St. pavement will be replaced and new signals installed
between Marsh Rd. and Woodland Ave.
• 86th St. pavement will be replaced between Mariesi Dr.,
just west of I-465 and Northwest Blvd., east of I-465.
• Loop ramps will be constructed in the NW quadrants of both
interchanges to accommodate the free flow of traffic from WB 71st
or 86th to I-465 SB.
• A new direct connect ramp will be constructed from I-465
NB to 73rd St. The new ramp will leave I-465 at the same location
as the I-465 NB ramp to 71st St., crossing over 71st St before ending
at 73rd and Woodland Ave.
• In conjunction with the Project, the City of Indianapolis
DPW will convert 73rd St. to one-way east and 74th St. to one-way
west.
• A multi-use trail will be constructed thru both interchanges
along the south side of each road. The trail is a coordinated effort
with the City of Indianapolis and will connect to future trails
on either side of I-465.
Maintaining Traffic
and Project Schedule
• Traffic on both 71st and 86th
St. will be maintained during construction by means of crossovers.
Traffic will be maintained on the existing WB lanes during construction
of new EB lanes. Traffic will then be maintained on the new EB lanes
while the WB lanes are replaced.
• All ramp traffic will be maintained during construction
with the exception that a ramp may be closed during the night or
over a weekend. Only 1 ramp in both interchanges may be closed at
a time.
• All new ramps and lanes, with the exception of the 73rd
direct connect ramp, will be open to traffic by November 17, 2006
unless unforeseen circumstances delay completion.
• The 73rd St. ramp will be open to traffic by June 1, 2007.