STATE OF |
) |
|
BEFORE THE INDIANA
DEPARTMENT |
||
|
|||||
COMMISSIONER OF THE
DEPARTMENT Complainant, v. ALCOA INC., WARRICK
OPERATIONS, Respondent. |
) |
|
|||
AGREED ORDER
Complainant and Respondent
desire to settle and compromise this action without hearing or adjudication of
any issue of fact or law, and consent to the entry of the following Findings of
Fact and Order. Pursuant to IC 13-30-3-3, entry into the terms of this Agreed
Order does not constitute an admission of any violation contained herein. Respondent’s entry into this Agreed Order
shall not constitute a waiver of any defense, legal or equitable, which
Respondent may have in any future administrative or judicial proceeding, except
a proceeding to enforce this Agreed Order.
I.
FINDINGS OF FACT
1.
Complainant is
the Commissioner (“Complainant”) of the Indiana Department of Environmental
Management (“IDEM”), a department of the State of
2.
Respondent is Alcoa
Inc.—Warrick Operations (“Respondent”), which owns and operates a plant
producing aluminum coil, and discharging wastewater to the Ohio River with
National Pollutant Discharge Elimination System (“NPDES”) Permit No. IN0001155,
(the “Permit”) located on Highway 66, in
3.
IDEM has
jurisdiction over the parties and the subject matter of this action.
4.
Respondent
waives issuance of a Notice of Violation and to the settlement period of sixty
(60) days as provided for by IC 13-30-3-3.
5.
Pursuant to 327
IAC 5-2-8(1) and Part I.A.1 of the Permit, Respondent is required to comply
with all terms and conditions of its NPDES permit.
6.
On December 13,
2007, representatives of Respondent met with representatives of Complainant to
discuss the various self-reported deviations from Respondent’s NPDES permit and
actions it has taken to prevent those deviations from occurring in the future. The deviations that were discussed are
itemized as follows:
a. 2003
From
March 19 through April 9, and on April 18, sampling for pH and total residual
chlorine at Outfall 002 could not be conducted in a safe manner due to low flow
conditions. A total of 9 samples for
each parameter could not be collected.
b. 2004
During
the weeks of May 5 and May 29, a total of 3 BOD samples were not obtained due
to flooding of the Outfall 303 weir caused by heavy rainfall. Because of the potential for composite
samples to be invalidated by heavy rainfall, sampling schedules were adjusted
to accommodate for the potential of flooding of the outfall weir.
On August 26, a sample for total suspended solids
(TSS) at Outfall 303 measuring 47 parts per million (ppm) versus a permit limit
of 40 ppm was reported. The elevated TSS
measurement was attributed to a storm water event of 0.4” and an upset
clarifier at the wastewater treatment plant.
From September 16 through October 24, total residual
chlorine samples for Outfall 003 were not collected due to a communication
error with the laboratory. Permit
requirements for this parameter were to sample three times weekly (report only)
and monthly average (report only).
Approximately 6 weeks worth of sampling (e.g., 18 samples) over a
thirty-nine (39) day period were not collected.
On
December 25, a fifty gallon oil spill overwhelmed an oil/water separator due to
frigid conditions creating a small oil sheen at Outfall 006.
c. 2005
The
permit requires that the temperature measurements for Outfall 002 influent,
effluent, and mixed river temperatures are to be submitted by January 28th
of the following year. The temperature measurements for 2004 were submitted on
March 24, 2005.
Cyanide
samples have an analytical holding time of 14 days. A sample collected on March 7th
was not analyzed until 16 days after collection. Two samples, one collected on
March 8th and the other on March 17th were not analyzed until
15 days after collection.
On
April 22, a BOD5 sample was not measured until the 6th day after the
sample was collected.
d. 2006
On
February 20, as a result of an inversion that caused an upset of the fly ash
ponds, TSS at Outfall 103 was measured at 155 ppm, which then resulted in a
monthly average of 54.0 ppm. The permit
limits for TSS at outfall 103 are 100 ppm for a daily maximum and a monthly
average of 30 ppm. As a part of this Agreed
Order, there will be no assessed fine or stipulated penalty due to an “Upset
Condition” as defined in the NPDES permit.
On July 18,
what appeared to be an oil sheen of less than 20 gallons was observed
discharging from Outfall 002 (condenser cooling). A sample was taken of the effluent at the
outfall and chemical analysis confirmed that the oily material did not come
from Warrick’s operations (e.g., from the power plant equipment) based
upon the chemical constituents of the oily material.
e. 2007
On
March 18, as a result of another inversion that caused an upset of the fly ash
ponds, TSS at Outfall 103 was measured at 238 ppm, which then resulted in a
monthly average of 35.8 ppm. As stated
above, the permit limits for TSS at Outfall 103 are 100 ppm for a daily maximum
and a monthly average of 30 ppm. As a
part of this Agreed Order, there will be no assessed fine or stipulated penalty
due to an “Upset Condition” as defined in the NPDES permit.
On
March 28th, 85.49 pounds of aluminum was measured as being
discharged from Outfall 303 versus a permit limit of 73.36 pounds per day. This event was attributed to a storm water
event and high flow conditions.
On
April 30 and May 1, 2 and 8, the facility experienced an upset at wastewater
treatment plant 879 resulting in measured aluminum discharges of 90.4, 105.49,
125.93 and 83.71 lbs/day respectively at outfall 303. As a result of this, the monthly average
aluminum discharge for May was 37.14 lbs/day.
The permit limits for aluminum at outfall 303 are 73.36 lbs/day for a
daily maximum and 34.91 lbs/day for a monthly average. This event was caused by an increase in rate
of wastewater flow to the 879 wastewater treatment plant from a “squeegee” roll
from approximately 3-5 gpm to 20 gpm, thus overwhelming the treatment capacity
of the plant.
The
events described in a. through e. above are in violation of 327 IAC 5-2-8(1)
and Part I.A.1 of the Permit.
7. In
recognition of the settlement reached, Respondent waives any right to
administrative and judicial review of this Agreed Order.
II.
ORDER
1.
This Agreed
Order shall be effective (“Effective Date”) when it is approved by Complainant
or Complainant’s delegate, and has been received by Respondent. This Agreed Order shall have no force or
effect until the Effective Date.
2.
Respondent shall
comply with permit conditions listed in the findings above at issue.
3.
Within 30 days
of the Effective Date, Respondent shall develop and submit to IDEM for approval
a “Compliance Plan” which identifies actions that Respondent will take to
achieve and maintain compliance with its NPDES Permit, specifically including the
actions Respondent will take to:
a.
Address aluminum
limit exceedances by making capital improvements at the 879 wastewater
treatment to ensure compliance with aluminum limits at outfall 303.
b.
Address total
suspended solids upset conditions at outfall 103 through the installation of a
dry fly ash handling system.
The
Compliance Plan shall include an implementation and completion schedule,
including specific milestone dates.
4.
Upon
Respondent’s receipt of IDEM’s approval of the Compliance Plan, Respondent shall
have twelve months to implement the actions set forth in the Compliance
Plan. This twelve month period shall be
referred to as the Performance Period.
Following the Performance Period, Respondent shall be required to
demonstrate five consecutive months of compliance with the terms and conditions
of its NPDES Permit (Compliance Demonstration).
During the Performance Period, Respondent shall be subject to stipulated
penalties, as specified below, for violations of its NPDES Permit. In the event that Respondent fails to make
the Compliance Demonstration within seven months following the Performance
Period, Respondent shall, within sixty days of becoming aware that the
Compliance Demonstration cannot be achieved within seven months following the
Performance Period, develop and submit to IDEM, for approval, an “Additional
Action Plan” which identifies the additional actions that Respondent will take
to achieve and maintain compliance with its NPDES Permit. The Additional Action Plan, if required,
shall include an implementation and completion schedule, including specific
milestone dates.
5.
The plans
required by Paragraphs 3 and 4 above are subject to IDEM approval. In the event IDEM determines that any plan
submitted by Respondent is deficient or otherwise unacceptable, Respondent
shall revise and resubmit the plan to IDEM in accordance with IDEM’s notice.
After three submissions of such plan by Respondent, IDEM may modify and approve
any such plan and Respondent must implement the plan as modified by IDEM.
Respondent, upon receipt of written notification from IDEM, shall immediately
implement the approved plan and adhere to the milestone dates therein. The approved Compliance Plan and Additional
Action Plan shall be incorporated into the Agreed Order and shall be deemed an
enforceable part thereof. Unless
Complainant has agreed to extend a milestone, failure by Respondent to submit
any plan by the specified date, or to meet any of the milestones in the
approved plan may subject Respondent to stipulated penalties as described
below. Failure to achieve compliance at
the conclusion of work under an Additional Action Plan will subject Respondent
to additional enforcement action.
6. Beginning on the Effective Date and continuing until the
completion of the Compliance Plan provided for by Paragraph 3 above, Respondent
shall, at all times, operate its existing wastewater treatment facilities as
efficiently and effectively as possible, and shall be subject to stipulated
penalties for its failure to comply with permit limitations.
7.
All submittals
required by this Agreed Order, unless Respondent is notified otherwise in
writing by IDEM, shall be sent to:
Mark
Stanifer, Section Chief |
Indiana
Department of Environmental Management |
Office
of Enforcement – Mail Code 60-02 |
|
|
8.
Respondent is
assessed a civil penalty of Forty Three Thousand Two Hundred Dollars ($43,200). Said penalty amount shall be due and payable
to the Environmental Management Special Fund within thirty (30) days of the
Effective Date. In the event that the
civil penalty is not paid within thirty (30) days of the Effective Date,
Respondent shall pay interest on the unpaid balance at the rate established by
IC 24-4.6-1-101. The interest shall continue
to accrue until the civil penalty is paid in full.
9.
In the event the
terms and conditions of the following paragraphs are violated, Complainant may
assess and Respondent shall pay a stipulated penalty in the following amount:
Paragraph |
Violation |
Stipulated
Penalty |
3,
4, and 5 |
Failure
to submit any plan within the required time period. |
$500
per week late, or part thereof. |
4 |
Failure to comply with effluent limitations during
the Performance Period or the period of the Compliance Demonstration. |
$500 per violation. |
5 |
Failure to implement any approved plan. |
$500 per week late, or part thereof. |
4, 5 |
Any other NPDES violation. |
$500 per violation. |
10.
Stipulated
penalties shall be due and payable within thirty (30) days after Respondent
receives written notice that Complainant has determined a stipulated penalty is
due. Assessment and payment of
stipulated penalties shall not preclude Complainant from seeking any additional
relief against Respondent for violation of this Agreed Order. In lieu of any of the stipulated penalties
set out above, Complainant may seek any other remedies or sanctions available
by virtue of Respondent’s violation of this Agreed Order or Indiana law,
including, but not limited to, civil penalties pursuant to IC 13-30-4.
11.
Civil and stipulated
penalties are payable by check to the “Environmental Management Special Fund.” Checks shall include the Case Number of this
action and shall be mailed to:
Indiana
Department of Environmental Management |
Cashier
– Mail Code 50-10C |
|
|
12.
Force majeure, for purposes of this Agreed Order, is defined as any event arising
from causes totally beyond the control and without fault of Respondent that
delays or prevents the performance of any obligation under this Agreed Order
despite Respondent’s best efforts to fulfill the obligation. The requirement that Respondent exercise
“best efforts to fulfill the obligation” includes using best efforts to
anticipate any potential force majeure
event and best efforts to address the effects of any potential force majeure event (1) as it is
occurring and (2) following the potential force
majeure event, such that the delay is minimized to the greatest extent
possible. Force majeure does not include (1) changed business or economic
conditions; (2) financial inability to complete the work required by this
Agreed Order; or (3) increases in costs to perform the work.
Respondent
shall notify IDEM by calling the case manager within three (3) calendar days
and by writing no later than seven (7) calendar days after it has knowledge of
any event which Respondent contends is a force majeure. Such notification shall describe (1) the
anticipated length of the delay; (2) the cause or causes of the delay; (3) the
measures taken or to be taken by Respondent to minimize the delay; and (4) the
timetable by which these measures will be implemented. Respondent shall include with any notice all
available documentation supporting its claim that the delay was attributable to
a force majeure. Failure to materially comply
with the above requirements shall preclude Respondent from asserting any claim
of force majeure for that event. Respondent shall have the burden of
demonstrating that the event is a force majeure. The decision of whether an event is a force
majeure shall be made by IDEM in its reasonable discretion.
If
a delay is attributable to a force majeure, IDEM shall extend, in writing, the
time period for performance under this Agreed Order, by the amount of time that
is directly attributable to the event constituting the force majeure.
13.
This Agreed
Order shall apply to and be binding upon Respondent and its successors and
assigns. This Agreed Order shall jointly and severally apply to and be binding
upon Respondent and its successors and assigns.
Respondent’s signatories to this Agreed Order certify that they are
fully authorized to execute this Agreed Order and legally bind the party he/she/they
represent. No change in ownership,
corporate, or partnership status of Respondent shall in any way alter its
status or responsibilities under this Agreed Order.
14.
In the event
that any terms of this Agreed Order are found to be invalid, the remaining
terms shall remain in full force and effect and shall be construed and enforced
as if this Agreed Order did not contain the invalid terms.
15.
Respondent shall
provide a copy of this Agreed Order, if in force, to any subsequent owners or
successors before ownership rights are transferred. Respondent shall ensure that all contractors,
firms and other persons performing work under this Agreed Order comply with the
terms of this Agreed Order.
16.
This Agreed
Order is not and shall not be interpreted to be a permit or a modification of
an existing permit. This Agreed Order,
and IDEM’s review or approval of any submittal made by Respondent pursuant to
this Agreed Order, shall not in any way relieve Respondent of its obligation to
comply with the requirements of its applicable permit or any applicable Federal
or State law or regulation.
17.
Complainant does
not, by its approval of this Agreed Order, warrant or aver in any manner that
Respondent’s compliance with any aspect of this Agreed Order will result in
compliance with the provisions of any permit, order, or any applicable Federal
or State law or regulation.
Additionally, IDEM or anyone acting on its behalf shall not be held
liable for any costs or penalties Respondent may incur as a result of
Respondent’s efforts to comply with this Agreed Order.
18.
Nothing in this
Agreed Order shall prevent or limit IDEM’s rights to obtain penalties or
injunctive relief under any applicable Federal or State law or regulation,
except that IDEM may not, and hereby waives its right to, seek additional civil
penalties for the same violations specified in part I. 6. herein.
19.
Nothing in this
Agreed Order shall prevent IDEM [or anyone acting on its behalf] from
communicating with the EPA or any other agency or entity about any matters
relating to this enforcement action.
IDEM or anyone acting on its behalf shall not be held liable for any
costs or penalties Respondent may incur as a
result of such communications with the EPA or any other agency or entity.
20.
This Agreed
Order shall remain in effect until Respondent has complied with all terms and
conditions of Order Paragraph Nos. 3 through 11 and IDEM issues a Resolution of
Case letter.
TECHNICAL RECOMMENDATION: |
|
RESPONDENT: |
|||||
Department of Environmental Management |
|
|
|||||
|
|
|
|||||
By: |
|
|
By: |
|
|||
|
Mark W. Stanifer, Chief |
|
Printed: |
|
|||
|
Water Enforcement Section |
|
Title: |
|
|||
|
Office of Enforcement |
|
|
|
|||
Date: |
|
|
Date: |
|
|||
|
|
|
|
|
|||
|
|
|
|||||
COUNSEL FOR COMPLAINANT: |
|
COUNSEL FOR RESPONDENT: |
|||||
For the Department of Environmental Management |
|
|
|||||
|
|
|
|||||
By: |
|
|
By: |
|
|||
|
|
|
|
|
|||
|
Deputy Attorney General |
|
|
|
|||
Date: |
|
|
Date: |
|
|||
|
|
|
|
|
|||
APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF
ENVIRONMENTAL |
|||||||
MANAGEMENT THIS |
|
DAY
OF |
|
, 2008. |
|||
|
|||||||
|
For the Commissioner: |
||||||
|
|
||||||
|
Signed on July 8, 2008 |
||||||
|
Robert B. Keene |
||||||
|
Assistant Commissioner |
||||||
|
Office of Legal Counsel and Enforcement |
||||||