Skip to content

Indiana Department of Transportation

< Back | Agency Home | Submit Events >

Search events. View events.
  Transportation, Indiana Department of Submit Events
Welcome to the IN.gov Calendar. Please use the Help button to the right for any assistance while using the Calendar.
Click for help in using calendar displays. Print the contents of the current screen.

Advanced Search (New Search)
  From:
  To:

 

 

 


Submit
Entry Details
Notify me if this event changes.Add this event to my personal calendar.Email this entry to a friend.
Go Back
[INDOT]
Start Date: 5/17/2013Start Time: 8:00 PM
End Date: 5/18/2013End Time: 5:00 AM
This event recurs on a custom schedule.   Click here to see the series dates.
Entry Description

Contractors Removing State Road 37 Flyover
Expect Overnight Lane Restrictions on Interstate 69

FISHERS, Ind. – Contractors for the Indiana Department of Transportation (INDOT) plan to continue removal this week of the former northbound I-69 Exit 205 flyover bridge to State Road 37.

Motorists should expect single lane restrictions on both directions of I-69 as work to remove the overhead structure resumes Tuesday, May 14. The overnight lane restrictions will begin at 8:00 p.m. and are expected to end by 5 a.m., repeating each night through Friday night (May 17).  The work is weather dependent and schedules are subject to change.

The southbound I-69 exit to 116th Street is expected to close in early June for no more than 90 days. The closure will allow contractors to expedite construction of the new southbound configuration. An exact date for this closure will be announced as soon as possible. The official signed detour will direct traffic to the 96th Street interchange and return north to 116th Street.

Southbound S.R. 37 is restricted to a single lane between 126th Street and I-69 as contractors construct a new bridge that will carry southbound S.R. 37 over southbound I-69 traffic exiting to 116th Street, intended to eliminate weaving traffic patterns and improve traffic flow. The restriction is expected to continue until the new bridge opens later this summer.

Milestone Contractors, the state’s contractor for the $18 million interchange improvement project at Exit 205, expects to complete all improvements to the northbound side of the interchange this spring. Complete the southbound side of the interchange by the end of this year.  A second Operation Indy Commute – I-69 contract, adding travel lanes to I-69 between 116th Street and I-465, is also expected to be complete by the end of this year.

For more information about Operation Indy Commute – I-69, and to sign up to receive updates throughout the project, visit www.IndyCommute.indot.in.gov. For construction updates, photos and more via social media, “like” the Indiana Department of Transportation:  East Central Facebook page and follow @INDOT_ECentral on Twitter.

Default
Entry Type:
Press Release
Entry Category:
  • Alerts and Notification
  • IN.gov Category:
  • Residents
  • Visiting & Playing
  • Agency Name
    Transportation, Indiana Department of

    Calendar software powered by Active Data Calendar   
    Select item(s) to Search






    Select item(s) to Search
    Select item(s) to Search

    Select item(s) to Search