Permit Type & Subtype Statutory Deadline Public Notice Proposed to
U.S. EPA
Base Application
Fees
Title V Program
New Source Minor PSD 120 days Yes Yes $4,375
New Source Major PSD 270 days Yes Yes $7,500
Significant Source Modification Minor PSD 120 days Yes No $4,375
Significant Source Modification Major PSD 270 days Yes No $7,500
Minor Source Modification 45 days No No $625
Significant Permit Modification 270 days Yes Yes none
Minor Permit Modification 90 days Yes Yes none
Administrative Amendment 60 days No No none
Title V EUSGU Notification NA No No none
Renewal 270 days Yes Yes none
Renewal with New Equipment Minor PSD 120 days Yes Yes $4,375
Renewal with New Equipment Major PSD 270 days Yes Yes $7,500
Title V Relocation 30 days No No none
Interim NA No No $625
FESOP Program
New Source FESOP Minor PSD 120 days Yes No $4,375
New Source FESOP Major PSD 270 days Yes Yes $7,500
Significant Permit Revision Minor PSD 120 days Yes No $4,375
Significant Permit Revision Major PSD 270 days Yes Yes $7,500
Minor Permit Revision 45 days No No $625
Administrative Amendment 60 days No No none
General Permit 120 days No No $625
Renewal 270 days Yes No none
Renewal with New Equipment 120 days Yes No $4,375
FESOP Relocation 30 days No No none
Interim NA No No $625
MSOP Program
MSOP NA Yes No $100
New Construction MSOP Minor PSD 120 days Yes No $3,500
New Construction MSOP Major PSD 270 days Yes Yes $6,000
Significant Permit Revision Minor PSD 120 days Yes No $3,500
Significant Permit Revision Major PSD 270 days Yes Yes $6,000
Minor Permit Revision 45 days No No $600
Notice-Only Change 30 days No No none
Renewal NA Yes No $100
Renewal with New Equipment 120 days Yes No $3,500
MSOP Relocation 30 days No No $100
Interim NA No No $500
Registration/Exemption
Registration 60 days No No $600
Registration Revision 45 days No No $100
Registration Notice-Only Change 30 days No No none
Exemption 60 days No No $100
SSOA Program
SSOA 60 days No No $625
SSOA New Source Review 120 days Yes No $4,375
SSOA Relocation 30 days No No $125
Acid Rain Program
Acid Rain Permit NA Yes Yes none
Acid Rain Modification NA Yes Yes none
Acid Rain Administrative Amendment NA No No none
Acid Rain Renewal NA Yes Yes none
Transition *
From Title V to FESOP 120 days Yes No $1,250
From Title V to SSOA 90 days No No $625
From FESOP to TV 120 days or 15 days after EPA review ends, whichever is later Yes Yes None
From FESOP to SSOA 60 days No No $625
All other transitions Use the information for the permit type/subtype being transitioned to.
Other Approvals
Revocation - any Type NA No No none
Permit-by-Rule NA No No none
Other Application Fees
TV/FESOP/SSOA All Other Approvals
Public hearing $625 $500
For each NSPS Review $625 $500
For each NESHAP Review $625 $500
For each 326 IAC 8-1-6 BACT Review $750 $600
PSD BACT or LAER Review
2 to 5 review Analyses $3,750 $3,000
6 to 10 Review Analyses $7,500 $6,000
11 or more Review Analyses $12,500 $10,000
Air Quality Impact Study Review
If applicant does analysis $4,375 $3,500
Per pollutant If OAQ does analysis $7,500 $6,000
PAL
Fee per ton of allowable emissions per PAL pollutant $50 $40
Maximum combined for all PAL pollutants $50,000 $40,000

* A transition is a move from one permit type to another, based solely on a Permittee's choosing. A transition does not include physical and operational change, modification, or new construction. If a Permittee plans physical and operational change, modification, or new construction that requires a different level of permit, IDEM will issue a New Source Review/Construction Permit of the new Permit level. The deadline, Public Notice, proposal to U.S. EPA, and base fee are all determined by the New Source Review/Construction Permit.