STATE OF INDIANA

COUNTY OF MARION

)
)
)


SS:

BEFORE THE INDIANA DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT

 

COMMISSIONER OF THE DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT,

Complainant,

v.

KNAUF INSULATION GmbH,

Respondent.

)
)
)
)
)
)
)
)
)
)






Case No. 2012-20736-A and
               2013-21810-A



 

 

 

AGREED ORDER

 

Complainant and Respondent desire to settle and compromise this action without hearing or adjudication of any issue of fact or law, and consent to the entry of the following Findings of Fact and Order.  Pursuant to IC 13-30-3-3, entry into the terms of this Agreed Order does not constitute an admission of any violation contained herein.  Respondent's entry into this Agreed Order shall not constitute a waiver of any defense, legal or equitable, which Respondent may have in any future administrative or judicial proceeding, except a proceeding to enforce this order.

 

I.  FINDINGS OF FACT

 

1.               Complainant is the Commissioner (“Complainant”) of the Indiana Department of Environmental Management (“IDEM”), a department of the State of Indiana created by Indiana Code (“IC”) 13-13-1-1.

 

2.               Respondent is Knauf Insulation GmbH (“Respondent”), which is a fiberglass manufacturing facility with Plant ID No. 145-00001, located at 400 E. Walker Street, in Shelbyville, Shelby County, Indiana (“Site”).

 

3.               IDEM has jurisdiction over the parties and the subject matter of this action.

 

4.               Pursuant to IC 13-30-3-3, IDEM issued a Notice of Violation (“NOV”) on May 16, 2013 and January 22, 2014 via Certified Mail to the following individuals.

 

Mark Andrews, CEO

Candace Bankovich, Registered Agent

One Knauf Drive

One Knauf Drive

Shelbyville, IN 46176

Shelbyville, IN 46176

 

5.               During an investigation conducted by a representative of IDEM, the following violations were found:

 

a.               Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.1.7(b), Permittee shall perform compliance testing using a non-phenol/formaldehyde binder at MFG 602 forming process to verify compliance with the PM emission limit in permit condition D.1.5.  Testing shall be completed no later than 60 days after issuance of permit No. 145-28817-00001.

 

Compliance testing at MFG 602 forming process to verify compliance with PM emission limit in permit condition D.1.5 took place on May 1, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.1.7(b).

 

b.               Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.2.3(a), Permittee shall perform testing on the fiberglass pipe insulation production Line 3010 stacks 17-1, 17-2, 17-3, and 15-1 or 15-2 in order to demonstrate compliance with the PM emission limit in permit condition D.2.2(a).  Testing shall be performed no later than 60 days after achieving the maximum capacity, but no later than 180 days after start-up.

 

Compliance testing for the fiberglass pipe insulation production Line 3010 stacks 17-1, 17-2, and 17-3 to verify compliance with the PM emission limit in permit condition D.2.2(a) took place on June 16, 2011.  However, this testing did not include all required emission stacks (either stacks 15-1 or 15-2).  Testing on stack 15-2 took place on May 3, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.2.3(a).

 

c.               Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.2.3(b), Permittee shall perform testing on the fiberglass pipe insulation production Line 3010 stacks 17-1, 17-2, 17-3, and 15-1 or 15-2 in order to demonstrate compliance with the PM10 emission limit in permit condition D.2.2(b).  Testing shall be performed no later than 180 days after publication of the new or revised condensable PM test method referenced in the US EPA’s Final Rule for Implementation of the New Source Review (NSR) Program for Particulate Matter Less Than 2.5 Micrometers signed on May 8, 2008.

 

Compliance testing for the fiberglass pipe insulation production Line 3010 stacks 17-1, 17-2, and 17-3 to verify compliance with the PM10 emission limit in permit condition D.2.2(b) took place on June 16, 2011.  However, this testing did not include all required emission stacks (either stacks 15-1 or 15-2).  Testing on stack 15-2 took place on May 3, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.2.3(b).

 

d.               Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.5.11(a)(2), Permittee shall complete stack testing of the Forming process on line 611 before control to determine compliance with VOC BACT emission limits as required in permit condition D.5.5(a), while operating line 611 with the phenol/formaldehyde binder.  Testing shall be performed no later than 60 days after achieving maximum capacity of the proposed modification approved under permit 145-20887-00001, but no later than 180 days after initial startup of the proposed expansion approved under permit 145-20887-00001.

 

Compliance testing for the Forming process on line 611 to verify compliance with VOC BACT emission limit in permit condition D.5.5(a) took place on May 3, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.5.11(a)(2).

 

e.               Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.5.11(a)(2), Permittee shall complete stack testing of the Forming process on line 612 before control to determine compliance with VOC BACT emission limits as required in permit condition D.5.5(b)(1), while operating line 612 with the phenol/formaldehyde binder. Testing shall be performed no later than 60 days after achieving maximum capacity of the proposed modification approved under permit 145-20887-00001, but no later than 180 days after initial startup of the proposed expansion approved under permit 145-20887-00001.

 

Compliance testing for the Forming process on line 612 to verify compliance with VOC BACT emission limit in permit condition D.5.5(b)(1) took place on May 2, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.5.11(a)(2).

 

f.                Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.5.11(a)(2), Permittee shall complete stack testing of the combined 613 Forming and 613 Curing/Cooling process to determine compliance with VOC BACT emission limits as required in permit condition D.5.5(c)(i)(3), while operating line 613 with the phenol/formaldehyde binder. Testing shall be performed no later than 60 days after achieving maximum capacity of the proposed modification approved under permit 145-20887-00001, but no later than 180 days after initial startup of the proposed expansion approved under permit 145-20887-00001.

 

Compliance testing for the combined 613 Forming and 613 Curing/Cooling process to verify compliance with VOC BACT emission limit in permit condition D.5.5(c)(i)(3) took place on May 4, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.5.11(a)(2).

 

g.               Pursuant to 326 IAC 2-7-6 and permit No. 145-28835-00001 condition D.5.11(a)(2), Permittee shall complete stack testing of the combined 614 Forming and 614 Curing/Cooling process to determine compliance with VOC BACT emission limits as required in permit condition D.5.5(d)(i)(3), while operating line 614 with the phenol/formaldehyde binder. Testing shall be performed no later than 60 days after achieving maximum capacity of the proposed modification approved under permit 145-20887-00001, but no later than 180 days after initial startup of the proposed expansion approved under permit 145-20887-00001.

 

Compliance testing for the combined 614 Forming and 614 Curing/Cooling process to verify compliance with VOC BACT emission limit in permit condition D.5.5(d)(i)(3) took place on May 3, 2012.  Respondent did not complete this testing within the required timing, in violation of permit No. 145-28835-00001 condition D.5.11(a)(2).

 

h.               Pursuant to 326 IAC 2-2-3 and permit No. 145-28835-00001 condition D.1.3(b)(2)(A), the PM/PM10 emissions from operation of the 602 LF MFG shall not exceed 2.8 pounds per ton of glass pulled.

 

Stack testing was conducted on May 2, 2012 in which PM emissions from the 602 LF MFG exceeded the 2.8 lbs/ton limit, in violation of 326 IAC 2-2-3 and permit No. 145-28835-00001 condition D.1.3(b)(2)(A).  The stack was retested in compliance on June 13, 2012.

 

i.                 Pursuant to 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(c)(i)(2) and D.5.5(d)(i)(2), the overall control efficiency of each RTO shall be at least 95% when controlling the VOC emissions from the 613 and 614 Curing/Cooling operation.

 

Stack testing was conducted on October 7, 2009 in which the control efficiency of the RTO was less than the minimum of 95%, in violation of 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(c)(i)(2) and D.5.5(d)(i)(2).

 

j.                 Pursuant to permit No. 145-28835-00001 condition C.16, a retest to demonstrate compliance shall be performed no later than 180 days after the date of the test.  A retest to demonstrate compliance of the RTO controlling VOC emissions from the 613/614 Curing/Cooling process was required by April 7, 2010 (180 days after the non compliance stack test conducted on October 7, 2009).

 

Respondent did not complete a retest of the RTO controlling VOC emissions within the required timing, in violation of permit No. 145-28835-00001 condition C.16.

 

k.               Pursuant to 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(c)(i)(2) and D.5.5(d)(i)(2), the overall control efficiency of each RTO shall be at least 95% when controlling the VOC emissions from the 613 and 614 Curing/Cooling operation.

 

Stack testing was conducted on May 4, 2012 in which the control efficiency of the RTO was less than the minimum of 95%, in violation of 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(c)(i)(2) and D.5.5(d)(i)(2).

 

l.                 Pursuant to permit No. 145-28835-00001 condition C.16, a retest to demonstrate compliance shall be performed no later than 180 days after the date of the test.  A retest to demonstrate compliance of the RTO controlling VOC emissions from the 613/614 Curing/Cooling process was required by November 4, 2012 (180 days after the non compliance stack test conducted on May 4, 2012).

 

Respondent did not complete a retest of the RTO controlling VOC emissions within the required timing, in violation of permit No. 145-28835-00001 condition C.16.

 

m.             Pursuant to 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(b)(1), VOC emissions before control from 612 Forming shall not exceed 6.1 pounds per hour of VOC emissions.

 

Stack testing was conducted on May 2, 2012 in which the VOC emissions before control from 612 Forming exceeded the VOC emission limit of 6.1 pounds per hour, in violation of 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(b)(1).

 

n.               Pursuant to permit No. 145-28835-00001 condition C.16, a retest to demonstrate compliance shall be performed no later than 180 days after the date of the test.  A retest to demonstrate compliance with VOC BACT emission limit before control from 612 Forming was required by November 2, 2012 (180 days after the non compliance stack test conducted on May 2, 2012).

 

Respondent did not complete a retest of VOC emissions from Forming Line 612 before control within the required timing, in violation of permit No. 145-28835-00001 condition C.16.

 

o.               Pursuant to 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(c)(i)(3), the combined VOC emissions from 613 Forming and 613 Curing/Cooling shall not exceed 9.0 pounds per hour of VOC emissions.

 

Stack testing was conducted on May 4, 2012 in which the VOC emissions from 613 Forming and 613 Curing/Cooling exceeded the VOC emission limit of 9.0 pounds per hour, in violation of 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.5(c)(i)(3).

 

p.               Pursuant to permit No. 145-28835-00001 condition C.16, a retest to demonstrate compliance shall be performed no later than 180 days after the date of the test.  A retest to demonstrate compliance with VOC BACT emission limit from 613 Forming and 613 Curing/Cooling process was required by November 4, 2012 (180 days after the non compliance stack test conducted on May 4, 2012).

 

Respondent did not complete a retest of VOC emissions from Line 613 Forming and Curing/Cooling process within the required timing, in violation of permit No. 145-28835-00001 condition C.16.

 

q.               Pursuant to 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.10, the RTOs for VOC, hazardous air pollutants and condensable particulates control shall be in operation and control emissions from the 613 and 614 Curing / Cooling operations at all times when these section are in operation and using a phenol/formaldehyde binder.

 

On October 3, 2011 and October 5, 2011 the 614 and 613 Curing/Cooling operations respectively were running with phenol/formaldehyde binder products and in each case the RTO was operating in bypass mode and not controlling emissions as required, in violation of 326 IAC 8-1-6 and permit No. 145-28835-00001 condition D.5.10.

 

r.                Pursuant to 326 IAC 2-7-5 and permit No. 145-28835-00001 condition D.2.8(b)(1), Permittee shall maintain daily records of picoampere (pA) display readings.

 

Respondent reported that the plant 3 daily parametric monitoring logs for picoampere (pA) were missing for the time period of March 21, 2011 to August 28, 2011, in violation of 326 IAC 2-7-5 and permit No. 145-28835-00001 condition D.2.8(b)(1).

 

s.               Pursuant to Permit conditions D.1.9(a), D.4.9(a) and D.5.14(a), Visible emission notations of stack exhaust shall be performed once per day during normal daylight operations when exhausting to the atmosphere. A trained employee shall record whether emissions are normal or abnormal.

 

Respondent failed to perform visible emissions notations of stack exhaust from furnace 602B, MFG 602, 602LF MFG, FURN 611 (Stack 6-21), Stack 6-22 exhaust and Stack 6-29 exhaust for 15 days during the compliance period 3Q 2011-2Q 2013 in violation of Permit conditions D.1.9(a), D.4.9(a) and D.5.14(a).

 

t.                Pursuant to Permit condition D.5.9, the wet electrostatic precipitator (ESP) for particulate control shall be in operation and control emissions from the 611 FORMING, 612 FORMING, 613 FORMING, and 614 FORMING at all times when any of these forming sections are in operation. Pursuant to Permit condition D.5.15(b), the appropriate primary and secondary current (amperes) and voltage in each electrical field shall be maintained within the normal range as established in most recent compliant stack test. Pursuant to Permit condition D.5.15(c), when any reading is outside the normal range, the Permitee shall take reasonable response steps. Failure to take reasonable response steps shall be considered a deviation from the permit.

 

Respondent submitted 4th quarter 2012 and 1st quarter 2013 quarterly reports identifying periods where 4 of the 8 wet electrostatic precipitator modules of the  611 forming line were in alarm or off during normal operations in violation of Permit condition D.5.9. The appropriate primary and secondary current (amperes) and voltage in each electrical field of the 611forming line’s wet electrostatic precipitator were not maintained within the normal range as established in the most recent compliant stack test in violation of Permit condition D.5.15(b) and without response steps in violation of Permit condition D.5.15(c).

 

u.               Pursuant to Permit condition D.5.3(c), the loss on ignition (LOI) of the binders used by the 611 FORMING, 612 FORMING, 613 FORMING, 614 FORMING, 613 CURING/COOLING, and 614 CURING/COOLING combined shall not exceed 18%.

 

Respondent exceeded the 18% limit loss on ignition (LOI) of the binders used by the 611 FORMING, 612 FORMING, 613 FORMING, 614 FORMING, 613 CURING/COOLING, and 614 CURING/COOLING combined in violation of Permit condition D.5.3(c).

 

v.               Pursuant to Permit condition D.5.15(b), the appropriate primary and secondary current (amperes) and voltage in each electrical field shall be maintained within the normal range as established in most recent compliant stack test. Pursuant to Permit condition D.5.15(c), when any reading is outside the normal range, the Permitee shall take reasonable response steps. Failure to take reasonable response steps shall be considered a deviation from the permit.

 

The appropriate primary and secondary current (amperes) and voltage in each electrical field of the 611, 612, 613 and 614 forming lines wet electrostatic precipitator were not maintained within the normal range as established in the most recent compliant stack test on various dates and without response steps during the compliance period for the 3rd quarter 2011- the 2nd quarter 2013 in violation of Permit condition D.5.15(b)(c).

 

w.              Pursuant to 326 IAC 2-7-10.5, an owner or operator of a Part 70 source proposing to construct new emission units shall submit a request for a modification approval in accordance with 326 IAC 2-7-10.5. Pursuant to 326 IAC 2-7-3, no Part 70 source may operate after the time that it is required to submit a timely and complete application.

 

Respondent constructed and operated two generators and fuel dispensing facilities without first applying for and obtaining a permit in violation of 326 IAC 2-7-10.5 and 326 IAC 2-7-3.

 

6.               In recognition of the settlement reached, Respondent waives any right to administrative and judicial review of this Agreed Order.

 

II.  ORDER

 

1.               This Agreed Order shall be effective (“Effective Date”) when it is approved by Complainant or Complainant’s delegate, and has been received by Respondent.  This Agreed Order shall have no force or effect until the Effective Date.

 

2.               Respondent shall comply with rules and/or permit conditions listed in the findings above at issue.

 

3.               All submittals required by this Agreed Order, unless Respondent is notified otherwise in writing by IDEM, shall be sent to:

 

Rebecca Hayes, Compliance and Enforcement Manager

Compliance and Enforcement Branch – Mail Code 61-53

Indiana Department of Environmental Management

100 North Senate Avenue

Indianapolis, IN 46204-2251

 

4.               Respondent is assessed and agrees to pay a civil penalty of Fifty Eight Thousand One Hundred Dollars ($58,100).  Said penalty amount shall be due and payable to the Environmental Management Special Fund within thirty (30) days of the Effective Date; the 30th day being the “Due Date”.

 

5.               Civil penalties are payable by check to the “Environmental Management Special Fund.”  Checks shall include the Case Number of this action and shall be mailed to:

 

Indiana Department of Environmental Management

Cashier – Mail Code 50-10C

100 North Senate Avenue

Indianapolis, IN 46204-2251

 

6.               This Agreed Order shall apply to and be binding upon Respondent and its successors and assigns.  Respondent’s signatories to this Agreed Order certify that they are fully authorized to execute this Agreed Order and legally bind the party they represent.  No change in ownership, corporate, or partnership status of Respondent shall in any way alter their status or responsibilities under this Agreed Order.

 

7.               In the event that the monies due to IDEM pursuant to this Agreed Order are not paid on or before their Due Date, Respondent shall pay interest on the unpaid balance at the rate established by IC 24-4.6-1.  The interest shall be computed as having accrued from the Due Date until the date that Respondent pays any unpaid balance.  Such interest shall be payable to the Environmental Management Special Fund, and shall be payable to IDEM in the manner specified in Paragraph 5 above.

 

8.               In the event that any terms of this Agreed Order are found to be invalid, the remaining terms shall remain in full force and effect and shall be construed and enforced as if this Agreed Order did not contain the invalid terms.

 

9.               Respondent shall provide a copy of this Agreed Order, if in force, to any subsequent owners or successors before ownership rights are transferred.  Respondent shall ensure that all contractors, firms and other persons performing work under this Agreed Order comply with the terms of this Agreed Order.

 

10.           This Agreed Order is not and shall not be interpreted to be a permit or a modification of an existing permit.  This Agreed Order, and IDEM’s review or approval of any submittal made by Respondent pursuant to this Agreed Order, shall not in any way relieve Respondent of their obligation to comply with the requirements of their applicable permit or any applicable Federal or State law or regulation.

 

11.           Complainant does not, by its approval of this Agreed Order, warrant or aver in any manner that Respondent’s compliance with any aspect of this Agreed Order will result in compliance with the provisions of any permit, order, or any applicable Federal or State law or regulation.  Additionally, IDEM or anyone acting on its behalf shall not be held liable for any costs or penalties Respondent may incur as a result of Respondent’s efforts to comply with this Agreed Order.

 

12.           Nothing in this Agreed Order shall prevent or limit IDEM’s rights to obtain penalties or injunctive relief under any applicable Federal or State law or regulation, except that IDEM may not, and hereby waives its right to, seek additional civil penalties for the same violations specified in the NOV.

 

13.           Nothing in this Agreed Order shall prevent IDEM or anyone acting on its behalf from communicating with the EPA or any other agency or entity about any matters relating to this enforcement action.  IDEM or anyone acting on its behalf shall not be held liable for any costs or penalties Respondent may incur as a result of such communications with the EPA or any other agency or entity.

 

14.           This Agreed Order shall remain in effect until IDEM issues a Resolution of Case letter to Respondent.

 

 

TECHNICAL RECOMMENDATION:

 

RESPONDENT:

Department of Environmental Management

 

Knauf Insulation GmbH

 

 

 

By:

 

 

By:

 

 

Janusz Johnson, Chief

 

Printed:

 

 

Compliance and Enforcement Section 1

 

Title:

 

 

Office of Air Quality

 

 

 

Date:

 

 

Date:

 

 

 

 

 

 

 

 

 

 

 

COUNSEL FOR RESPONDENT:

 

 

 

 

 

 

 

 

 

By:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Date:

 

 

 

 

 

 

APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL

MANAGEMENT THIS

 

DAY OF

 

, 2014.

 

 

For the Commissioner

 

 

 

Signed on October 6, 2014

 

Keith Baugues, Assistant Commissioner

 

Office of Air Quality

 

Indiana Department of Environmental Management