STATE OF INDIANA

COUNTY OF MARION

)
)
)


SS:

BEFORE THE INDIANA DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT

 

COMMISSIONER OF THE DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT,

Complainant,

v.

THYSSENKRUPP WAUPACA, INC.,

Respondent.

)
)
)
)
)
)
)
)
)
)






Case No. 2005-14739-A




 

 

AGREED ORDER

 

Complainant and Respondent desire to settle and compromise this action without hearing or adjudication of any issue of fact or law, and consent to the entry of the following Findings of Fact and Order.  Pursuant to IC 13-30-3-3, entry into the terms of this Agreed Order does not constitute an admission of any violation contained herein.  Respondent's entry into this Agreed Order shall not constitute a waiver of any defense, legal or equitable, which Respondent may have in any future administrative or judicial proceeding, except a proceeding to enforce this order.

 

I.  FINDINGS OF FACT

 

1.                  Complainant is the Commissioner (“Complainant”) of the Indiana Department of Environmental Management (“IDEM”), a department of the State of Indiana created by Indiana Code (“IC”) 13-13-1-1.

 

2.                  Respondent is ThyssenKrupp Waupaca, Inc. (“Respondent”), which owns and operates the stationary gray and ductile iron foundry with Plant ID No. 123-00019, located at 9856 State Highway 66, in Tell City, Perry County, Indiana (“Site”).

 

3.                  IDEM has jurisdiction over the parties and the subject matter of this action.

 

4.                  Pursuant to IC 13-30-3-3, IDEM issued a Notice of Violation on May 17, 2006 via Certified Mail to Gary Thoe, President of ThyssenKrupp Waupaca, Inc. and CSC, Registered Agent.

 

5.                  During an investigation conducted by representatives of IDEM, including compliance testing performed at the Site on December 14-16, 2004, the following violations were found:

 

a.   Pursuant to Title 5 Permit T123-9234-00019, condition D.2.1(a), particulate matter ("PM") emissions from stack S07 shall be limited to 0.005 grains per dry standard cubic foot (gr/dscf) and 7.8 lbs/hr.

 

During compliance testing conducted at the Site on December 16, 2004, PM emissions from stack S07 measured 0.0072 gr/dscf and 10.437 lbs/hr, in violation of Permit T123-9234-00019, condition D.2.1(a).

 

b.      Pursuant to Title 5 Permit T123-9234-00019, condition D.2.2, lead emissions from stack S07 shall be limited to 0.0019 lbs/hr.

During compliance testing conducted at the Site on
December 16, 2004, lead emissions from stack S07 measured 0.0041 lbs/hr, in violation of Permit T123-9234-00019, condition D.2.2.

 

c.      Pursuant to Title 5 Permit T123-9234-00019, condition D.2.3, Beryllium emissions from stack S07 shall be limited to 0.000017 lbs/hr.

During compliance testing conducted at the Site on
December 16, 2004, Beryllium emissions from stack S07 measured 0.000029 lbs/hr, in violation of Permit T123-9234-00019, condition D.2.3.

 

d.      Pursuant to Title 5 Permit T123-9234-00019, condition D.1.5, VOC emissions from stack S09 shall be limited to 3.2 lbs/hr. and 0.02 lbs/ton.

During compliance testing conducted at the Site on
December 17, 2004, VOC emissions from stack S09 measured 10.86 lbs/hr. and 0.073 lbs/ton, in violation of Permit T123-9234-00019, condition D.1.5.

 

e.      Pursuant to Title 5 Permit T123-9234-00019, condition D.3.2, lead emissions from stack S16 shall be limited to 0.005 lbs/hr.

During compliance testing conducted at the Site on
December 14, 2004, lead emissions from stack S16 measured 0.0062 lbs/hr, in violation of Permit T123-9234-00019, condition D.3.2.

 

6.                  Compliance testing was performed at the Site on May 10 and 11, 2005.  Stack S07 tested in compliance for PM, Pb and Be at 45% of the maximum permitted capacity.  However, compliance during operations greater than 45% cannot be determined.  Stack S09 tested in compliance for VOC.  Stack S16 tested in compliance for Pb at 22% of the maximum permitted capacity.  However, compliance during operations greater than 22% cannot be determined.

 

7.                  In recognition of the settlement reached, Respondent waives any right to administrative and judicial review of this Agreed Order.

 

II.  ORDER

 

1.                  This Agreed Order shall be effective (“Effective Date”) when it is approved by Complainant or Complainant’s delegate, and has been received by Respondent.  This Agreed Order shall have no force or effect until the Effective Date.

 

2.                  Respondent shall comply with the most recent effective permit.

 

3.                  Respondent shall use only 18-ounce duo-density bags in the Stack S07 baghouse unless or until such time that compliance with PM, Pb and Be limits can be demonstrated during compliance testing conducted pursuant to 326 IAC 3-6 using another type of bag.  Respondent shall indicate the change of bag type for testing purposes on the test protocol.  Bags may not be changed within twenty-one days prior to the test date.

 

4.                  Respondent shall install and operate a bag leak detection system on stack S07 in accordance with the requirements of 40 CFR Part 63.7710 within sixty (60) days of the Effective Date of this Order.

 

5.                  Respondent shall not operate the emission units exhausting to S07 at a rate greater than 70 tons per hour until testing is performed in accordance with the provisions of 326 IAC 3-6 demonstrating compliance at a greater production rate.

 

6.                  Respondent shall not operate the emission units exhausting to S16 at a rate greater than 50 tons per hour until testing is performed in accordance with the provisions of 326 IAC 3-6 demonstrating compliance at a greater production rate.

 

7.                  Respondent shall test for opacity, PM, Pb and Be for all facilities exhausting to stack S07 and opacity, PM, Pb and Be for all facilities exhausting to stack S16 within sixty (60) days of the Effective Date of this Order using methods as approved by the Commissioner to demonstrate compliance with the total stack limits listed in Condition D.2.1, D.2.2, D.2.3 and D.3.2 of permit T123-9234-00019.  All facilities exhausting to stack S07 and S16 shall be in operation during the stack tests in order for the tests to be considered valid.  All testing shall be performed according to the provisions of 326 IAC 3-6 (Source Sampling Procedures), utilizing any applicable procedures and analysis methods specified in 40 CFR 51, 40 CFR 60, 40 CFR 61, 40 CFR 63, 40 CFR 75, or other procedures approved by IDEM, OAQ.  This Order does not require Respondent to meet the requirement of 326 IAC 3-6-3(b)(1) for testing required in this condition since the results will provide the basis for a permit modification application to de-rate production.

 

Test protocols shall be submitted to:

 

Indiana Department of Environmental Management

Compliance Data Section, Office of Air Quality

Mail Code 61-50

100 North Senate Avenue

Indianapolis, Indiana  46204-2251

 

no later than thirty-five (35) days prior to the intended test date.

 

8.                  If Respondent fails to demonstrate compliance with the emission limits during the testing required in paragraph 7, the Respondent shall perform a re-test within ninety (90) days of the failed test and will be subject to additional civil penalties.

 

9.                  If Respondent demonstrates compliance with the emission limits during the testing required in paragraph 7, the Respondent shall submit a permit modification application within ninety (90) days of the Effective Date of this Order to include the following requirements:

a.                  De-rate the maximum production of the operation of the facilities exhausting to Stacks S07 and S16 to the level at which compliance with the PM, Pb and Be limits were demonstrated during the testing required in paragraph 7 of this Order.

b.                  Install and operate a bag leak detection system on stack S07 in accordance with the requirements of 40 CFR Part 63.7710.

c.                  Use only 18-ounce duo-density bags in the Stack S07 baghouse unless or until such time that compliance with PM, Pb and Be limits can be demonstrated during compliance testing conducted pursuant to 326 IAC 3-6 using another type of bag.  Permittee shall indicate the change of bag type for testing purposes on the test protocol.  Bags may not be changed within twenty-one days prior to the test date.

 

The permit modification application shall include a copy of this Order and shall be submitted to:

 

IDEM Air Permits Administration

Attn: Incoming Application

100 North Senate Avenue

Indianapolis, IN  46204-2251

 

10.             Respondent shall test for opacity, PM, Pb and Be for all facilities exhausting to stack S07 and opacity, PM, Pb and Be for all facilities exhausting to stack S16 using methods as approved by the Commissioner, between January 1, 2009 and March 31, 2009 to demonstrate compliance with the total stack limits listed in Condition D.2.1, D.2.2, D.2.3 and D.3.2 of permit T123-9234-00019.  All facilities exhausting to stack S07 and S16 shall be in operation during the stack tests in order for the tests to be considered valid.  All testing shall be performed according to the provisions of 326 IAC 3-6 (Source Sampling Procedures), utilizing any applicable procedures and analysis methods specified in 40 CFR 51, 40 CFR 60, 40 CFR 61, 40 CFR 63, 40 CFR 75, or other procedures approved by IDEM, OAQ.

 

Test protocols shall be submitted to:

 

Indiana Department of Environmental Management

Compliance Data Section, Office of Air Quality

Mail Code 61-50

100 North Senate Avenue

Indianapolis, Indiana  46204-2251

 

no later than thirty-five (35) days prior to the intended test date.

 

11.             Copies of all submittals required by this Agreed Order, unless Respondent is notified otherwise in writing by IDEM, shall be sent to:

 

Lynne Sullivan, Enforcement Case Manager

Office of Enforcement – Mail Code 60-02

Indiana Department of Environmental Management

100 North Senate Avenue

Indianapolis, IN 46204-2251

 

12.             Respondent is assessed a civil penalty of Ninety Thousand Dollars ($90,000).  Said penalty amount shall be due and payable to the Environmental Management Special Fund within thirty (30) days of the Effective Date.  In the event that the civil penalty is not paid within thirty (30) days of the Effective Date, Respondent shall pay interest on the unpaid balance at the rate established by IC 24-4.6-1-101.  The interest shall continue to accrue until the civil penalty is paid in full.

 

13.             In the event the terms and conditions of the following paragraphs are violated, Complainant may assess and Respondent shall pay a stipulated penalty in the following amount:

 

Paragraph

Violation

Stipulated Penalty

3

Failure to use 18-oz duo density bags

$1000 per day

4

Failure to install and operate bag leak detection system on S07 within 60 days

$1000 per day

5

Exceeds production rate for S07

$1000 per day

6

Exceeds production rate for S16

$1000 per day

7

Failure to test S07 and S16 within 60 days

$1000 per week

8

Failure to re-test within 90 days (if necessary)

$1000 per week

9

Late permit modification application

$1000 per week

10

Untimely 2009 testing of S07 and S16

$1000 per week

11

Late copies of submittals to Enforcement

$500 per week

 

14.             Stipulated penalties shall be due and payable within thirty (30) days after Respondent receives written notice that Complainant has determined a stipulated penalty is due.  Assessment and payment of stipulated penalties shall not preclude Complainant from seeking any additional relief against Respondent for violation of this Agreed Order.  In lieu of any of the stipulated penalties set out above, Complainant may seek any other remedies or sanctions available by virtue of Respondent’s violation of this Agreed Order or Indiana law, including, but not limited to, civil penalties pursuant to IC 13-30-4.

 

15.             Civil and stipulated penalties are payable by check to the “Environmental Management Special Fund.”  Checks shall include the Case Number of this action and shall be mailed to:

 

Indiana Department of Environmental Management

Cashier – Mail Code 50-10C

100 North Senate Avenue

Indianapolis, IN 46204-2251

 

16.             “Force Majeure”, for purposes of this Agreed Order, is defined as any event arising from causes totally beyond the control and without fault of the Respondent that delays or prevents the performance of any obligation under this Agreed Order despite Respondent’s best efforts to fulfill the obligation.  The requirement that the Respondent exercise “best efforts to fulfill the obligation” includes using best efforts to anticipate any potential force majeure event and best efforts to address the effects of any potential force majeure event (1) as it is occurring and (2) following the potential force majeure event, such that the delay is minimized to the greatest extent possible.  “Force Majeure” does not include changed business or economic conditions, financial inability to complete the work required by this Agreed Order, or increases in costs to perform the work.

 

The Respondent shall notify IDEM by calling the case manager within three (3) calendar days and by writing no later than seven (7) calendar days after it has knowledge of any event which the Respondent contends is a force majeure.  Such notification shall describe the anticipated length of the delay, the cause or causes of the delay, the measures taken or to be taken by the Respondent to minimize the delay, and the timetable by which these measures will be implemented.  The Respondent shall include with any notice all available documentation supporting its claim that the delay was attributable to a force majeure.  Failure to comply with the above requirements shall preclude Respondent from asserting any claim of force majeure for that event.  The Respondent shall have the burden of demonstrating that the event is a force majeure.  The decision of whether an event is a force majeure shall be made by IDEM.

 

If a delay is attributable to a force majeure, IDEM shall extend, in writing, the time period for performance under this Agreed Order, by the amount of time that is directly attributable to the event constituting the force majeure.

 

17.             This Agreed Order shall apply to and be binding upon Respondent and its successors and assigns.  Respondent’s signatories to this Agreed Order certify that they are fully authorized to execute this Agreed Order and legally bind the party they represent.  No change in ownership, corporate, or partnership status of Respondent shall in any way alter its status or responsibilities under this Agreed Order.

 

18.             In the event that any terms of this Agreed Order are found to be invalid, the remaining terms shall remain in full force and effect and shall be construed and enforced as if this Agreed Order did not contain the invalid terms.

 

19.             The Respondent shall provide a copy of this Agreed Order, if in force, to any subsequent owners or successors before ownership rights are transferred.  Respondent shall ensure that all contractors, firms and other persons performing work under this Agreed Order comply with the terms of this Agreed Order.

 

20.             This Agreed Order is not and shall not be interpreted to be a permit or a modification of an existing permit.  This Agreed Order, and IDEM’s review or approval of any submittal made by Respondent pursuant to this Agreed Order, shall not in any way relieve Respondent of its obligation to comply with the requirements of its applicable permit or any applicable Federal or State law or regulation.

 

21.             Complainant does not, by its approval of this Agreed Order, warrant or aver in any manner that Respondent’s compliance with any aspect of this Agreed Order will result in compliance with the provisions of any permit, order, or any applicable Federal or State law or regulation.  Additionally, IDEM or anyone acting on its behalf shall not be held liable for any costs or penalties Respondent may incur as a result of Respondent’s efforts to comply with this Agreed Order.

 

22.             Nothing in this Agreed Order shall prevent or limit IDEM’s rights to obtain penalties or injunctive relief under any applicable Federal or State law or regulation, except that IDEM may not, and hereby waives its right to, seek additional civil penalties for the same violations specified in the NOV.

 

23.             Nothing in this Agreed Order shall prevent IDEM or anyone acting on its behalf from communicating with the EPA or any other agency or entity about any matters relating to this enforcement action.  IDEM or anyone acting on its behalf shall not be held liable for any costs or penalties Respondent may incur as a result of such communications with the EPA or any other agency or entity.

 

24.             This Agreed Order shall remain in effect until the Respondent’s Title 5 renewal permit and permit modifications required by this Order are issued or for a period of five (5) years after the Effective Date of the Agreed Order, whichever is earlier.

 

 

 

TECHNICAL RECOMMENDATION:

RESPONDENT:

Department of Environmental Management

ThyssenKrupp Waupaca, Inc.

 

 

By: _________________________

By:  _________________________

 

Craig Henry

Chief, Air Section

 

 

Office of Enforcement

Printed: ______________________

 

 

 

Title: ________________________

 

 

Date: __________________

Date: _______________________

 

 

 

 

COUNSEL FOR COMPLAINANT:

COUNSEL FOR RESPONDENT:

For the Department of Environmental Management

 

 

 

By: ______________

By: ________________________

 

Deputy Attorney General

 

 

 

Date: _______________________

Date: ______________________

 

APPROVED AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL

MANAGEMENT THIS

______

DAY OF

________________________

, 200

___

.

 

 

For the Commissioner:

 

 

 

Signed June 26, 2007

 

Robert B. Keene

 

Assistant Commissioner

 

Office of Legal Counsel and Enforcement