Note: This message is displayed if (1) your browser is not standards-compliant or (2) you have you disabled CSS. Read our Policies for more information.
The submittal of Notice of Intent (NOI) Form (State Form 47487) is required for all projects meeting the applicability requirements of 327 IAC 15-5 regardless of whether they are within or outside a designated MS4 entity. IDEM does not delegate their authority to administer Rule 5 to an MS4, but does recognize the local permitting process and plan review of the MS4 entities as a qualifying local program.
The Notice of Intent (NOI) Form - State Form 47487 is now available on the IDEM Forms page.
Note: Always verify with the web site to ensure that you are using the most current form.
A Notice of Intent (NOI) must be submitted a minimum of forty eight (48) hours prior to initiation of land disturbing activities to meet the requirements of Rule 5. MS4s may have additional requirements that must be met prior to the submittal of the NOI. It is the responsibility of the project site owner to understand and meet these local requirements.
A separate NOI letter is required for each submitted Construction Plan, and the project site acreage identified in the Construction Plan must directly correspond to the acreage figures provided in the NOI submittal.
An NOI Form (State Form 47487) form (available on the IDEM Forms page) has been developed for projects meeting the applicability requirements of Rule 5. This form must be completely filled out and must include the following attachments:
To successfully aid in completing the Notice of Intent (NOI), the following guidance for Completing the Notice of Intent has been developed.
The original NOI must be submitted to the Indiana Department of Environmental Management (IDEM). The completed form and all attachments should be sent to the following address:
Indiana Department of Environmental Management
Attention OWQ Rule 5
Cashiers Office
100 North Senate Avenue
MC 50-10C
Indianapolis, IN 46204
A copy of the NOI letter should also be submitted to the plan review authority. The plan review authority will either be the SWCD or a local MS4.
For more information regarding the NOI submittal process, please contact the IDEM Permits Coordinator.