Skip to content

Indiana Department of Transportation

< Back | Agency Home | Submit Events >

Search events. View events.
 

Transportation, Indiana Department of

Submit Events

Welcome to the IN.gov Calendar. Please use the Help button to the right for any assistance while using the Calendar.

Click for help in using calendar displays. Print the contents of the current screen.

Advanced Search

(New Search)
  From:
  To:

 

 

 


Submit
Entry Details
Notify me if this event changes.Add this event to my personal calendar.Email this entry to a friend.
Go Back
[INDOT] 116th Street Loop Ramp Closure Scheduled, I-69 Lane Restrictions
Start Date: 10/4/2012Start Time: 10:00 PM
End Date: 10/5/2012End Time: 5:00 AM
This event recurs until 10/5/2012.   Click here to see the series dates.
Entry Description

14 Day Closure of 116th Street Loop Ramp
To Northbound I-69 and SR 37
Scheduled for October 15

FISHERS, Ind. – Indiana Department of Transportation (INDOT) contractors have scheduled the expected 14-day closure of the 116th Street loop ramp to northbound I-69 and State Road 37. 

Milestone Contractors, the state’s contractor for the $18 million interchange improvement project, plans to close the looping northbound entrance ramp from 116th Street for up to 14 days on or after Monday, October 15.  Motorists will not be restricted from exiting northbound I-69 to 116th Street or State Road 37.  The official signed detour for the ramp closure will follow I-69 south to the 96th Street interchange (Exit 203) and return to I-69 northbound.  Sometime after the ramp reopens, access from 116th Street to northbound I-69 is expected to be restricted for up to 60 additional days.

Milestone plans additional overnight lane restrictions on I-69 at Exit 205 tonight (Thursday, Oct. 4) and Friday.

Milestone will restrict the right lane of northbound I-69 and the left lane of the Exit 205 collector-distributor beginning at 10 p.m. both nights.  Some temporary stoppages of traffic will be necessary after midnight as Milestone relocates two sign trusses over the highway.  The lane restrictions are expected to end before 5 a.m. Friday and Saturday mornings.  The exit ramp to 116th Street and State Road 37 will remain open.

Construction on the northbound side of the interchange started this spring.  I-69 is currently restricted to two lanes north of Exit 205 as a new two-lane flyover ramp to State Road 37 is constructed.  Milestone is expected to complete the northbound improvements this year and finish southbound work by the end of 2013.

For details about the Operation Indy Commute – I-69 project and for information on how to sign up for the project enewsletter, visit indycommute.indot.in.gov.  For construction updates, photos and more, go to Indiana Department of Transportation:  East Central on Facebook and like our page or follow @INDOT_ECentral on Twitter.

Default
Entry Type:
Press Release
Entry Category:
  • Alerts and Notification
  • IN.gov Category:
  • Residents
  • Visiting & Playing
  • Agency Name
    Transportation, Indiana Department of

    Calendar Software powered by Active Calendar and Active Data Calendar   
    Select item(s) to Search






    Select item(s) to Search
    Select item(s) to Search

    Select item(s) to Search